04th Change Order 07/29/2005 MONROE COUNTY
ENGINEERING/CONSTRUCTION
CONTRACTE ORDER
PROJECT TITLE: Freeman Justice Center
CHANGE ORDER NO: 4
Date: July 21, 2005
Original Contract Amount $13,804,000.00
Total Previous Change Orders $ (27,720.00)
Current Change Order $ 14 069.83
Revised Contract Amount $13,790,349.83
% of Original Contract Amount 1.02%
% of Contract after Prior C/O's .9
Detailed description of change order and justification:
An existing sanitary sewer main was discovered and broken during excavation which necessitated sewage
pumping on a daily basis from the manhole at the north side of site. This change order represents
removal of sanitary sewage from this manhole for a period of 173 days starting November 9 2004 and
continuing thru July 12, 2005.
ARCHITECT: LI
Gonzalez Architects Date
CONTRACTOR: A- b,
The Tower Group Date
r
CONSTRUCTION MANAGER: - = '`- 2-�2- `
y Ch rs Date
COUNTY ENGINEER: '_
David S. Koppel, P.E. Date
I OUNTY ADMINISTRATOR
Thomas Willi
CMD007--11/03/97
MEM ORA 1VD UM
TO: Board of County Commissioners
From: Thomas J. Willi
County Administrator
Date: July 28, 2005
RE: Change Orders
Attached is a proposed change order for The Tower Group, for the Freeman
Justice Center . (Change Order #4 is for $14,069.83, for sewage pumping
resulting from a broken sewer main.)
According to the ordinance adopted by the Board of County Commissioners,
proposed change orders are to be presented to members of the Board of County
Commissioners prior to approval, assuming they are within the Administrator's
prescribed limits. Change orders not within the Administrator's authority are
placed on the BOCC agenda.
The Administrator intends to approve this change order on Friday , July 29,2005.
Thomas J Willi
)e-j�County Administrator
TJW-.adc
LETTER OF TRANSMITTAL
Date: August 03, 2005
MONROE COUNTY Attention: Jackie/Pam
Construction Management RE: The Tower Group/Change Order No. 4
1100 Simonton Street
Key West, Florida 33040
(305) 292-4429
ENCLOSED PLEASE FIND THE FOLLOWING ITEM(S):
DATE I COPIES I DESCRIPTION
1 7/29/05 Executed copy for your files.
THESE ARE TRANSMITTED AS CHECKED BELOW:
❑ Approved as Noted ❑Returned for Corrections ❑ Copies for Approval
REMARKS:
Jackie, Change Order No. 3 is being routed for signature.
�aAA 0
ay CurrV)
("Mf)025 9/11/95
LETTER OF Tp..ANsMITTAL
Date: August 03, 2005
MONROE COUNTY Attention: Greg GaImin
Construction Management RE: Change Order No. 4
1100 Simonton Street
Key West, Florida 33040
(305) 292-4429
ENCLOSED PLEASE FIND THE FOLLOWING ITEM(S):
-F—
NO. I DATE COPIES DESCRIPTION
1 7/29/05 Executed copy for your files.
THESE ARE TRANSMITTED AS CHECKED BELOW:
F-1 Approved as Noted F-IReturned for Corrections El Copies for Approval
REMARKS:
1--Gay- Curry1j,