Loading...
1st Change Order 06/24/2020 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Lower Keys Pavement Preservation Project CHANGE ORDER NO: 1 INITIATION DATE:6116/20 TO CONTRACTOR: Pavement Technology Inc. CONTRACT DATE:4/15120 The Contract is changed as follows: The original Contract Sum ................................................... ..... ., ..... ., ..$616,866.35 Net change by previously authorized Change Order.............. ... .......................:......... $0 The Contract Sum prior to this Change order was................................................:....:•...$616,866.35 The Contract Sum is increased by this Change Order#1 ............................................... $10,336.00 The Revised 1 Contract Sum including this Change Order............................................$627,202.35 Due to Field measurement changes and varying widths county roads treated, total quantity increased by 10,880 square yards. At$.95 a square yard(per article 4.1 of contract),this equated to an ovorrua of$10,336.00. The project commencement was May 7,2020. Contractor agrees to accept the increase in monetary compensation and hereby elves and r leases any and all claims for any additional compensation related to these bi ,kms. This Change Order is(1.67%)of the original Tact puce. CONTRACTOR f� 6115� Date ENGINEERING SERVICES DIRECTOR /{1• ? �y�� Digitall J)iVttW by Kevin G.Wilson,P.E. DN:cn Kevin G.Wilson,P.E.,o=Monroe County,FL(the Florida Keys,ou,email=wilsonkevin@monroecounty-fl.gov,c=US ASSISTANT COUNTY ADMINISTRATOR W Date:2020.06.2410:42:43 04'00' Date i I Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No❑ If Yes, explanation: Due to field measurements and varying roadway widths, quantity of pavement treated increased. • Change Order was included in the original specifications. Yes❑ No If Yes, explanation of increase in price: • Change Order exceeds$25,000 or 5% of contract price(whichever is greater). Yes❑ No ED If Yes, explanation as to why it is not subject for a calling for bids: • Project engineer/architect approves the change order. Yes ❑ No ❑ If no, explanation of why: N/A • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: