21st Change Order 10/23/2006 MONROE COUNTY / ENGINEERING /FACILITIES DEVELOPMENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 21 Freeman Justice Center Jackson Square INITIATION DATE: Various Key West, FL CONTRACT DATE: June 16, 2004 TO CONTRACTOR: The Tower Groin,Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price) ........................................ $13,804,000.00 Net change by previously authorized Change Orders ................................................ $1,147,437.32 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change Order was ......... $14,951,437.32 The (Contract Sum) (Guaranteed Maximum Price)will be Qncreased) (decreased) (unchanged) by this Change Order.................. $ 26,085.72 The new(Contract Sum) (Guaranteed Maximum Price) including this Change Order is ... $14,977,523.04 The Contract Time will be (increased) (decreased) (unchanged) by .................. ( ) N/A The date of Substantial Completion as of the date of this Change Order is ..................January 25, 2007 Detailed description of change order and justification: Chance Order No. 21 is in response to Change Order Reauests(COR) #7-R1. 45-R1,49 50, and 51, summarised as follows: COR#7 R 1-modify site llahtlna to facilitate pedestrian and vehicle traffic $2,710.05 COR#45-R1-credit for door hardware at the Sheriff holding cells (4,507,04) COR#49.3-way control yalyes for the chilled waW system in lieu of 2-way valves &317.40 COR#50-additional fthfing for artwork in MW,gW 511.19 51-M24ific to the a d 3rd flo"lobby lighting 19 054.12 _TOTAL $19.555.91 for items 50, and 51, will be funded by the 16m Circuit Court This Chanae Osier is .19%f the odainal contract amount Not valid until sianed by Owner.Construction Manager and Contractor ARCHITECT: N/ Date CONTRACTOR: 4 cj;1'?� ICa� The Tower Group Date DIRECTOR, FACILITIES DEVELOPMENT: "Oct Jery B Date COUNTY ENGINEER: U David S. Koppel, P. Date COUNTY ADMINISTRATOR !0 2 3 v Thomas Willi/De ' Frederick-Deputy Date FREEMAN JUSTICE CENTER CHANGE ORDER NO. 21 ANALYSIS Change Order Request# Descriotion Amount 7-R1 Modify the lighting on site to facilitate pedestrian and vehicle traffic along Fleming Street and Thomas Street: • Credit for changing 18 pole mounted light fixtures to 8 pole Mount fixtures, 8 wall mounted light fixtures, and 4 up-lights $(3,434.00) • 4 additional wall mounted light fixtures 6,144.65 • 1 pole mount light fixture for parts TOTAL $2,710.65 45-R1 Credit for Door Hardware at the Sheriff Holding Cells: • Original electric locksets for 23 doors $(4,740.81) • Dummy locksets for 19 doors 1,118.15 • Credit for 23 bronze closures replaced with 19 aluminum (325.00) • Credit for 23 bronze kick-plates replaced with 19 stainless steel (245.50) • Credit for sales tax (314.49) TOTAL $(4,507.64) 49 Furnish and install 3-way control valves and bypass branch for the Chilled water system at each of the six air handling units, in lieu of 2-way control valves: • Additional costs for the 3-way valves $770.80 • Labor S Material for installation by Weathertrol 7,181.82 • The Tower Group 5% 384.78 TOTAL $8,317.40 50 Furnish and install additional lighting for artwork in Room#3047: • Material $315.56 • Labor 131.90 • Sales Tax 23.67 • The Tower Group 10% 40.06 TOTAL(Funded by the 16'*Circuit Court) $511.19 51 Modifications to the 2nd and 3rd floor lobby lighting: • Material including estimated freight charges $14,058.34 • Labor 2,487.58 • Sales Tax 941.88 • The Tower Group 10% 1,566.32 TOTAL(Funded by the le Circuit Court) $19,054.12 TOTAL CHANGE ORDER NO. 21 26.085.72 1 Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes® No❑ If Yes, explanation: Change Order Request #7-R1 to modify the lighting on site was proposed by the architect to facilitate pedestrian and vehicle traffic. The credit for Change Order Request#45-R1 is primarily due to the vendor not being able to sell locksets to our Contractor, They must be purchased by the end user. Change Order Request#49 is correcting the design for the chilled water piping system that had been designed with 2-way control valves, and could be corrected to have a- way control valves. Change Oder Request #60 and #51 were requested by Monroe County to include additional lighting for artwork in room #3047, and modifications to the lighting in the 2nd and 3"d floor lobby. These will be funded by the 16'Circuit Court • Change Order was included in the original specifications. Yes❑ No If Yes, explanation of increase in price: • Change Order exceeds$25,000 or 5% of contract price(whichever is greater). Yes❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes❑ No If no, explanation of why: The Architect is not required to approve Change Orders for the Freeman Justice Center. • Change Order is correcting an error or omission in design document. Yes❑No Should a claim under the applicable professional liability policy be made? Yes❑ No Explain: Monroe County FacBiBes FILDevebp -ems � � � - ment OvY AUG 2 2 2006 TIME: RECEIVED BY: MONROE COUNTY COURTHOUSE ANNEX SIXTEENTH JUDICIAL CIRCUIT OF FLORIDA 5 STREET KEY WEST, F FLLORRIDA 33040 TELEPHONE(305)292-3423 SUNCOM:494-3423 TELEFAX (305)292-3435 August 17, 2006 RO UTI N Mr. David Koppel _ Monroe County Engineer w 1100 Simonton Street Key West, FL 33040 RE: Freeman Justice Center Dear Mr, Koppel: Please see attached the following change order requests from the Tower Group: • Change Order Request 00050 in the amount of$515.87 • Change Order Request 00051 in the amount of$20,429.91 Both of these COR's are for lighting changes in the Freeman Justice Center. The Court, using the existing Court Facilities budget, would like to pay for both of these changes. By using the Court's existing budget, there would be no additional costs to the Capital Fund, therefore we are asking for your approval to these requests. Thank you for your attention to this matter. If you have any questions, or need any additional information, please do not hesitate to contact me. Sincerely, C t � Holly H. omina Administrative Services Manager CC: Chief Judge Richard G. Payne John Chandler, The Tower Group OUTING Clar^� 0 r;/k der� [� D d'r!;j 4 �a�� uaityizuub ib:u7 PAX Hb4 37U 5401 UNITED ENGINEERING CORP. Q 001 �,D �? �1 'cy THE TOWER GROURJ September 19, 2006 0417-02294 General Attn: Clark Briggs, Senior Project Manager Fax: (305)295-4321 Contractors Monroe County Facilities Development 1100 Simonton Street Monroe County Construction Facilities Development Management Key West, FL 33040 Re: Freeman Justice Center(FJC) SEP 19 Hub Subject: COR#7-R1 -Site Lighting Revisions TIME: Construction RECEIVED BY: v Dear Mr.Briggs: Deslgn-Build Please find enclosed Change Order Request(COR) #7-R1 for the site lighting revisions proposed by Gonzalez Architects(GA)in their Request For Proposal (RFP)#l, dated March 29, 2005, and the site lighting revisions proposed by Currie Sowards Aguila Architects(CSA) Planning in Item#1 of their September 8, 2006 RFP. The Tower Group proposes to implement these changes for an increase to the Contract Value of$2,733.26 plus one pole-mounted Type SA fixture complete with pole as spare parts, and Site Development no change to the Contract Time. This change is implemented at the request of the Architects to facilitate pedestrian and Infrastructure vehicle