32Rnd Change Order 05/16/2007 MONROE COUNTY / ENGINEERING /FACHMES DEVELOPMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 32R
Freeman Justice Center
Jackson Square INITIATION DATE: 05/16/07
Key West, FL
TO CONTRACTOR: CONTRACT DATE: June 16, 2004
405 SW 148th Avenue Suite One
Davie, FL 33325
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price) ........................................ $13,804,000.00
Net change by previously authorized Change Orders ................................................ $ 2,116,361.42
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change Order was ......... $15,920,381.42
The (Contract Sum) (Guaranteed Maximum Price)will be(increased) (decreased)
(unchanged) by this Change Order................. $ TBD
The new(Contract Sum) (Guaranteed Maximum Price) including this Change Order is ... $15,920,361.42
,The Contract Time will be (increased) (decreased) (unchanged) by ............................. WA
The date of Substantial Completion as of the date of this Change Order is ..................... January 25, 2007
Detailed description of change order and justification:
Removal of Cast Slone Claddina and EIFS from the Scope of Worlr-
Schedule of Values MOV111ne#99 and#100. Cast Stone Labor and Materials for 20'elevation and
below. SOV line#166 and#107 Foam Molding and EIFS and Stucco
CmW amount to be deftnn ned at a later date
This chanae order is 0%of the oriaJnal contract price.
Not valid until sianed by Owner Construction Manager and Contractor
ARCHITECT: NIA
Date
CONTRACTOR:
The Tower Group Date
DIRECTOR, FACILITIES DEVELOPMENT:
Jerry Barnett Date
COUNTY ENGINEER:
David S. Koppel, P.E. Date
COUNTY ADMINISTRATOR
Thomas Willi/Debbie Frederick-Deputy Date
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes® No❑
If Yes, explanation:
The E.I.F.S and Cast Stone was Included/n the original SpecHfcations. Owner decided
to install cast stone and brick veneer to the exterior of the building In lieu of E.I.F.S.
The credit will be determined at a later date.
Change Order was included in the original specifications. Yes❑ No
If Yes, explanation of increase in price:
• Change Order exceeds$25,000 or 5% of contract price(whichever is greater). Yes❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes❑ No
If no, explanation of why: The Architect was not under contract with us at the lime.
• Change Order is correcting an error or omission in design document. Yes❑No
Should a claim under the applicable professional liability policy be made? Yes❑ No
Explain: