32nd Change Order 05/11/2007 MONROE COUNTY / ENGINEERING /FACILITIES DEVELOPMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 32
Freeman Justice Center
Jackson Square INITIATION DATE: 05/11/07
Key West, FL
CONTRACT DATE: June 16, 2004
TO CONTRACTOR:
405 SW 148th Avenue Suite One
Davie, FL 33325
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price) ............................. .......... $13,804,000.00
Net change by previously authorized Change Orders ........................... .................... $ 2,116,361.42
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change Order was ......... $15,920,361.42
The (Contract Sum) (Guaranteed Maximum Price)will be (increased)(decreased)
(unchanged) by this Change Order ...... .......... '$ (654,619.03)
The new (Contract Sum) (Guaranteed Maximum Price) including this Change,Order is... $ 15,265,742.39
,The Contract Time will be (increased) (decreased) (unchanged)by ............................. N/A
The date of Substantial Completion as of the date of this Change Order is ..................... January 25, 2007
Detailed description of change order and justification:
Credit for the stone cladding and EIFS;on the exterior of the Freeman Justice Center:
Line#99 Cast Stone Materials less 5`%profit $244,761.90
Line#100 Cast Stone Labor less 5'%profit 244,761.90
Line#167 EIFS & Stucco less 5% from remaining balance 165,095.23
Total $654,619.03
This Change Order responds to Change Order Request#85
This change order is (4.7%) of the original contract price.
Not valid until signed by Owner, Construction Manager and Contractor
ARCHITECT: N/A
Date
CONTRACTOR:--
The Tower Group Date
DIRECTOR, FACILITIES DEVELOPMENT:
Jerry Barnett Date
COUNTY ENGINEER:
David S. Koppel, P.E. Date
COUNTY ADMINISTRATOR
Thomas Willi/Debbie Frederick-Deputy Date