traffic along Fleming Street and Thomas Street,and to incorporate resolution of grade conflicts first identified by The Tower Group to Monroe County and GA via Request For Information(RFl)#9, dated November 9, 2004, Consulting Please furnish your acceptance of this proposal and process a Change Order to the Contract for this Extra Work. Estimating I If you have any questions,you may call me at(786) 367-0549, Sincerely, Scheduling Value Engineering John Chandler Project Manager Post Construction Encl. COR No. 00007-R1 (13 pages) V CGCA38309 cc: TTG/MO (COR-7), FF (COR-7) 405 S,W, 148th Avenue - suite One - Davie,Florida 33325 - Tel:954.476.3200 Fax:954.474.3111 7601 S,W.lost River Road - Stuart, Florida 34497 - Tel: 772.287.7525 - Fax: 772.287.7524 9440 Philips Highway,Suite#5 -Jacksonville, Florlda 32256 - Tel: 904.292.1811 - Fax:904.292.4865 v�ii�ic,vuu lu.ur rnA vug aru a4u1 uAlirll 1!1Vx311NhhK1NU x:UKr. to002 The Tower Group, Inc. CMANGE ORDER REQUEST 405 SW 148 Avenue No. 00007-Rl Suite One Phone: (954)476-3200 Davie,FL 33325 Fax: (954)474-3111 TITLE: Site Lighting Revisions DATE:9/19/2006 PROJECT:Freeman Justice Center(FJC) JOB: 0417 Monroe County Facilities Development TO: Attn: Clark Briggs CONTRACT NO: 1 Monroe County Facilities Development SEP 19 2606 1100 Simonton Street _ J � Key West, FL 33040 TIME: �! RECEIVED BY: a -- Phone: (305) 295-4306 Fax: (305) 295-4321 RE:RFP To: TTG From: CSA Number: 1A DESCRIPTION OF PROPOSAL Change Order Request(COR)#7-R1 addresses the costs to implement site lighting modifications desnbed in Request For Proposal (RFP)#1 from Gonzalez Architects(GA),dated March 29, 2005,and Item#1 on the RFP from Currie Sowards Aguila Architects (CSA),dated September 8,2006(henceforth referred to as RFP#IA). The original scope of site lighting included 18 pole-mounted Type SA light fixtures only(See attached,reduced copy of Contract Dwg.#E0.01). RFP#1 from GA(copy attached,4 pages)changed this scope to 8 pole-mounted Type SA light fixtures,8 wall-mounted Type SA light fixtures,and 4 Type SC up-lights. The Tower Group(TTG)submitted COR#7,dated June 16,2006, proposing a credit in the amount of$3,434.00 for these changes based on the June 6, 2005 proposal from Patrick Power(copy attached, 1 page). Monroe County accepted this proposal in their October 6,2005 Ietter(copy attached, 1 page)and Patrick Power proceeded to order the fixtures based on this scope. CSA subsequently modified the parking lot to resolve grade conflicts in the GA design,which changed the exterior lighting scope to 7 pole-mounted Type SA light fixtures, 12 wall-mounted Type SA light fixtures and 4 Type SC up-lights as described in Item#1 of the September 8,2006 RFP(copy attached, 3 pages). COR#7-R1 supersedes COR#7 in its entirety. COR#7-RI is based on the the June 6,2005 Patrick Power credit proposal for GA's RFP#1 and The Tower Group cost analysis and Farrey Quotation,dated August 31,2006(copy attached,2 pages). Please note that Patrick Power had already purchased 8 poles and 8 Type SA pole-mounted fixtures. As The Tower Group cannot return the spare pole and fixture,we are turning them over to the County as spare parts in lieu of a credit. Please process a Change Order in the amount of$2,733.26 plus one spare pole and Type SA fixture for this Extra Work. This Extra Work does not change the Contract Time. Item Description Stock# Quantity Units Unit Price Tax Rate Tax Amount Net Amount 00001 Change scope to 8 pole-mtd. 1.000 LS ($3,434.00) 0.000/0 $0.00 ($3,434.00) Type SA fixtures,8 wall-mtd. Type SA fixtures,and 4 Type SC up-ilghts(RFP#1 from GA) 00002 Change scope to 7 pole-mtd, 1,000 $6,167,26 0.00% $0.00 26 Type SA fixtures,12 wall-mtd. S Type SA fixtures,and 4 Type 4-1 - SC up-lights(RFP#lA from CSA) Unit Cost: ,733.26 Unit Tax: $0.00 Unit Total: $2, 3.26 o) WO ,&S Ua11014000 10:1J VAA y04 3rU 04U1 UNITED ENGINEERING CORP. � C0013 tvlonroe County � Faclllfles Development CEP 19 2006 RECENEDY: a N O O �i 1A 0 0 p O O �i M t7 N►19 r 0 � 0 0 0 0 0 CO iA O � � j W -21 1 0000 -`y Ooa0000a o oou� 000c�, o M � Z O1l�frr� cotei +� d' � N0 LU � 40 � Jo � � w ~ w00 o fir, 01 r as o � � � � om v- ia L� C z0 � g za IL Lij ILzm w W a V y t � z 5 x x W `t W � e 0 LL � H =d 9 WeacO M M gr Z M ZWWLL1ryrWWWW � VVwt NI- WtWt uN/1U/L000 10:14 t'AA H04 3!u 04Ul UNITED ENGINEERING LO014 ILE CORP.No.129 08r31 '06 12:08 �_�: FAX: , 7 — PAGE 1i 1 7": . `� '�► ''� QUOTATION Dates ()8/31/06 1ft50'N,tt. 146 Street - Miami,Florida 33181 USA Quote: 083106EML Monroe County Corporate Office:(305)947-5451 - FAX(305)940-3450 Project: EREEMANS JUSTICE CENTER racilHles Development ww►,'iarreys,aom, - E-Mail', t'arroys@pate.net Page: 1 SEP i 9 2006 Vle".1- Quotpilon submitted by: Prices quoted., F.0.8, Miami Manny Maaolras Prices valid for: 90DAYS RECEIVED BY: Direct Lints:(305)919.0151 Lead time: 6-9 WEEKS Coliulaf;(305)812.1313 (paged on®vnilubili(y ns crabova data) Terms: Prices quoted are hayed upon quantities Presented tot JOSE CLAUSELL Ife[ad. Any ohuagae will invalldato quota. THE TOWER GROUP Urdor will he proeeemd upon racvipr of - P14ONS:954-275.1127-PAX:305.296.2587/954.474.3111 (1)Signed approved quotation; (2)Purchase Order confirmMi quati i(lee QUANTITY TYP& CATALOG NUMBER AND DESCRIPTION UNIT PRICE TOTAL PRIG 4 SA•W SUNV XAE-WM-INVBRT0D/LCICMI 5I1NV CPA $1,110,5te $4,443.02 (FROSTOD}I50-HPSM'r@277.91INV PT-HK $0•00 AM8 AS TYPO 4A" BLIT WAl 1.MOUNTHI)• $0.00 $0,00 SOA0 So.00 $0.00 $0.00 $O,OD tiD.OU $0 00 • sn,00 $0.00 $0.00 $0.00 sn•oo •. so.ao so.00 sn,ao ' so•oD MOO $00 so.nn • sn,00 $6,00 $0.M S0.00 $0 00 an.nn S0,00 5D.0n t' additional are based ou bulk purchase. SUBTOTAL. $4,443,93 fixtures a new quote must be provided, TAX $311,07 uote must be used,no artlals. TOTAi. $4,794.00 The Tower Group,Inc. 405 SW 148"'Avenue,Suite One Davie,Florida 33325 Phone: 954-476-3200 Fax:954-474-3111 THE TOWER GROUP Th: Monroe County Facilities Development From: John Chandler o � U y N Attn: Ann Riger Tel/Pax:(954)476-3200/(954)474-3111 0 0 Fmc (305)295-4321 Pages: 1 f-- � m Phonei (305)292-4439 Date: October 7,2006 a Re: Freeman Justice Center(FJC) CC: TTG/MO(MCCM),FF(MCCM) 041 7-02346 Sualsct: Labor Burden for TTG Field Forces ❑ Urgent ❑ For Review ❑ Please Comment ❑ Please Reply ❑ Please Recycle • Comments: Dear Ann: In response to your request,please accept the following breakdown of our labor burden costs for field forces at the Freeman Justice Center Project: Vacation and Holiday Pay 6.15% Social Security and Medicare 7.65% Unemployment Compensation 2.70% Workers Compensation 24.72% Health and Dental Insurance 8.16% Payroll Services 0.03% Per Diem 10.00% Total 59.41% We round this value down to 55%because some employees choose not to participate in the health and/or dental insurance plans, and because unemployment tax decreases every six months of continuous employment. I hope this clarifies this issue,and I apologize for taking so long to get you this information. If you have any questions,please call me at(786)367-0549. Sincerely, John Chandler,Project Manager A U`J/lU/GUUU 1b:U6 VAb U04 S!U 54U1 U1 llhO hlNUliNhSK11Vti UUKV. I tOUU3 VAR III a Monroe County Facllltles Development SEP 19 2006 _ a -, TIME:—, — RE RECEND BY: m Q go b H C g� m aIr KE I t9® py6y� M » e CCtCC+ F r vF4o�narwotu+e'aw•�oo-am�rw��ani�wolio�ta�ro�d