05th Change Order 04/15/2020 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 005 Plantation Key Courthouse & Detention Center INITIATION DATE: April 15, 2020 COMMENCEMENT DATE August 5, 2019 CONSTRUCTION DAYS: 913 TO CONTRACTOR APPROVED DELAY DAYS: 0 Biltmore Construction Company 1055 Ponce Do Leon Blvd Belleair, FL 33756 The original (Contract Sum) (Guaranteed Maximum Price) $ 32,818,441.14 Net change by previously authorized by Amendments $ 202,086.00 Net change by previously authorized Change Orders $ (1,985,286.42) The (Contract Sum)(Guaranteed Maximum Price) prior to this Change order was $ 31,035,240.72 The (Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased) (unchanged) by this Change Order by $ (213,360.00) The new(Contract Sum) (Guaranteed Maximum Price) including this Change Order is $ 30,821,880.72 The Contract Time will be (increased) (decreased) (unchanged) by 0 Days The date of Substantial Completion as of the date of this Change Order is February 3, 2022 Detailed description of change order and iustification:1 i Monroe County wishes to purchase the HVAC directly from the supplier to take advantage of the County's tax free status. The GMP will be reduced and the funds will then be used to procure the same materials via a purchase order from OMB (attached) This Change Order is: -0.65% of the original contract price Not valid until signed bV Owner, Architect (if applicable), and Contractor ARCH ITECTIDESIGNER: 4/27/2020 Date CONTRACTOR: C -/- 2- Date Digitally signed by Cary Knight Cy Knight ate: 020.05.06 19:40:57 -04'0DIRECTOR OF PROJECT MANAGEMENT: Digitally signed by Kevin G.Wilson,P.E. Date DN:cn=Kevin G.Wilson,P.E.,o=Monroe County,FL(the Florida Keys,ou, email=wilson-kevin@monroecounty- ! fl.gov,c=U 5 COUNTYIASSISTANT ADMINISTRATOR Date:2020.05.11 13:57:49-04'00' Date CHANGE ORDER LEDGER PLANTATION KEY COURTHOUSE & DETENTION CENTER r 4/14/2020 �. Total GMP Change bV Co 38 Days $ (2,198,646.42) 01 ODP Generators 0 $ (684,007.00) 02 ODP PKG Lighting 0 $ (986,135.21) 03 ODP Gypsum 0 $ (235,144,21) 04 ODP Concrete 0 $ (8.0,000.00) 05 ODP HVAC 0 $ (213,360.00) 06 Site Survey Delay 38 $ - MONROF COUNTY PURCHASE ORDER NO. 00062116 BOARD OF COUNTY COMMISSIONERS 1100 Simonton Street, Suite 2-213 PAGE NO. I Key West, FL 33040 SALES TAX EXEMPT NO.: 85-8013825294C-7 PDF COPY V F- 93782 PHONE: 305-406-9758-1 H F M C PROJECT MANAGEMENT E INTEGRATED COOLING SOLUTIONS, LLC 1100 SIMONTON ST, 2ND FL RM 2-215 ND 10405 NW 37TH TERRACE P KEY WEST, FL 33040 DORM, FL 33178 ORDER DATE:04/01`20 BUYER: B ERICKSON REQ. NO•: 00056721 REQ.DATE: TERMS: NET 3 0 DAYS F.Q.B.: DESC.: ITEM# QUANTITY UOM DESCRIPTION UNIT PRICE EXTENSION 01 1 . 00 LOT OWNER DIRECT PURCHASE 213360 . 0000 213 , 360 . 0 HVAC PACKAGE FOR THE NEW PLANTATION KEY COURTHOUSE AND DENTENTION CENTER 02 1 . 00 LOT SHIP TO ADDRESS . 0000 . 0 OFF-SITE STORAGE ADDRESS: 1315 NW 98TH COURT, UNIT 15 DORAL, FL 33172 ITEM# COST CENTER ACCOUNT PROJECT PROJECTACCT AMOUNT PAGE TOTAL $ 213 , 360 . 00 01 26008 560620 CP1503 530340 213,360.00 TOTAL $ 213, 360 . 00 02 26008 560620 CP1503 530340 . 00 PARTIAL PAYMENT FINAL PAYMENT INVOICE NO. INVOICE AMOUNT PAYMENT DESC. PAYMENT APPROVAL PURCHASING AGENT