05th Change Order 07/09/2020 MONROE Co Nw/ENGINEERINGI PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: #05 Monroe County Library and Adult Education INITIATION DATE: 06/23/2020 Center, Marathon Branch CONTRACT DATE: 03/21/2019 TO CONTRACTOR: Pedro-Falcon Contractors, Inc. 31160 Avenue C Big Pine Key, FL 33043 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price) ...........................................$ 7,016,385.00 Net change by previously authorized Change Orders-......................... .......... $ 294,897,33 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was .............$ 7,311,282.33 The (Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased) (unchanged) by this Change Order .............$ 2,906.96 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ......S 7314,189.29 The Contract Time will be (increased) (decreased) (unchanged) by................................. 7 Days The date of Substantial Completion as of the date of this Change Order is........................ 09/16/2020 Detailed description of change order and justification: During construction, the placement of under-window up-lighting on the exterior of the building was questioned. it was determined the glare from the lights would be detrimental to people inside the building after dark. After coordination with the Architect, it was determined the preferable placement of this accent lighting would be between the windows in lieu of beneath them. As a result, the size of the fixtures decreased, crediting the budget for this feature. However, the change in up-lighting placement resulted in re-work of the conduit already installed presenting a net contract increase of$2,906.96 for the required change. Increase Substantial Completion by 7 calendar days, from September 09, 2020 to September 16, 2020 due to estimated time required to complete the additional work. Change order is 0.04% of original contract price. Not valid until signed by Owner, Architect (if applicable), and Contractor ARCHITECT: Synaldy &fia'ffik Faye LLC Date / CONTRACTOR: - �7 e C Pedro-F can Contractors, Inc. Dare Cary Knight Digitally signed by Cary Knight DIRECTOR PROJECT MANAGEMENT Date:2020.07.07 14:38:10-04'00' Cary Knight, Director Date Project Management 1of2 Digitally signed by Kevin G.Wilson,P.E. DN:cn—Kevin G.Wilson,P.E.,o—Monroe County,FL (the Florida Keys,ou,email—wilson- kevin@monroecounty-fl.gov,c—US COUNTY/ASSISTANT ADMINISTRATOR: Date:2020.07.09 16:57:17-04'00' Roman Gastesi Date Kevin Wilson Christine Hurley Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: The additional cost stems from changing the planned exterior up-lighting fixtures and their respective locations after contract award. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ®No ❑ Should a claim under the applicable professional liability policy be made? Yes ® No ❑ Explain. The additional cost was generated by an error in the lighting design. All errors and omissions will be reviewed at the end of the project to determine if a claim should be made. 2 of 2 PEDRO FALCON CONTRACTORS, 31160 Avenue C, Big Pine Key, FL 33043-4516 (305) 872-2200 -Fax(305)672-2219 EC 13003416 f CGC 1507617 www.pedrofalcon.com Request for Change Order Revised 24 June 2020 Project: Marathon Library PCO Number: 014 Description: Lighting Revisions Exterior Fixtures T3 ..... ......M..r.e...n♦a�v........r.........y.......t.Y............................ ....-........./.{.".............+... Pedro Falcon Electrical Materials See Attached Breakdown..............................>............ ................+...,+,........,. ........$456.94 Credit Six T3 Fixtures/Revise to Ti SalesTax Included...........................................................................................<$4,200.00> Subtotal Materials........................................................................<$3,743.06> Equipment See Attached Breakdown (Manlift 2 Day).............-.. .....................................+,,..$300.00 SubtotalEquipment.............................................................................$500.00 Labor Add See Attached Breakdown........................ ..........................................$6,308.84 Credit Delete Six F3 Fixtures..............................................................................<$483.00> Subtotal Labor...................................................................................$5,825.84 1.}1'���.....��•�...•.��...r�kf/R�Y.k.�...�.....•Y�! •*♦ Yys�sfwww V,i1.M,Y1r►.Y.,1.M.i►.i•.�.!l�.M...1111• • �)Ii�....i1fi...�i.'...ak.