Loading...
06th Change Order 05/08/2020 MO COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDIER PROJECT TITLE: CHANGE ORDER NO., 006 Plantation Key Courthouse & Detention Center INITIATION DATE: April 15, 2020 COMMENCEMENT DATE: August 5, 2019 CONSTRUCTION DAYS: 913 TO CONTRACTOR APPROVED DELAY DAYS: 0 Biltmore Construction Company 1055 Ponce De Leon Blvd Belleair, FL 33756 The original (Contract Sum) (Guaranteed Maximum Price)-- $ 32,818,441.14 Net change by previously authorized by Amendments $ 202,086,00 Net change by previously authorized Change Orders $ (2,198,646.42) The (Contract Sum)(Guaranteed Maximum Price) prior to this Change order was $ 30,821,880.72 The (Contract Sum)(Guaranteed Maximum Price)will be (increased) (decreased) (unchanged) by this Change Order by $ The new(Contract Sum) (Guaranteed Maximum Price) including this Change Order,is $ 30,821,880.72 The Contract Time will be (increased) (decreased) (unchanged) by 38 The date of Substantial Completion upon approval of this Change Order will be March 13, 2022 Detailed description of change order andju,stification:U The construction schedule's critical path was delayed by a total of 38 days as redesign of the project site was required due to a faulty site survey provided by the County to Biltmore Construction Company, The 38 delay days is the complete compensation for the site survey delay. This Change Order is: 0.00% of the original contract price Not valid until signed by Owner, Architect(if applicable), and Contractor lys' ARCHITECT/DESIGNER: 4/27/2020 Date CONTRACTOR: Date t Digitally signed by Cary Knight Ca K n I ✓ h Date:2020.05.06 19:42:15 -04'00' DIRECTOR OF PROJECT MANAGEMENT: Date Digitally signed by Kevin G.Wilson,P.E. DN:cn=Kevin G.Wilson,P.E.,o=Monroe County, FL(the Florida Keys,ou,email=wilson- kevin@monroecounty-fl.gov,c=us COUNTY/ASSISTANT ADMINISTRATOR Date:2020.05.08 09:14:36-04'00' Date CHANGE ORDER LEDGER {7� PLANTATION KEY COURTHOUSE & DETENTION CENTER 4/14/2020 38 Clays $ (2,198,646.411) 01 ODP Generators 0 $ (684,007.00) 02 ODP PKG Lighting 0 $ (986,135.21) 03 ODP Gypsum 0 $ (235,144.21) 04 ODP concrete 0 $ (80,000.00) 05 ODP HVAC 0 $ (213,360.00) 06 Site Survey Delay 38 $