Ua/10/4VU0 lo:Ua rAA ma4 JIU a4U1 UA11hV hAU11VL'L'H1AU UUKF. ( LQUU4 CA Gonzalez Architects Architecture * Planning * Interiors Monroe County F00111t1e3 Development MEMORANDUM SEP 192096 i7ME:_. _44_ Date: March 29, 2005 RECEIVED BY: To: Greg Galmin, The Tower Group From: .lose A. Gonzalez,NCARB ALA Project: ,Freeman Justice Building Re: Site Lighting Revisions - Request for Proposal (RFP) #I Cc: Larry Chalmers, Director of Construction &Planning, Monroe County Please see attached Site Plan, sheet E0.01 for the revisions to the site lighting fixture type and location. The revisions are `clouded' and include the following: Front Entrance—Relocate pole fixture (SA) to accommodate revised parking. Add (4) lights (SC) to up-light columns. Thomas Street—Remove (4) pole light fixtures (SA) and add (4)�wall+mounted fixtures. ' FterninQ Street—Remove (6)pole light fixtures (SA) and add (4)wall-mounted fixtures. The site light fixtures are to match existing site lighting. See attached information provided by Monroe County for the existing site light fixtures. The wall-mounted fixture to be used is Security Lighting Systems, Inc., fixture RWS 70MH DL WH 277 —see attached specification. Please submit a proposal for these revisions. C 4 G� 5 � � 8 32 East Bav Street, Savannah, Georgia 31401 * (912)201-9888,Fax (912)201-0240 :720 A N orth Roosevelt Blvd.. hey West, Florida 33040 * (303)294-3748,Fax (305)294-8217 1602 _-�1ton Road,PNIB 503, Miami Beach, Florida 33139 * (30)672-90-14, Fax (303)866-8324 09/19/2006 16:09 FAX 954 370 5401 UNITED KNG1NEEK1NG UUKY. /— �1 . � I¢J UU5 I Monroe County �acllltles Development SEP 19 2u o roar RECEIVED \ W } I Baer.V.YLr 'I \� \ y rae..eraar�es rE)USTINO A w \ w ! ®, .• r _ _ _ ID thr.am FVV �oaer..omo 6.aL eu t 0�• •`. + .'wTP a , "1`7f 1 © �� F rcw nesma W. .wraLL � ®Ern. ;CA ■ Date aeayT R r.w Lr,aOarNt rRTJ� Uh tY.K � y/y�JSIGTl, IL.. rrrrj I '' MA&D YM UN a t a#F4lia►+ \ a6aGa'+ tcaaa m MM a 0 t r 1r a,�arc `� o�eoial�ncx�t / c.t a aoa f i L= s 1 10 l ! al [NEW JUDICIAL BU 1 I t r y �• � I � 1 i I ` I rcrr I �y n W CNu'IF..1•tlQ�•TLI • I i I I -------------- I I 1 -cwel. Ua/19/GUUb Ib:IU r'AA U04 3'!U 04U1 UNITED ENGINEERING CORP. � 1 006 1 . t Monroe County as: cvuvW-rtoNN f ,.�., Fcacflltfes Development X< + ry w h. SEP 19 200H - W RECEIVED BY:—�� 1 uvd•Sa+6ouW \ F ► M PAC b rrto eaea, ■I m r r�L Co. faR ` �i , ex•a1w+.c= J W _ wutxlNc rent Ns, 'R a co�cncrc puttucxrI y1Ngg1Y ♦ a1gUN0 ..r ouCrS wax[WAC CWPCR taa� Il M O,M e� WH. sC>tmut.t w 1 \ I j•� -�'-- v es• -+� a�: a• I I i ��G.oaeo+l ow.go axana AU7.C?A.�—t i __. —,s.�..d.�—�,•t[ Da ram'►L - 1` 1� L eMri it ri c'N JUCICIAL suiLOINcl 17-1 l � lr. r• r r r l r i i n •\ ' I E � i 9 VIA47 U oi 776 Coe 7 .�� i.ii c.vvu iu.tv i'Aa JJY J,V JYV1 U1V11L`L Jr.1V 1111�L'L'j'(J.1Vu VVICY• •.id UUI ` I II � ��� 1 l..V...V♦ vv W�f i�_••+ .mil iF1Jacksoa Square Renovations J, • �.� Freeman Justice Center Flen+ieg Speer Kcy wetG Florida I 1 n M 1 14.4 1 1 EB N � � - I l G. 1 V m• •�- I t s- \ a s O a7 1 I n.oMot WALU Piscoriao tad. 1U= \ �•r�•Data " 'umuMan V&.G' w•arwn,a Y'9U'G/t,P�l 1 � A4W]L _��\ ae�r.J --� � Franyie Eegtaa Fat. `Monroe County ^Tr' '• w+^+u Facllltles Development. . MR Mae V� r.%M.va A•r'a 9.0T. SEP 19 2006 / TIME: RECENED BY:___ xa t•tara% j FSt+.1�Qir,Cc'NI- iPRGPpJti'7 i 1 It g®g y i1 ' r In.,svu=7K r c sic,•.0 WASr gq Al" b-0. SITE PLAN \C SITE PLAN /2- TT6 �� . U`J/19/LUUb 1b:11 PAA `J04 JIU b4U1 U1V11L'V hINU11VL'1'.K11Vli UuKr. LY/JVV0 FATRi�f�' POWER �O.-M Electrical Contractors and Engineers C 0 M M E A C I A L INS T / T U T 10 NA L I NO US T R I A L I June 06,2005 The Tower Group Mr. Greg Galrr in 405 SN 148 h Avenue, Suite 1 Davie, Florida, 33325 CON, MONRO�CCO Ref: Freeman Justice Center Subject: Cost Proposal—RFP#1 QU 05 PROPOSAL After carefully reviewing RFP #1,described as: Site Lizhtinp_Revisions on drawing number E0.01-revision dated on 03.23.05 "Site Revision", there was a cost impact found on our scope of work as a credit for the amount of53,434.00 Our proposal is good for 30 days or until-conditions change. An example of change on conditions will be pouring of the slabs. Layout, Corinz. CutiinQ and Patching has not been included in our pronosaL Please contact me if 1 can be of any further assistance. Monroe coup ty Facilities Development Sincerely, SEP 19 2666 Ivan C amayor TIME: RECEIVED BY: ;,� Project Manager ------v_ cc: lyfichael J. Driscoll,PPC Jose Clausell, PPC 5591 N.E- 14:h Avenue Fort Lauderdale, Florida 3333-,' Telephone (95:—1 491.7745 Facaimil_: (95. ) 772-212e UU/1y/LUUb 1b:11 t'AA U04 3!U 04U1 UN11'ED ENGINr:E1t1NG UUKY. WjU09 BOARD OF COUNTS'COW-USSIONERS C)UNTI� MQNRO� Mayor Dixie M, spehar, District J Mayor Pro Tem Chorles"Sonny"McCoy, District KEY WEST FLORIDA M040 George.Neugent,District 2 (3105)2944641 David P. nice,District 4 Murray E Nelson, District 5 Monroe County `^ L: F00111 fes Development October 6,2005 SEP 19 2606 Greg Galmin rIME: —---- - The Tower Group RECEIVED 405 SW 148`I'Avenue Suite 1 Davie,FL,33325 Re:Freeman Justice Center--CraWt to Owner for Deleted Light Fixtures Dear Mr, Galmin, In reference to the Tower Group Change Order Request received in our office August 11,2005 in flit amount of$3,434,for credit to Owner on deleted exterior light fixtures at the Freeman Building; the format appears to be acceptable to Monroe Coutsty. The fomsat and content appear to be consistent with your contract and with previous credits to the Owner (Change Orders#1 and#3)wherein there are no Iine items inclusive of overhead and profit as cited by Gonzalez as his basis for recommending disapproval of this Change Order Request in his August 30,2005 memo to our office. We are at a loss to explain Mr,Gonzalez' recommendation for disapproval Therefore please accept this letter as authorization from Monroe County to notify your sub-contractors that the proposed credit to the Owner is acceptable, Sincerely, Alan French t 100 Simontan Struct Tel: 305-29.'.-4429 Key Wcst,FL 33040 Fax: 303-295- 432 J Uy/19/LUU5 16:11 r'AX U54 3'/U 54U1 UN1'1'ED ENGINEERING UUKY. �7 ((l --►J tQJUlU CURRIE i 56WARDS - AQUILA J ARCHITECTS Robert G. Currie, AIA Jess M. Sowards, AIA Josd N. Aguila, AIA September 8, 2006 O�rt- aZloD John Chandler The Tower Group 302 Fleming Street Key Weat, Florida 33040 Monroe County Facilities Development Re: Freeman Justice Center 19 Z�tO6 Project No. 060905 1iME: RECEIVED BY: Dear John, You are directed to provide proposals for the following: 11 The added exterior lighting for the parking area, as defined by the new approved photometric drawings. 2, The added sally port related Items aS defined by drawing "51"C-1"from C5A and drawing 5-01 from i'istorino. This includee but le not limited to'walls, columns, beams, canopy, access doors, Security folding gates, overhead door, arld vents. ,- 31 Garage area exhaust fans ae Shown on drawing W-V from C5A/TYEC. 41 New Security fence and gate at south west corner of building at FKAA property along Thomas Street aS shown on "fence"drawing from CSA. 5, New louver at south west corner of garage ae Shown on "G-Louv"drawing from CSA. if you have any queotlon5, please call me at the office, thank you. Sincerely, Hank Goldman cc; Clark 6rl06s (—,,, 11 The Tower Group, Inc. FORMERLY ROBERT O , CURRIE PARTNERSHIP, INC , • AIA FLORIDA FIRM OF THE YEAR 2000 134 Northeast First Avenue • Delray Beach, rlorids 33444 • 561476.4951 - rax: 561 •243�8181 • AA000227 I w w w.cuyr�rlearc.com �g f UUI IU14000 10:14 VAA J04 J IU 04U1 UNII'ED ENGINEERING UUKr. � �� ��-^'� _ IQ Ull The I ower Group, Inc. SUBIVIITTAL NO. 16500-05 405 Southwest 148thAvenue Phone: 954-476-3200 ]PACKAGE NO: 16000 Davie,Florida 33325 Fax: 954-474-3111 TITLE: Photometric Analysis-Parking Lot REQUIRED START: 9/6/2006 PROJECT: Freeman Justice Center(FJC) REQUIRED FINISH: 9/15/2006 DRAWING: Sun Valley Lt Dwg. #Ll DAYS HELD: 0 STATUS: NEW DAYS ELAPSED: 211 BIC: CSA DAYS OVERDUE: -9 RECEIVED FROM SENT TO RETURNED BY FORWARDED TO TTG JC CSA HG CSA HG TTG JC Revision Drawing No. Description/Remarks Received Sent Returned Forwarded Status Sepias Prints Date HeldElapsed 001 Photometric Analysis 2/7/2006 2/8/2006 2/17/2006 2/20/2006 DIS 1 6 0 13 Original Drawing is 18x24, copies are 11x17. Review Comments: -Min.2 ft-candles -Max. 12:1 light-to-dark 002 Photometric Analysis 9/5/2006 9/6/2006 NEW 7 QAonrae County 0 1 ac""t"� v�l� lrlenl ItME: RECEIVED BY: THE TOWER GROUP, INC. SHOP DRAWING SUBMITTAL THE REVIEW IMPLIES GENERAL CONFORMANCE WITH THE REVIEWED REJECTED 13 DESIGN CONCEPT OF THE PROJECT AND WITH INFORMATION, GIVEN IN THE CONTRACT DOCUMENTS ONLY,REVIEW OF THE REVIEWED AS NOTED 0 SUBMITTALS BY THE TOWER GROUP, INC, IS NOT TO BE REVISE AND RESUBMIT ® INTERPRETEDASADETAILED INVESTIGATION OFINFORMATIOI. PROVIDED IN THE SUBMITTALS OR AS APPROVAL TO DEVIATE SUBMITTAL,NOT REQUIRED ri FROM THE REQUIREMENTS OF THE CONTRACT DOCUMENTS. RETUR E WITHOUT ACTION APPROVED AS SUMBITTED 0REVISE AND RESUBMIT 6Y: DATE; O 8APPROVED AS NOTED O REJECTED AND RE-SUBM!' ❑REVIEWED CURRIE SOWARDS AGUILA A CHITECTS SATE:_C74,/0 134 N. E. 1 s7 Avenue 3Y; _T' � --� Delray Beach, Florida 33444 IROJECT; 'CP DRAWING M 'vs'�.., 1 ft- ILL .�._.... Y,.'.. .:i [1EP 7 2006Group, 11nc, sowARDcU" -a.mmawm.►..-«.o-..�.�..au� ARCHITECTS UU/1U/LUUb 1b:1L t'A3 U04 3!U 04U1 UN1'M) L'NUINLEKINU (:UKY_ Lgjulz +eMao�m.�rwa w+ taplauwadea OuP4011 meeaiNl�atl tRNe1 OwA S91N30 3�Ilsnr NVN332� ma e.wr•Mw yy m Amin rc 6S® �ooe (BPVJO IV)UOROM0190 00—fWMIII Mcd-AeWlod **-c nroe County Faclll es Development D BY cliN a� NO A Y N LA r G •; N Oj a M� I I M 4 I� u yy }I•A r r r r r �• cO n t N 't• L J r.� tD N tp � d• �"CV o lnunur�� ❑� r- m n o I ❑ � tI7 N O 0 N N A4 00 0) r r a 00 rl- i The Tower Group, ht�._ -ANGE ORDER REQUEST 405 SW 148 Avenue No. 00045-Rl `Suite One Phone: (954)476-3200 Davie,FL 33325 Fax: (954)474-3111 TITLE: Security Door Hardware Changes DATE:9/11/2006 PROJECT:Freeman Justice Center(FJC) JOB: 0417 TO: Attn: Clark Briggs CONTRACTN&oe County I Monroe County Facilities Development Facilities Development 1100 Simonton Street SEP ] 9 2006 Key West, FL 33040 Phone: (305) 295-4306 Fax: (305) 295-4321 - - RECEIVED BY. RE: EST To: TTG From: CRAFTMAS Number: CRO03 DESCRIPTION OF PROPOSAL The Monroe County Sheriffs Office(MCSO)requested that TTG furnish Southern Folger Model 10300E electromagnetic locks for the holding cell doors. TTG included all the door and door hardware changes in Change Order Request#23,which was ultimately approved as Contract Change Order#12,except the material costs for holding cell door hardware and the electromagnetic locks, which were pending final verification of door swings and locking preferences. With the door swing and locking preferences confirmed,we are pleased to submit our proposal for the security door hardware changes,Change Order Request(COR)#45-R1 COR#45-R1 supersedes COR#45 in its entirety. COR#45-R1 excludes the costs to furnish the MCSO-specified Southern Folger electromagnetic locks based on the enclosed correspondence from Southern Folger's regional distributor,Craftmaster Hardware,explaining the manufacturer's restriction of sales to certified contractors and end-users only. MCSO must furnish Southern Folger Model 10300E locks,as indicated in TTG COR#45,in order to comply with the door frame modifications that are part of Contract Change Order#12,as well as to comply with the door hardware specified by this proposal. TTG proposes to implement the holding cell door hardware modifications for a Contract Price Decrease of$4,507.64 and no change to the Contract Time. This proposal is based on the attached quotes from Craflmaster Hardware for the original scope of holding cell door hardware and for the revised scope of holding cell door hardware. Item Description Stock# Quantity Units Unit Price Tax Rate Tax Amount Net Amount 00001 Storeroom Electric Lockset 12.000 EA ($393.00) 7.50% ($353.70) ($4,716.00) (Original Scope) 00002 Storeroom Lockset(Original 11.000 EA / ($2.26) 7.50% ($1.86 ) ($24.81) Scope) 00003 Dummy Lockset(Revised 19.000 EA / $58.85 7.50% $83.86 $1,118.15 Scope) 00004 Bronze Closer(Original Scope) 23.000 EA . ($150.00) 7.50% ($258.75) ($3,450.00) 00005 RH Aluminum Closer(Revised 1.000 EA '` $155.00 7.50% $11.63 $155.00 Scope) 00006 RH Cushioned Aluminum 7.000 EA $165.00 7.50% $86.63 $1,155.00 Closer(Revised Scope) 00007 LH Cushioned Aluminum 11.000 EA $165.00 7.50% $136.13 $1,815.00 Closer(Revised Scope) 00008 Bronze Kick Plate(Original 23.000 EA ($21.00) 7.50% ($36.23 ) ($483.00) Scope) 00009 SS Kick Plate(Revised Scope) 19.000 EA V,`' $12.50 7.50% $17.81 $237.50 00010 Door Silencers,100/PK 1.000 PK ($10.50) 7.50% ($0.79 (Original Scope) ) ($10.50) 00011 Door Silencers, 1.000 PK $10.50 7.50% $0.79 $10.50 100/PK(Revised Scope) Unit Cost: ($4,193.16) Unit Tax: ($314.49) Unit Total: ($4,507.64) 7-3 "I e Craftmaster Hardware Co., Inc. 4�R Wholesale Security Hardware —CP 190 Veterans Drive Tel(201)768-0808 ext. 100 ' Northvale, NJ 07647 Fax(201)768-3883 E-mail:ms in el craftmaster.ne ° www.c raftmaster.net bG1Rp�+7G�R�' August18,2006 Mr.John Chandler The Tower Group Re: Your P.O.3 0417-045 for(Freeman Justice Center) i Dear Sir, Due to our contract with Southern Folger Detention Equlpment Company we can no longer sell their products to anyone except local, county,slate&federal correctional institutions or a limited list of detention contractors who have completed Southern Folger's certification process. We would be able to sell the products to Monroe County f they issue us a purchase order directly. I'm song for any inconvenience this has caused. Monroe County Please let me know if 1 can be of further assistance. Facilities Development Yours truly, SEP 19 2006 TIME:__ el Spingeld RECEIVED BY:— "-------- President Sap 11 06 10:45a The Tower Group 305-296-2557 11 :J— p.5 iH .�r.vv. tvvv SV.4i �.VS iVv. J ll'V-1r 1 � �ICm r- �-'(a�jt brj Crai#master Ha ware Co., Inc. �te� �e � TER WHOLESALE LOCKSMITHSep a,2W6 S PLIES-DOOR HARDWARE Quote Number 190 Vetoer ns Drive 0010270 in 0 o Northvale,�J 07647 Customer No, SP TOLL-FREE: 800-221-3212 C9999 HQUSE2 Local: (201)768-0808 Fax:(201) 768-3883 Step via �Q� Q Fad l.D.013-27=33351 U.P.S.CUST EXP. Terms C.O.D. Quote For. TOWER GROUP INC 406 SW 148TH AVE,SUITE 1 DAME, FL, 33325 ( Quotation Quotations varid for 45 days unless renewed in writing. ATT:MR.JDHN &CHANDLER We appreciate the opportunit to quote on the following,.. ly CMwt ty urn iftun Number r.. D Nption Unit Ptlw Ext.Pr1eo 19 EA —!- BE-93K-1DT-16D-S 828,DUMMYLOCKSET 58,6500 1,118.15 / T EA LC/4011 AL-RH CLOSER RH 155.0000 155.00 7 EA —1- LC-4111CUSH-11K CLSER 185,0000 1,'155.00 Of r 11 ESA —f- LC-4111CUSH-LI-i- CLSER 165.0000 1,815.0c . 19 EA —f- HG-19OS4rX34-32 ,PLATE STAINLESS STEEL 12=0 237.5C 1 PK IWSR64 DOOR SILENCERS(1001PK) 10.5000 10. -kl . fI i I I ow6 ep- - 1 I Please refer to quotatio 01027 w n placing o er, Total: 4,491.15 Quotation Submitted b PLUS ANY APPLICABLE TAX OR FREIGHT CI-"GES z l f - 3 09/11/2006 MON 10:41 [TX/RX NO 77281 IM005 Sep 11 06 10:45a The Tower Group 305-296-2587 p.3 —A r vv1 .r I.ICH� i P1H:3 I trm � � (1� FAbE 02 Craftmaster Hardware Co.. Inc. ` gD" iKI age WHOLESALE LOCKSTH SU PLIES-DOOR HARDWARE Sep a,ass quatn Number 190 Veterapis Drive 0010278 J ° Northvale,tilJ 07647 Customer Nu, sP TOLL-FREE: 00-7-21-3212 C9999 KCUSE2 c Local:(201)768-0808 -1 Fax (201) 768-3883 ship Via Fed I.D.#113-2733361 U.P.S.CUSTJEKP. G Terms C.O.D. Quote For: T142 TOWER GROUP,INC j 405 SW 146TH AVE,SUITE 1 DAVIE, FL, 33326 Q u ota#� r1 Quotations valid for 46 days unless renewed in writing. (: A1ET,MR.J0HN:S.CHANDLER reciate the opportuni�to quote on the following... -.Quantity unn item Number 0-4cripUan Unit Prix• Est,Price 12 EA -I- BE-93KW7-DELL15D-S3-613,STOREROOM ELECTRIC U 393.0000 4,716.DD LOCKS ARE PRICED W/Cd IE WILL NEED nt AY 11 EA --1 SE-931<7-150-83, OREROOM LOCK,613 ✓ 2.2580 24.81 23 EA -/- LC 411'I-4116 MNOING-WS FIN SH-DARK BRONZE CLS ✓'150.0000 3,450.00 ✓ CLOSER ABOVE IS A HANC ED CLSER,AND NED TO KNOW SIZE 1 THRL)6 23 EA -/- IV 640a-10X24-613 KICK PLATE 21.0000 483.00 CHECK SIZE 10X2 7? 1 PIC IV/SR64 DOOR SiLENCERS11001Pl4 10,5000 10.50 r I I l I Please refer to quotation Q01 7 p a �der. Total: 8,684.31 PLUS ANY APPLICABLE Quotation Submitted by: i TAX OR FREIGHT CHARGES f 09/11/2006 MON 10:41 [TX/RX NO 77281 IM 003 ...... ... . ..... �y 5 Monroe County Facilities Development AUG 99 20Q6 TIME: ' THE RECENED BY: TOWER G ROU R August 8, 2006 0417-02183 General Attn: Clark Briggs, Senior Project Manager Fax: (305) 295-4321 Contractors Monroe County Facilities Development 1100 Simonton Street Construction Key West, FL 33040 Management Re: Freeman Justice Center(FJC) Subject: COR#49 -Change CHW to 3-Way Control Valve Construction i I Dear Mr. Briggs: Design-Build Please find enclosed Change Order Request#49 for the additional work to change the 2-way control valves, shown on the Contract Drawings for the chilled water system at each of the six air handling units, to 3-way control valves with bypass branch connections. The total cost Planning for this extra work is$8,317.40. This change was initiated by RFI#214, which identified that the chilled water piping system had been erroneously designed with 2-way control valves and constant volume pumps. The Site Development Engineer's response to RFI#214 corrected this error by changing the 2-way control valves to 3-way control valves. Infrastructure A detailed breakdown for the costs of the labor, material and equipment associated with this change is attached. This change does not affect the critical path of the project. Please process a Change Order in the amount of$8,317.40 as soon as possible. Consulting Sincerely, Estimating ', John Chandler Scheduling Project Manager Value Engineering Encl. COR#49 (6 pages) -a A._ ! Post Construction CGCA38309 cc: TTG/MO (COR-49),FF (COR-49) CSA/H.Goldman (Fax: 561-243-8184) 405 S.W. 148th Avenue a Suite One • Davie, Florida 33325 v Tel: 954.476°3200 o Fax 954-474.311 1 7601 S.W. Lost River Road e Stuart, Florida 34497 • Tel: 772-287.7525 ° Fax: 772,287.7524 9440 Philips Highway, Suite#5 a Jacksonville, Florida 32256 ^ Tel:904-292.1811 e Fax:904-292.4865 The Tower Group, Inc. C.tANGE ORDER REQUEST 405 SW 148 Avenue No. 00049 Suite One Phone: (954)476-3200 ------ '- Davie,FL 33325 Fax: (954)474-3111 TITLE: Change CHW to 3-Way Control Valve DATE:8/8/2006 PROJECT:Freeman Justice Center(FJC) JOB: 0417 TO: Attn: Clark Briggs CONTRACT NO: 1 Monroe County Facilities Development 1100 Simonton Street Key West, FL 33040 Phone: (305) 295-4306 Fax: (305) 295-4321 RE:RFI To: CSA From: TTG Number: 00214 DESCRIPTION OF PROPOSAL Change Order Request(COR)#49 proposes to furnish and install 3-way control valves and bypass branch,in lieu of 2-way control valves shown on the Contract Documents,for the chilled water piping at all six Air Handling Units. This change corrects HVAC design error in accordance with the Engineer's response to RFI#214. Please process a Change Order to increase the Contract Price$8,317.40 for this extra work. There is no change to the Contract Time as this change does not affect the critical path of the project. Item Description Stock# Quantity Units Unit Price Tax Rate Tax Amount Net Amount 00001 ESSI Change less sales tax 1.000 LS $721.60 0.00% $0.00 $721.60 ✓ 00002 Weathertrol Change less sales 1.000 LS $6,974.02 0.00% $0.00 $6,974.02 tax Unit Cost: $7,695.62 Unit Tax: $0.00 Unit Total: $7,695.62 Subtotal: $7,695.62 Description Markup Percent Markup Amount Sales Tax $237.00 ✓ Profit 5.000% $384.78 ✓ Total Cost: $8,317.401/ NNW Electronic Systems Southeast, LLC PkoPOSED CHANGE ORDER No. ESS001 2263 Boca Raton Blvd., Suite 210 Phone: (561)955-9006 Boca Raton,FL 33431 Fax: (561)955-9007 77 TITLE:Change to 3-Way Control Valve DATE:8/8/2006 PROJECT:Freeman Justice Center(FJC) JOB: 0417 TO: Attn: John Chandler CONTRACT NO:0417-035 The Tower Group, Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 Phone: (954) 476-3200 Fax: (954) 474-3111 RE: COR To: MCCM From: TTG Number: 00049 DESCRIPTION OF PROPOSAL Per the Engineers request to provide 3 way CHW Valves,ESSI respectfully requests a change order for the difference in cost between the 2 way&3 way valves. Belimo 2 way CHW valves: 2 Model B238NM24-SR $488.00 4 Model B248NM24-SR $1184.00 Total $1672.00 Belimo 3 way CHW valves: 2 Model B331ARB24-SR $652.00 4 Model B349ARB24-SR $1676.00 Total $2328.00 The difference in cost between 2 and 3 way valves is$656.00 Plus 10%profit& 10%overhead Request for Change order is$794.00 A quick response would be greatly appreciated;the valves have already been shipped to the site. (Contract only allows 5%profit&5%overhead). Item Description Stock# Quantity Units Unit Price Tax Rate Tax Amount Net Amount 00001 Difference in cost between 2& 1.000 tS $656.00 0.00% $0.00 $656.00 3 way valves Unit Cost: $656.00 Unit Tax: $0.00 Unit Total: $656.00 Subtotal: $656.00 Description Markup Percent Markup Amount Overhead 5.000% $32.80 Profit 5.000% $32.80 Sales Tax 7.500% $49.20 Total Cost: $770.80 Aqg 07 06 03:46p Anthony Burke "115-296-2587 p.2 vv. v. <c.Vv 1V.