1st Change Order 01/28/2020 .�ONROE COS / NGI EKING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: INITIATION DATE: December 13, 2019
Big Pine Key Community Park Lighting Repair
CHANGE ORDER NO: 1
TO CONTRACTOR: CONTRACT DATE: July 17,2019
Electrical Contracting Service, Inc.
2375 West 77 Street
Hialeah FL, 33016
The Contract is changed as follows:
The original(Contract hum) (Guaranteed Maximum Price)............................................$333,770.00
Net change by previously authorized Change Orders....a............. ............................$0.00
The(Contract SuM)(Guaranteed Maximum Price)prior to this Change order was.............$333,770.00
The (Contract Sum)(Guaranteed Maximum Price)will be increased by this Change Order..$48,850.00
The new(Contract Sum)(Guaranteed Maximum Price)including this Change Order is.......$382,620.00
The Contract Time will be(increased)by.................................................................. 60 Days
The date of Substantial Completion as of the date of this Change Order is.....................February 29, 2020
Detailed description of change order and justification:
Additional work to complete the,&hting re airs at SI Pine 1{e Ccr r rtrnr't Park. These Il hts were
inadvertently left of of the on inal RFP and are included on the Hurricane Irma FEIVIA re art. Darin
installation of the bat)rield ll hts it was d efernined there are to areas alon the walkin ath that remain
unlit. Seca se Big Pine lie Communi Park Is o erg until 9;00 .m, and holds re ular s ortln events after
sunset staff recommends.coon letion of the lj htln re air on the pathway for the safe and wellbeing of
the public. Original substantial date December 31 2011-new substantial cam letion dates Februart 29
2020.
Change order is 14.6° of on Inal contract price
Not valid until signed by Owner Architect if applicable),and Contractor
ARCHITECT: N/A
Date
/v
CONTRACTOR: .2 .)0
ate
DIRECTOR PROJECT MANAGEMENT
� Da e
AN 2020
COUNTY/ASSISTANT ADMINISTRATOR: 28_/ T
Rovnan Gastesi Date
Kevin Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes® No❑
If Yes, explanation: Inadvertently left off of the original RFP, however required repairs were
recognized in damage report dated February 28, 2019 and approved in the FEMA project#68387
• Change Order was included in the original specifications. Yes ❑ No 1U
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5% of contract price(whichever is greater). Yes ❑ NoO
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes❑ No�
If no, explanation of why: An architect was not utilized in this Project. Required repairs were
recognized in damage report dated February 28, 2019 and approved in the FEMA project#68387
• Change Order is correcting an error or omission in design document. Yes ❑No�
Should a claim under the applicable professional liability policy be made? Yes❑ No
ky
Explain:
Electrical Contracting Service, Inc. somata
2375 West 77th Street -----Hialeah,FL FL 33016 DATE ESTIMATE NO.
Send Payments To: 12/13/2019 2922
12101 Tara Dr, Plantation FL 33325
NAME/ADDRESS
Monroe County
Attn: Suzi Rubio
102050 Overseas Hwy., Suite 219
Key Largo, FL 33037
PROJECT
BigPineKeyPark...
DESCRIPTION QTY COST TOTAL
Big Pine Key Park Path Ir ighting
All necessary labor,material&equipment to complete
the following:
Provide& install 10- 15'mounting height poles to
match existing.
Provide& install 12-LSD fixtures to match existing.
Provide& install new wire&weatherproof splices to
path lights&parking lot lights.
Lot Cost ] 48,850.00 48,850.00
EXCLUDES-
Permit fee.(if required)
Repair of existing fixtures.
Repairing existing conduit if needed.
QUOTE IS OD FOR 60 DAYS FROM TODAYS DATE
TOTAL $48,850.00