• Industrial-Commercial-Institutional-Residential-Utility Established 1964 Subtotal.Labor/Materials/Equipment..........................................$2,5d2R78 Overhead @ 5%...................................►......w.................i....................$129.14 PrOfit@ 5%...w......................................................►.........................►..$12g.14 SalesTax on Materials.........................................................................$34.27 P&P Bond 1.1% of Total Cost...................................................... $31.63 1+.►IY�Y1;�.VR•Y�;;%;;'w;ww•T,TTTWiw.,w1'wTY'I..iiP.Y�.�Y;•.1.1ri'..fYV.i.•...Y4♦.w,;�;i ills iw.YY.wYlR!l�..�i.;��.li.i.A'Y►R►iRi.TA�.tk.• Total Requestfor Change Order Amount:......................................$2,go6.96 Additional Time Requested:........................................................................7 Calendar Days Respectfully Submitted, Ken Bygler Project Manager o" U? LLN tt �z d0 w 4 r- U Own my 10; J w a - z 0 o 117 o> a ra a o tool .Q n �y o +ostill n a o a w '� :69 4•i ut �ai ��'. F.n S5 � � C G � � u a v w Q a DATF RECAPULATION PEDRO FALCON SHEET ELECT.CONTRS.INC FOR SHEETNO.AND DESCRIPTION Mnt HA, Labor Haun 5W-141%af— Labor%areost LIGHTING S 456.94 109.50 100.0% 100.00% Branch Pawer $ - 0.00 0.04% fl.00'/a Switch Oe¢r $ - 0.00 0.00% fl.00% GENERATOR s - 0.00 0.00% 0.00% FI.Alarm $ - 0 0.04% C00-4 Seeudty Systems $ - 0.00 0.06% 0.00% C.—ID¢ta $ - 0 0.04% 0.00% CCTV 5 - 0 0.60% 0.00% Liehtn€nE PratecHou $ - 0.00 0.00% 000% PubOc Addre[s $ - 0.00 0.64% 0.00% Calhadlc Prntectlan S - 0,00 0.04% QA0% Mlle. S 0,00 0.00% fl.44•�e 109.50 100,001/1 10ox0% MISCELLANEOUS MATERIAL $ SUBTOTAL MATERIAL S 456.94 TOTAL MATERIAL COST ; 491.21 FORSMAtV`HODtis�S¢1ATE - .:3 -4300 k643$ $' 7S4 j3 "IOURN$Y11f.)"N}[017R:4:�.SRA`IS. : $ 35;00 }09 SQ,S ,''3,8�259 LABOR HOURS Q 5 RATE TRAVEL/NON PRODUCTIVE l OVERTIME S �AIRBL'I!)GA.BOR TOTAL PERMrT AND INSPECTION FEE S FUEL(GALLONS Q RATE) S - TELEPHONE S - FREIGHTEXPRESS AND CARTAGE $ - SPECIAL EQUIPMENT S - DRAWINGS S - SANITARY S - S S - EXPENSES,LODGING.MEALS S - PROJECT TRAVEL(#OF TRIPS aQ RATE) $ - TOOLS S TOTAL JOB EXPENSE S 2,231,22 TOTAL PRIME COST(MATERIAL/LABORIJOB EXP.) $ 7,300.05 OVERHEAD% 0% S - S 7,300.05 SUB-CONTRACTOR OUOTES FIRE ALARM LIGHTNTNG PROTECTION COMMUNICATIONS CATHODIC PROTECTION MrsC,Q11OTEs ,misc.QUOlms SUB-CONTRACTOR TOTAL S - Tax 0.0% S - SUB-CONTRACTOR GRAND TOTAL S - Sub Cuntr¢ctor Mark up -0.00% 0.00 0.00 TOTAL NET COST S 7,300,05 PROFIT•/. -0% $ - SUBTOTAL S 7,300,05 BOND �7, S - SELLINGPRICE Credit fnd-_-T50"ei DNLY flit Ius�IleHdrt-FO'MH3 54830 .-:. - ...-Total Chengc0[de[: ;5. -:'261T.65 5 u re F¢¢ta ern!rmaH¢n 5Q.FOOTAGE SQ.FT. SQ.FT COST #DlVf01 S .FT. Schedule Da[es: W ark Schedule: S lurtD¢te Da 5lWk 5 Cam tedon Date Hts.l Da $ Total Dura.tlon far C..tructlau 0 Wks. M.S. 0.0 Total Wark D¢ JREn Da Average Houm I.W"k 40 Hours Taml Dlrect Labor Ho." 1I0 Hours Aver¢ eAtrect Lsh¢r Crew Slxe 0.0 Meu Date: Jun 5, 2020 Quote: MIA19-133640-5 Quote Page 1/1 Power & Lighting Systems, Inc. 3832 Shipping Avenue Miami FL 33146 Phone: (305) 444-8520 Fax: (305) 445-1948 From: Jessica Hoyos Project Marathon Library and Adult Education Quoter Ph: (305) 444-8520x122 Center - New Design Email: jhoyos@p-Is.com Location Marathon FL Quote MIA19-133640-5 To: Craig Cowan For Pedro Falcon Electric ESI Bid Date Aug 27, 2019 13395 NW 107 AVE Expires Sep 26, 2019 Hialeah Gardens FL 33018 Architect: Synalovski Romanik Saye Phone: (305) 702-6001 Engineer: Delta G Engineers Fax: (305) 590-5709 EMail: Craig@electricalsuppliesinc.com Remarks: EC TO CONFIRM ALL TYPES &COUNTS: QTY Type M FG Part DEDUCT FOR TYPE T CHANGE 6/5120 6 T-T LUMP LOG RO 120 36 40K 1OX60 WAM12 SI NO ETE CRC $4,200.00 12 REVISE T-3'TO T-1' Total Deduct: $4,200.00 Notes: 1) INCLUDES WHIPS 2) LESS FUSES 3) INCLUDES CONTROLS AND SENSORS 4) DOES NOT INCLUDE ANY STEMS OR PENDANTS 5) DOES NOT INCLUDE TAX 6) DOES NOT INCLUDE SPARES 7) DOES NOT INCLUDE AN INVERTER(UNLESS NOTED) OR GENERATOR Power& Lighting Systems, Inc.- Miami Jessica Hoyos Page 111 ,E ���� _-■ :Illlll(11111111 � i � � �.��'��I �.o��, ® � � .I��_,. .�L�III : ■i�we�.�� ' ' e1111111111 �■ �� t :�� +ter � �� a� r�1, ii�ii[ilnlrint � 10 i�rwwri '. ��]11111�>~. �Z�►����� a r�.r err �1 111.0 ■.......■ ►�i'��. A;llil{I ll�Ill�i��� ® � � ��u��wr r��������� 1 ". '� 1111111 1 ON-I all OMNI N ® ,� •-�11111111! i �s®il pl�►UP1��� WORM F&Him, IIU IIIr1111e � �,�I� �iC � eeeee IIIII�1111r` 01 IS man a �.1IA1111111�14110OWNS TA 01 NON NON, MAW IRE 11111 1l = �1 11i� ii i ii i ii{)ii{muF'iI !� �illll�llllllll ���� _ r■ 11 1 �_ �; v0 04