`1ll JO17J:3 I t55i tAbI PAGE 01/01 t7artrenlr ��ms SardAi,Paty�Lt' z2ss 9oca Ra[o�9ovrevar0_ Sufte r,n Boc Raton. Fin�IOa asvat August 7, 2006 The Tower Group, Inc. I 405 SW 148`h Avenue, suite #1 ; Davie, F'133325 Attu: Joan Chandler Fax#: 305-290-2587 Re: Freeman Justice Center RFCO#1 CHW Valve i Dear John: i As per the fin f p Engineers request to provide 3-way CHW Valves, T✓SSl respectfully request a change order for the difference in cost between the 2-way and 3-way valves. i Belimo 2-way CHW valves ' i Qnty. Req. Model# ESST's Cost Total { 2 B238 NM24-SR $244 each S 488: 4 B248 NM24-SR $296 each ILLM $1671 Selimo 3-way CHW valves Qnt3'. Req- Model# ESSI's Cost Total 2 B331 ARB24-SR $326 each S 6521 4 13349 ARB24-SR $419 each $1676 $23281 The difference in cost between 2-way and the 3-way valves is S656 Plus /a profit and overhead i The request for change order is.i-� 77v3. i pp i A quick response would be greatly appreciated; the valves have already been shipped to the site, If I can be of any further assistance please do not hesitate to cal] me. i Very trill ours, I ot► y outheast, LL Ste en S_ Fo I t Project Manager Boca Raton: (877) 455 9006 Paxr {561) 955 9007 i 08/07/2006 MON 15:43 [TX/RX NO 75861 10002 f Weathertrol Maintenance Corporation Pk%jPOSED CHANGE ORDER No. WT009 7250 NE 4th Ave. Phone: 305-908-1000 11 Miami,FL 33138 Fax: 305-908-1039 J TITLE:Change to 3-Way Control Valve DATE:8/8/2006 PROJECT:Freeman Justice Center(FJC) JOB: 0417 TO: Attn: John Chandler CONTRACT NO:0417-004 The Tower Group, Inc. 405 SW 148 Avenue Suite One Davie, FL 33325 Phone: (954) 476-3200 Fax: (954) 474-3111 RE: COR To: MCCM From: TTG Number: 00049 DESCRIPTION OF PROPOSAL Additional work to furnish and install bypass branch for the change from 2-way control valve to 3-way control valve,based on response to Project RFI#214. Item Description Stock# Quantity Units Unit Price Tax Rate Tax Amount Net Amount / 00001 Material by Weathertrol 1.000 LS $2,504.02 0.00% $0.00 $2,504.02/ 00002 Iabor by Weathertrol 1.000 LS $3.311.00 0.00% $0.00 $3,311.00 00003 Insulation Subcontractor 1.000 LS $550.00 0.00% $0.00 $550.00 Unit Cost: $6,365.02 Unit Tax: $0.00 Unit Total: $6,365.02 Subtotal: $6,365.02 Description Markup Percent Markup Amount 5% O/H on Items 1 &2 $290.75 Profit 5.000% $318.25 7.5% Sales Tax on Mat'ls $187.80 Total Cost: $7,161.82 By: By: Hector Ruiz John Chandler Date: Date: Expedition Aug 08 '06 Q3:21 p Anthony Burke q05-296-2587 p.1 hvu, d. lu�1c i :�orr� NO. 752 P. 1 CHANGE ORDER REQUEST eatbertro Ea Change Order Request#. 04.790.00'17 M�F i15rn Mai y.1�IJ�M/.VM Date: W712006 Project: Freeman Justice Center Project#: 04-790 To: The Tower Group @ Freeman Justice Center From: Weathertroi Attn: Jahn Chandlor Hector J, Ruiz 600 Whitehead St, 600 Whitehead Straet Key West, FL 33040 Key West, FL 33040 Ph.: (305)295-2521 Fax: (305)296-2687 Ph.: (305)9OB-1000 Fox: (305)W8-1039 We hereby propose to make the following changes: Change the two way control valve to three way control valve Change Order Price $B,A Original Contract Amount $1,259,385,00 This price Is good for 0 days, If conditions change,this price is void. { _ We are requesting a dme extension of 0 days in conjunction with this change, Hector J.Ruiz 8/7/2008 Author DateThe Tourer Group, Inc. Accepted The above prices and specifications of this Change Order request are satisfactory and are hereby accepted, AN work to be performed under same terms and conditions as specified in original contract unless otherwise specified. Authorized Signature Date of Acceptance OR/OR/2006 TT1F. 15: 18 TTX/RX Nn 7.1;RR1 r<'hOO1 Aug 08 06 03.21 p Anthony Burke 'n5-296-2587 p.2 NO, 752 P. 2 ! CHANGE ORDER REQUEST SUMMARY Project: Freeman Justice Center COR fP 04-790.0017 Labor UtxwType MHra SiHr uurdsn Fringe Tape Total Pipefilter 22 $65.00 $0.00 $0.c0 $0.00 $1,430,00 Welder 111 559.00 $0.00 $0.00 $0,00 $1.044.00 Helper Is 348.50 $0.00 $0.00 $0.00 $837,00 Subtclal $1311.00 Material Material Quanft Cast Tax Total Diaeleofric unions 9 $3110 $19.85 $303.35 Dlaelsclrloflaws 9 i<80,50 $41.60 �40.40 _Reducing Tees 6 $78.00 $32.97 $503.97 Buc SU pipe 20 $4.81 $0.73 1102.93 Plug vanes 0 $128.00 $53.78 $$21.76 Weld nedc flanges 6 $20.60 $8,61 $131.61 3ubtatal 52,604.02 Subcontracts ubcontractor DMzriptlon Tool Insulation Extra instdadcn for bypass cannection 9350.00 subtotal S68a.0o Total Cost $6.815.02 Overhead $62 � Profit Subcontract Markup Subcontract Band .Tatgf $8,63132�3. I 5 V 7 r j. nR/nR/9nnR TTTR 15.1R rTX/RX Nn 7GRR1 ri3tnn� The Tower Group, Ir �� v"EH REQUEN4 405 SW 148 Avenue No. 00050 Suite One Phone: (954)476-3200 Davie, FL 33325. Fax: (954)474-3111 TITLE: Room 93047 Artwork Lighting DATE: 8/9/2006 PROJECT:Freeman Justice Center (FJC) JOB: 0417 Monroe county Faclilties Devel ment TO: Attn: Clark Briggs CONTRACT NO: cr Monroe County Facilities Development AUG 2 2 2606 1100 Simonton Street KeyWest, FL 33040 rlrv(r: RECENED BY:e, Phone: (305) 295-4306 Fax: (305) 295-4321 RE: LTR To: TTG From: CSA Number: 06-07-20 DESCRIPTION OF PROPOSAL Change Order Request(COR)#50 addresses the cost to furnish and install additional lighting for the artwork being furnished under separate contract for Room#3047. This change was requested by CSA Architects, on behalf of the Owner,via the enslosed fax memo (3 pages). TTG proposes to furnish and install two(2)Omega Model#OM4-75MR16LV-RADJ-CS-EB fixtures,or two(2)Portfolio Model 9H7493T/DT-9473 fixtures for a Contract Price Increase of$515.87 and no change to the Contract Time. t Please forward a Change Orderas acceptance of this proposal and indicate the.desired fixture and lamps. Item Description `Stock# Quantity Units " Unit Price Tax Rate Tax Amount Net Amount 00001 Labor,Material&Equipment 1.000 LS S447.46 0.00% $0.00 $447.46 . by 17G Unit Cost: $447.46 Unit Tax: $0.00 Unit Total: $447.46 Subtotal: $447.46 Description Markup Percent Markup Amount Overhead % `�' ` � `�'--900-655.000% PC 0? $t 7 Profit 5.000% $22.37 Sales Tax on Mat'ls $23.67 Total Cost: -$-51 - � o0 oo .- cci• c� O h T CR LA tD r` m M m Lo (D LO M T Q CO at T N h J tfl64 Cl) 61) I�r J Q H O F- F- N 0 o y Q D w � = Nu`ny I— O O J Q o T C O T J 0 J O (O cD IxZ to uO O w to LO w M m F- J J w F- Z w � - CC to LA p;' T In t r LU uj tY ti -„ st C1 s � EE O N LL 'Q N V � T w C 2 O Z w L~L M Cl N o T A 03N3336 KEN �l OR �uaiudot�n�q sol�tllo�� A4unoo aojuow CURRIE - SOWARD5 - AGUILA - ARCHITECTS Architects, Planners & Interior Deslgners — AA 0002271 134 NE 11, Avenue, Delray Beach, Florida 33444 Monroe county Phone (561) 276-4951 Fax (561) 243-8184 e-mail rz2gcA�� �s slopment FACSIMILE RECEWD BY: To: YI From:io . . C Com ra nyi � Fax.No.: Re: Job No. "Date: # of pages - Including this.cover COMMENTS: _ .y� 4( .s a hr Gopy: �'� ;c:,+�► ��®� �spa... I� :._�...�, �� ®® ■®® ®,1®.t „_.®A ', ice; _ ;' Quo TATION Date: IS50 N.E.146 Street - Miami,Flarida33181 USA Quote: Carporate 0Mee:(305)947-5451- FAX(305)940-3450 Project: FREEDMAN JUSTICE CENTER www.farreystom - E-Mail: farreysfgateaet Page: 1 Quotation submitted b)r Prices quoted: F.0>3.Miami Monroe County facllltles Development Manny Maceim Prices valid for. 90DAYS Direct Line: (305) 919-0151 Lead torte: 60DAYS AUG 22 2006 Cellutar:005) 812-1313 (Ban ionavalabilitya+ofabrnedate) Terms: Prices quoted are based Presented in: THE TOWER GROUP listed. Anycharcges willirrRiaE �E.wtte. ATTN:JOSS CLAUSELL Order wilibe processed upon receipt of (1)Signed approved quotation; (2)Purchase Orderconfianing.quant s QCTANTIIY ?YF£,.'s CATALOCIV(TMMANDIZSCRIMON umTPRICH TCirALPSICE a &MGAOM4-7_W16LV-RADJ-CS-!B $155.00 $31000 S LOL MPS INCLUDED UBTOTAL LETE QUOTE MUST BE USED NOPARTIALS TAX UOTATIONSARE SUBJECT TO APPROVAL. AL TYPE: \LOGAI: Portfoliol PORTFOLIO DESCRIPTION SPECIFICATION FEATURES A low brightness 4 1/2"aperture C••-Aiming Mechanism through branch wiring. Six 1/2" low voltage/line voltage adjustable Stable lamp aiming and locking pry outs and 4 integral Romex accent fixture for a wide variety mechanism allows smooth 358e traps.Access to junction box of lamp types. Optics allow the -rotation and 350 elevation through panel in side of housing. lamp axis to pivot about the adjustment Lamp aiming scale lip center of the aperture at the enables consistent setting across H•-•Transformer d y ceiling line, allowing maximum multiple fixtures. 