Loading...
3rd Change Order 07/14/2020 MONROE o G T MMAGMENT CONTRACT CHANGE ORDER PROJECT TITLE: West Martello Ammo Bunker Repairs INITIATION DATE:05111/2020 CHANGE ORDER NO:03 TO CONTRACTOR: Innovative Masonry Restoration,LLC(IMR) CONTRACT DATE:0911812019 (NTP: 1211812019) The Contract is changed as follows: The original(Contract Sum) (Guaranteed Maximum Price}.................................. .s....... $ 223,000.00 Net change by previously authorized Change Orders ..............---...............--------------,.... 6,482.47 The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was.... .....e.,. $ 229,482.47 The(Contract Sum)(Guaranteed Maximum Price)will be(increased) (decreased) $ -, (unchanged)by this Change Order................... The new(Contract Sum) Guaranteed Maximum Price)including this Change Order is....... $ 229,482.47 The Contract Time will be(increased)(decreased)(unchanged)by.. . ............................. 46 days The date of Substantial Completion as of the date of this Change Order is... .................. 416/2020 Detailed description of change order and justification; This change rsrder is re ulred toad ast the contract days to the actual time ex eared. IMR proceeded with the work immediatelZ and continued without un-necessa dela - The work was finally corn feted and met the conditions of the contract. A certificate of substantial com l titrrr was a rtrvad b the Architect and the Court( on rt16 2020. The delay results in a NO—COST contract time extension of 46 days, This change order is 0.0%of the original contract price- Not valid until sl ned by Owner Arclrltect lif a llcabl and Contractor ARCHITECT: Data CONTRACTOR: ate Cary Knight Digitallysigned by Cary Knight DIRECTOR PROJECT MANAGEMENT Date:2020.07.1410:32:03''��-04'00' Digitally signed PWA.W ikon,P.E. ( DN KevnG WI PE o Monroe County FL(the Florida i� �+ mal wls k in@monroeco—yflgovc=US COUNTY/ASSISTANT ADMINISTRATOR Dat 2020.0].14121830 0400 1JYJ F T4h70.7 ADMINISTRATOR:4.i[� Roman Gastesi - gate..... Nevin Wilson Christine Hurley Change Order Aftachment per Ordinance No, 004-1999 Change Order was not included in the original contract specifications. Yes E] No Z If Yes, explanation- 49 Change Order was included in the original specifications. Yes C]No Z If Yes, explanation of increase in price: s Change Order exceeds$50,000 or 5%of contract price(whichever is greater)- Yes F1 No Z If Yes,explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes M No El If no, explanation of why: - • Change Order is correcting an error or omission in design document. Yes E]No N Should a claim under the applicable professional liability policy be made? Yes[I No Explain: