Loading...
2nd Change Order 05/20/2020 MONROE CouNTY/ENGiNEERiNG/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: INITIATION DATE: May 15, 2020 Big Pine Key Community Park Lighting Repair CHANGE ORDER NO: 2 TO CONTRACTOR: CONTRACT DATE: July 17, 2019 Electrical Contracting Service, Inc. 2375 West 77 Street Hialeah, FL 33016 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price)............................................$333,770.00 Net change by previously authorized Change Orders...................................................$48,850.00 The 3 (Guaranteed Maximum Price)prior to this Change order was.............$382,620.00 The (Contract Sum) (Guaranteed Maximum Price)will be increased by this Change Order..$7,400.00 The new(Contract Sum) (Guaranteed Maximum Price) including this Change Order is.......$390,020.00 The Contract Time will be JUaqtgDggLd1 by............................ ..................................... 120 Days The date of Substantial Completion as of the date of this Change Order is.....................June 30, 2020 Detailed description of change order and justification: The scoreboard was damaged during Hurricane Irma and was intended to be replaced with in-house labor During reconstruction of the park, it was determined that the wiring would need to be replaced from the panel to the scoreboard. This change order is 0.022%of the original contract price. Not valid until signed by Owner, Architect(if applicable), and Contractor ARCHITECT: NIA Date CONTRACTOR: Date Digitally signed by Cary Knight DIRECTOR PROJECT MANAGEMENT Cary Knight Digitally 2020.05.19 10:11:29-04'00' Diqt.fly ig—d by K-im G.Wil—,'i, Wil_ 'Q DN:C_K, G RE,0—mo (the F 0'id.Key,—,­fl­i1,­-k­m@m­,­co­ty C_U' COUNTY/ASSISTANT ADMINISTRATOR: D.b,.2020.05.20 151439-0400' Roman Gastesi Date Kevin Wilson Christine Hurley Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Facilities Maintenance had intended to install a new scoreboard using in house resources, however it was determined the electrical component could not be met in house as Irma damage to the wiring was greater than originally anticipated. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ❑ No If no, explanation of why: Architect was not required for this project. • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: Electrical Contracting Service, Inc. Estimate 2375 West 77th Street Hialeah, FL 33016 DATE ESTIMATE NO. Send Payments To: 5/15/2020 2970 12101 Tara Dr, Plantation FL 33325 — NAME/ADDRESS Monroe County BOCC 500 Whitehead Street Key Wst, FL 33040 PROJECT Big Pine Comm ... DESCRIPTION CITY COST TOTAL Big Pine Community Park Scoreboard All necessary labor, material & equipment to complete the following: Mount new scoreboard on existing columns. Provide& install new wiring from panel to scoreboard & terminate. Lot Cost 1 7,400.00 7,400.00 EXCLUDES: W indload calculations for existing columns. Repair of damaged existing conduit system if needed. QUOT IS GOOD 60 DAYS FROM TODAYS DATE TOTAL $7,400.00