12V dual tap 120/277V magnetic y light output with no flashback. transformer mounted to ensure ` it 200 truncated cone allows full D --Socket Adapters quiet operation.Transformer can range and flexibility of aiming. Keyed quick connect plug allows be bypassed with SA99 socket interchangeable lamp types. Easy adapter for line voltage lamps. SPECIFICATION FEATURES -.installation via single spring clip. H74943DT has dual output 12/5.5VE...Housing' taps (for 5.5V PAR H7493T 9473 lampsamps))a as well as 1 20/277V input A.••Reflector .,One=piece die cast 1 deep'collar, transformer. H7493DT 9473 Spun 0.040" aluminum.Available -Housing is painted optical matte in low iridescent clear,haze, black to eliminate stray light. Insulation Detector straw, wheat and specular black F---U n i v e r s a l Mounting Self-resetting insulation detector Monr a County Alza0 finishes. Torsion springs Bracket opens circuit if insulation is FaClitles eveb pull trim tight to ceiling.Trim is improperly installed. j�TffiIl1Y t o 7 5 W Accepts 1/2"EMT, C Channel, MAX . keyed to prevent improper 'T bar fasteners and hanger bars. Labels orientation in housing. Provides 5"total adjustment. U.L. listed, C.S.A. certified, dam�'&Jffi 2 2006 M R 1 6 B...Trim Ring G -•Junction Box location, IBEW union made. 7 5 W M A X ' White painted die cast trim ring or ,Listed for eight/112g(four in, four TIME: - A R 7 O self flanged reflector. ,out) 90e C conductors feed RECENED BY:_,_ - R 1 1 1 P A R 3 6 P A R 2 0 P,AA30 i 4 1/2" ADJUSTABLE E............: (-- C e P .- = . ••••.•H SA90, SA91 7 i!4' oo" (184mml - - - F..:6 G A....�.......1............... i I SA93 SA94 8.............:............ 47l16' - - (tl3mml 5 118' (130mm1 Top View 5 3/4' [748mm1 O 17" SA96. SA99 (432mm1 NOTES: -Lamps not included Accessories should be ordered separately. I,_jl For additional options please consult your L— 13 112' —l Cooper Lighting Representative. (343mml '..Alzak is a registered trademark of Aluminum Company of America. ORDERING INFORMATION: Complete unit consists of housing, ballast and trim. Housing Options Trims Finish Options Socket Adapter Accessories H7493T=4'Low Voltage Directional DR37-DeRated r9471..Reflector, LI=Low WF=White Painted SA91=MR 16 75W Max H277=Step Down Transformer. with 1201277V Input TransformerWattage Label, ngedIridescent Clear Flange(Self Flanged SA93=A870 5OW Max 300VA Max H7493TCP-4'Low Voltage 37W Reflector, H=Haze only) SA94-ARI I 175W Max H826=C Channel Bar Hanger, Directional with 120/277VInput ORSO-DeRated rimRng, S=Straw _ SA96=PAR36 Sow Max 26'Long,Pair Translormer,Chicago Plenum Wattage Label, WH=Wheat SA99=Converts to 120V, HB50=C Channel Bar Hanger, H7493DT-4'Low Voltage Directional SOW WMH=Warm PAR201PAR30 75W Max 50'Long,Pair with 120/277V Input Transformer Haze RMS22=Wood Joist Bar and Dual Output of 12V and 5.5V 8=Black Hanger,22'Long,Pair H7493DTCP-4'Low Voltage W=White FK5=Field Installed Fuse Kit,5 Directional with 1201277V Input 88=Black Baffle Amp Transformer and Dual Output of 12V (9473.only) L200 SERIES=Optical Lenses and 5.5V,Chicago Plenum WB=White Baffle for PAR Lamps,use with LC30 (9473 only) Lens Clip LC30=lens Holder for PAR30 Lamps and L200 Series Lens COOPER LIGHTING ADV985100 H7493T 9473 H7493DT 9473 PHOTOMETRICS Fixture Performance Dataca�Elffl ``_ 'f� fry 1 � t i 30� 30 - D FC L W S D FC L W S D `1� iYED 2Y:""'a'W--S Lamp- - Beam Spread 01 Tilt Horizontal Illuminance 30°Tilt Horizontal Illuminance 300 Tilt Vertical Illuminance SOW PAR36 VNSP 8.5°x 8.5° 5'0' 452 1.0 1.0 116' 510, 288 1.5 1.5 1'0' 2'0' 336 2.0 1.0 1'0' 7'6' 201 1.5 2.0 110' 7'6' 128 2.0 2.0 2'0' 3'0' 150 3.0 2.0 2'0' 1010' 113 2.0 2.5 2'0' 10'0' 72 2.5 2.5 216' 4'0' 84 5.0 2.0 2'0' 12'6' 72 2.5 3.0 2'5' 12'6' 46 3.5 3.5 3'0' 510' 54 6.0 3.0 310' - D FC- L W - S 0 FC L W S D FC L W S Lamp Beam Spread 00 Tilt Horizontal Illuminance 300 Tilt Horizontal Illuminance 300 Tilt Vertical INuminance 35W AR/11/3/SS 3°x 3° 1010' Soo 1.5 1.5 1'6' 10'0' 318 2.0 1.5 116' S'0' 249 2.5 1.5 1'0' 12'6" 320 2.0.. . 2,0 1'6' 12'6" 204 2.5 2.0 2'0' 7'6' 111 4.0 2.0 2'0' 15'0' 222 2.0 2.0 2'0' 15'0' 141 3.0 2.5 2'0' 10'0' 62 5.0 3.0 2'6' 17'6" 163 2.5 2.5 2'6' 17'6' 104 3.5 3.0 2'6' 12'6' 20 9.0 5.0 4'0' 0 FC L W S D FC L W S D FC L W S Lamp Beam Spread 0°TJt'Horizontal Illuminance - 300 TJt Horizontal ISuminance 30°TIlt Vertical Illuminance -076W MR/6/NSP 14°x 14° 5'0" $82- 1.5 - 1.5 1'e' _ 5'0' 397 1.5 1.5 1'6" 2'0' 573 2.0 1.0 110, 7'6' 259 2.0 2.0 2'0' 7'6' 177 2.5 2.5 2'8' 3'0' 255 3.0 2.0 210' 10'0' 146 3.0 3.0 2'6' 1010' 99 3.5 3.5 3'0" 4'0' 143 5.0 2.0 2'0' 12'6' 93 - 3.57 3.5 3'0' 12'6' 64 4.0 4.0 3'8' 510' 92 6.0 3.0 3'0' D FC L W _ S D FC L W S D FC L W S Lamp- Beam Spread 00 Tilt Horizontal Illuminance 30°Tilt Horizontal Illuminance 30°Tilt Vertical Illuminance i Q75W MR16 FL 42?x 42° 5'0' 95 - 5.0 5.0� 4'01 5'0' 72 5.0 .4.0 4'0' 2'0' 161 3.0 2.0 2'0' 7'6' 42 7.5 7.5 5'6' 7.6' 32 7.5 6.5 610' 3'0" 72 5.0 3.0 3'0' 10'0'- 24 9.0 9.0 7'6' 1010' 18 10.5 8.5 8'0' 4'0' 40 7.0 4.0 4.0' 12'6' 15 --11.5 11.5 916' 12'8' 11 12.5 10.5 1010' 510" 26 10.0 5.0 510' O FC - L W S - D FC L W S O FC L W S Lamp- Beam Spread 0°Tilt Horizontal,llluminanca- 30°Tilt Horizontal illuminance 300 Tilt Vertical Illuminance AR70/,S/SP. 10°x 10° 510, 600_.. 1.5 1.5 1'6' 5'0' 404 I'S 1.0 110' 2'0'- 625 2.0 1.0 1'0' 7'6' 267 -_2.0 2.0 2'0' 7'8' 180 2.5 1.5 1'8' 3'0' 278 3.0 1.0 110' 10'0' 150 2.0 2.0 2'0' 1010' 101 3.5 I'S 116' 410' 156 4,0 1.0 110' 12'6' 96 3.5- 3.5 3'S" 12'6' 65 4.0 2.0 2'0' 5'01. 100 5.0 2.0 2'0' - D FC L W S D FC L W S D FC L W S '- - Lamp..- Beam Spread 00 Tat Horizontal IIlumin'ance .30°Tilt Horizontal Illuminance 30°Tilt Vertical Illuminance AR70150FL 30°x.30° 5'0' 164 - 2.5 - 2.5 2'6' 5'0' 60 2.0 2.0 2'0' 2'0" 133 3.0 1.0 1'0' 7'6' 36 3.0 30 310' 7'6' 27 5.0 5.0 510' 3'0" 59 4.0 1.0 110' 10'0' 20 - 5.0 5.0- 510" 10'0' 15 8.5 6.5 6'5' - 410' 33 6.0 2.0 2'0' 12'6' 13 6.5 6.5 610' 12'6' 10 8.5 8.5 8'0' 510' 21 7.0 2.0 2'0' D FC L W S D FC L . W S D FC L W S Lamp Beam Spread 0°Tilt Horizontal Illuminance 300 Tilt Horizontal Illuminance 30°TJt Vertical Illuminance 35AFI111/3/SP 10°x 10° 5'0" 560 1.0 1.0 110' 5'0' 357 I'S 1.S 1'8' 2'0' 435 2.0 1.0 1'0" 7'6' 249 I'S- 1.5 -115" 7'6' 159 2.5 2.0 2'0' 3'0' 193 2.5 1.5 1.0' 10'0' 140 2.0 2.0- 2'0" 1010' 89 3.0 2.5 216' 4'0' 109- 3.5 2.0 116' 12'6' 90 3.0 3.0 2'6' 12'6' 57 4.0 3.5 3'0' 510" 70 4.5 2-5 2'0' D FC L W S D FC L W S D FC L W S Lamp Beam Spread 0°Tilt Horizontal Illuminance 300 Tilt Horizontal Illuminance 300 Tilt Vertical Illuminance 75AR111110/SP 10°x 101 5'0' 1143 1.0 1.0 1'0' 5'0' 731 1.5 1.5 1'0' 2'0' 892 2.0 1.0 110" 7'6' 508 1.5 1.5 1'6' 7'6' 325 2.5 2.5 2'0' 3'0" 396 2.5 1.5 110" 10'0" 286 2.0 2.0 2'0' 10'0' 183 3.0 3.0 2'6" 4'0' 223 3.5 2.0 116, 12'6' 183 3.0 3.0 - 2'6' M IppanIT4,0 4.0 3'0' 5'0" 143 4.5 2.5 210" ?G�Ift 8S eV-t7pmen Diatencro �, From Watl 00.aetance Down 1 Notes: Rom Cai4ng *Illuminance values are cosine corrected initial values with no con ir (�l�lyi W .reffections from other room __ ___ surfaces.Total illumination may increase from contributions trom of $cr'b3" """ ""`-� �_-_-_-- *Changing fixture spacing will affect illuminance level. Oiaance Abny Wall a Illuminance in footcandles.Lux conversion factor: 1 FC=10.76 LUX No Speciticatioru and Oim-i-subiect to change without mild- / Visit our website at www.cooperiighting.com COOPER Lighting Customer First Center 1121 Highway 74 South Peachtree City,GA 30269 770.486.4800 FAX 770 468.4801 AOV985100 Cooper Lighting 5925 McLaughlin Rd.Mississauga,Ontario,Canada L5R 168 905.507-4000 FAX 905.568,7049 Aa!g 09 06 10:43a Anthony Burke 305-296-2587 p.2 the Tower Group, Inc`. - ANGE ORDER REQUEST )5 SW 148 Avenue No. 00051 :.uite One Phone: (954)476-3200 Davie, FL 33325 Fax: (954)474-3111 TITLE: 2nd & 3rd Floor Lobby Ltg. Changes DATE: 819/2006 PROJECT:Freeman Justice Center (FJC) JOB: 0417 Monroe County Fcacliffles Develo nt TO: Attn: Clark Briggs CONTRACT NO: Monroe County Facilities Development AUG 09 2006 1100 Simonton Street rIME: �. Key West, FL 33040 RECEIVED av: ,�� Plione: (305)295-4306 Fax: (305) 295-4321 RE: RFP To: From: Number: 06-05-18 DESCRIPTION OF PROPOSAL Change Order Request(COR)951 addresses the cost for the changes to the 2nd& 3rd floor lobby lighting based on the attached lighting specifications sheets(2 pages)and two unnumbered 2436 drawings signed "Approved" by Holly Elomina,and dated 5118106. These specification sheets and unnumbered drawings were subsequently incorporated into Drawing#I13-8, dated 7/2 P06, delivered to TTG by Monroe County on July 25,2006. TTG proposes Eo furnish and install the changed lighting for a Contract Price Increase of S20,429.91 and no change to the Contract Time. Please forward a Change Order as acceptance of this proposal. Item Description Stockg Quantity Units Unit Price Tax Rate Tax Amount Net Amount 00001 Labor,Material&Equipment 1.000 L,S _4tfiT 93 UON. $0.0o 5k�59s§S by TTG(See attached .9)L, _ /l✓breakdown, 1 page) Unit Cost: j4.0-5:1 , Unit Tax:: S0.00 Unit Total: $� Subtotal: Description Markup Percent Markup Amount Overhead/&s'ys-td 5.000% ?WS J4, "-7- :30 Profit /saes,�s )e 0 5.000% -"k3.), S&:7- 36 Sales Tax on Mat'ls $4��38 Total Cost: S20,429:71 I OSq, f � o ! 000 � o � ovoo coanC) ^ O O R N 't O N to C] C7 O 11 09 W ma 6 Lo W N 0 O Lo e- o Ci N r GD O CO J cm co r t� J � a 0 = wwwWwUUU H = O H � J O000inoU, 3 'm0 0 0 �� pq occ000P o ra o g Q O N [Y N Q •- "i �m V- p J tt � -J 0 0 0 0 r- It 00 O O t Z Q O O to O Q) r 0 a- C1 M 0 W W N HA N 69 60Q J F O 1 tfT to 69 v) J � d m H Q W ~O -i W Z wwwLU 10'ej L CD o CD 0 w w <DI= a* W UA O to O to N N r o? O V ti O 1-- O Ln m to N = O ptR11tRLn MetmIh O Q r w 40% � `n r Lw LJ W w W -j Ix = Q x X O ~ _ = w kt~.� cOwW0M L) WM W LL LL LL ti ti ry p V1 x Q CO 0000N � Qooi0 O Cq a m m O E- zluc,uwwwwwwww Qc0 C C1 O N to W 00 0 r i s 0-d Z89Z-96Z-90E mane Auoyluy eCV:O� 90 60 Bny - Aug 09 06 10:44a Anthony Burke 305-296-2587 p.4 { 1 1 � QUOTATION Date: 06/22106 1850 N.E.146 Street - Miami,Florida 33181 USA Quote: ADDED TYPES Corporate Office:(305)947-5451- FAX(305)940-3450 Project: FREEDMAN JUSTICE CENTER www.farreys.com - E-Mail: farreys@gate.net Page: 1 Quotation submitted by: Prices quoted: F.O.B. Miami Manny Maceiras Prices valid for: 90DAYS Direct Line: (305)919-0151 Lead time: 60DAY5 Cellular: (305)812-1313 (Bated on availability as of above date) Terms: Prices quoted are based upon quantities Presented to: TOWER CROUP listed. Any changes will invalidate quote. ATTN:JOSE CLAUSELL Order will be processed upon receiprof (1)Signed approved quotation; (2)Purchase Order confirming quantities QUANTITY TYPE CATALOG NUNIBER AND DESCRUMON UNIT PRICE TOTAL PRICE NEW FLYTCRES 9 OA S1,147.50 S1Q327,50 OB 3337.50 S2,025.00 PLUS FREIGHT ON BOTH ITEMS._..T.B.D. o r LL LAMPS INCLUDED SUBTOTAL Slzj52.50 COMPLETE QUOTE MUST BE I;SED,NO PARTIALS TAX S80'-.9t ALL QUOTATIONS ARE SUBJECT TO APPROVAL. TOTAL S13.1:5.,1 Aug 09 06 10:44a Anthony Burke 305-296-2557 p,5 American Glass Light Product Spec Sheet: Fixture Name: Betsey Uplight OA ,, ,... . . �. , s ,� Catalog : 5533-U Selected Width: 33" Selected Height: 37" (std.) Selected Lanping: (4) 26VV Quad Tube Compact FIUorescent Selected Glass/Panel: Black & White Sandblasted Glass Selectee Finish: Satin aluminum/nickel Additional Details: Weight for standard tamping 23".width: 10 Lbs. Weight for standard lamping 33 ' width: 30 Lbs. Uses (3) 60IN A lamps at 16" height. Please contact us for iamp specificaticn and ballast remoding information. Meta! halide lamping requires,remote ballast. Extension. `ption available. Dimensions, finishes, and lamping ship standard as listed unless special order options are requested. 120 volts is standard unless other voltage is ordered. Your Notes: When specifying this product, please indicate all selected options so we have complete information when an order is placed, 0 i ✓L/ htip��.americanglassl1Rht.com%SpecSheet.asp 5(17/2006 H.!g U�) I'S 1 U:44a Anthony Burke 305-296-2587 p.6 American Glass A ss Light Product Spec Sheet: Fixture Name: Lucy Sconce �r TV r. Catalog ?#: 18010-S - Selected Width: 10" Selected Height: 9 1 f2" Selected Lamping: (2) 40W Candelabra Selected GlassfPaneL V%rnite Sandblasted Glass (std) Selected Finish: Sa'in aluminum Additional Details: Projection: 4" Distance from top to center of wining box: 2 1/4" Weight standard Ia:-nping- 4 Lbs. Dimensions, finishes, tamping and voltage are standard as listed unless special order options are requested. 120 volts is standard unless other voltage is ordered. Your Notes: " When specifying this product, please indicate all selected options so we have complete information when an order is placed. ����tiv.americanglass tight com'SpecSheet.asp 5/1&`2406 MEMORANDUM TO: Board of County Commissioners From: Debbie L. Frederick County Administrator Date: October 19, 2006 RE: Change Orders Attached is a proposed change order for The Tower Group, for the Freeman Justice Center. (Change Order #21 in the amount of $26,085.72 is for Modification of Lighting, Credit for Door Hardware, Furnishing and Installing Control Valves and Bypass Branch for the Chilled Water System and Lighting and Artwork for Room#3047.) According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda A3 The Administrator intends to approve this change order on Friday, October 24 2006. Debbie L. Frederick Deputy County Administrator OLF:adc Page 1 of 1 Cyr-Connie From: Cyr-Connie Sent: Friday, October 20, 2006 9:14 AM To: County Commissioners and Aides Subject: Change Order Attachments: Change Order#21.PDF Please find attached Change Order #21 for The Tower Group, for the Freeman Justice Center. Connie Cyr Aide to the County Administrator The Historic Gato Cigar Factory 1100 Simonton Street,Suite 2.205 Key West,Florida 33040 Office 305-292-4441 Fax 305-292-4544 cyT-connie(kmonroecounty-11.gov_ HELP US HELP YOU.t Please take a moment to complete our Customer Satisfaction Survey: http:Z/monroesLirvey.-,irtualtoAnhafl.net/sLinTy.php?qaceiAaeib Please note:Florida has a very broad public records law. Most written communications to or from the County regarding County business are public records available to the public and media upon request. Your e-mail communication may be subject to public disclosure. 10/23/2006