Item C11 BOARD OF COUNTY COMMISSIONERS
AGENDA ITEM SUMMARY
Meeting Date: March 19,2014 Division: Public Works/En ineerin
Bulk Item: Yes X No _ Department: Project Management
Staff Contact Person/Phone#: Kevin Wilson X8797
AGENDA ITEM WORDING: Approval to(1)award contract for ADA Segments 1 &2 Combined to D.
L. Porter Constructors,Inc. in the amount of$689,070.00, which represents the stated total Base Proposal minus
the Alternates, (2) to waive bid irregularity in the bid which included the alternate prices in the total base
proposal and(3) approval of contract in the amount of$689,070.00. If the contract cannot be executed at that
price, approval to award bid to the second highest bidder,Pedro Falcon Electrical Contractors,Inc., any contract
with Pedro Falcon will be brought back to the BOCC for approval.
This contract will be funded by a CDBG Grant, overseen by the DEO and by 304 funds.
ITEM BACKGROUND: On 2/13/14 proposals were received for the ADA Compliance Segments#1 
Combined project. 5 alternate proposals for additional work were requested in addition to the base proposal. A
total of four Contractors submitted proposals. After review, it appears D.L.Porter Constructors' proposal
included the cost of 5 alternate proposals in their base proposal. The RFP does not call for the alternates to be
included in the base proposal.Therefore,D L Porter either made a mistake by submitting the cost of Alternates
in their base proposal or they intended the base proposal to be $908,100. Because of budget limitations with the
CDBG Grant,none of the 5 alternates will be accepted. Staff is seeking approval to award the contract to D.L.
Porter Constructors at the total base price of$689,070.00, which excludes alternates, and to waive the
irregularity in the bid of adding the alternates to the base price. If D. L. Porter Constructors states that the base
bid of$908,100.00 and states that his price remains $908,100.00; then staff seeks approval to award the contract
to Pedro Falcon Electrical Contractors,whose base price proposal is $848,745.00.
PREVIOUS RELEVANT BOCC ACTION: June 19,2013, the BOCC terminated the original Contractor
on ADA Segments 1 &2 for violation of contracts. The Contractor filed suit against the County and on
November 18, 2013,the Contractor agreed to forfeit all claims to all monies held by the Clerk related to these
contracts. The lawsuit was dismissed. In February 2014, the County reissued an RFP for Segments I &2
Combined.This agenda item is for approval a Contractor to proceed with ADA compliance.
CONTRACT/AGREEMENT CHANGES: N/A
STAFF RECOMMENDATIONS: Approval as stated above.
TOTAL COST: $689,070.00 INDIRECT COST: N/A BUDGETED: Yes X No_
DIFFERENTIAL OF LOCAL PREFERENCE: N/A
COST TO COUNTY: N/A SOURCE OF FUNDS: CDBG
REVENUE PRODUCING: Yes _ No X AMOUNT PER MONTH Year
APPROVED BY: Coui:ity Atty,.&, (fI3/Purc: ,i ing Risk Management
DOCUMENTATION: Included X Not Required
DISPOSITION: AGENDA ITEM#
MONROE COUNTY BOARD OF COUNTY COMMISSIONERS
CONTRACT SUMMARY
Porter Contract with: D.L. Po er Constructors Contract#
Effective Date: 03/19/14
Expiration Date:
Contract to com Letee
Contract Purpose/Description:late the ADA Corn Hance for Se ants#1 and#2 Combined i
Contract Manager: Ann Ri er X4439 Pro"e+ct r1 mt/Sto #1
(Name) (Ext.) (Department/Stop#)
for BOCC meeting on 03/19/14 A enda Deadline: 03/04/14
CONTRACT COSTS
Total Dollar Value of Contract: $ 686,070.00 Current Year Portion: $ 686,070
Budgeted?Yes® No❑ Account Codes: -01 -O I1006- 4_0-
irant: $ 686,070 - - - -
County"Match:$ N/A - - - -
ADDITIONAL COSTS
Estimated Ongoing Costs: $_Jyr For:
(Not included in dollar value above) (ea.maintenance,utilitiesjanitorial,salaries,etc.)
CONTRACT REVIEW
Changes Date Out
Date In Needed ve r
Division Director Yes[:]N�
Risk Management YesE]No
O.M.B,/P"ur acing -"' Yes[ No[D `y-1
County Attorney 3 / "Yeses No
'" "a
Comments:
OMB Form Revised"7 'Ml MCP#
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
Agreement
Between Owner and Contractor
AGREEMENT
made as of the Nineteenth day of March in the year of Two Thousand Fourteen
(In Words, indicate day, month and year.)
BETWEEN the Owner: Monroe County Board of County Commissioners
(Name and address) 500 Whitehead Street
Key West, FloridaIT33040
and the Contractor: D.L. Porter Constructors, Inc.
(Name and address) 6574 Palmer Park Circle
Sarasota, FL 34238
For the following Project: ADA COMPLIANCE, SEGMENT# 1 & 2 Combined,
Monroe County, FL.
County Public Facilities
The work consists of numerous and varied construction projects created to update certain
County facilities and to bring the listed facilities into compliance with the Americans with
Disabilities Act of 1990 (ADA) and ADA Amendments Act of 2008. The facilities are located in
Monroe County, FL. The Contractor' work is as delineated in the project drawings which
describes in some detail the 32 - 37 Facilities, where the work will be required. The drawings
and technical specifications are necessary to insure compliance with ADA requirements and to
obtain required permits. If the ADA requirements differ between State and Federal
requirements, the "more stringent" requirement shall be used in construction.
Project Management: The Director of Project Management
1100 Simonton Street
Second Floor—Room 2-216
Key West, Florida 33040
The Owner and Contractor agree as set forth below.
ARTICLE 1
The Contract Documents
The Contract Documents consist of this Agreement, Conditions of the Contract (General,
Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to
execution of this Agreement, Contractors Proposal Documents, Requirements under the CDBG
and the ADA, Section 01750 CDBG Supplemental Conditionsl, and other documents listed in
........... -.. CONTRACT BETWEEN OWNER AND ..... .... ..�... ... ..... .. .... _..�
CONTRACTOR N
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
this Agreement and Modifications issued after execution of this Agreement: these form the
Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated
herein. The Contract represents the entire and integrated agreement between the parties
hereto and supersedes prior negotiations, representations or agreements, either written or oral.
An enumeration of the Contract Documents, other than Modifications, appears in Article 10.
ARTICLE 2
The Work of this Contract
The Contractor shall execute the entire Work described in the Contract Documents, except to
the extent specifically indicated in the Contract Documents to be the responsibility of others, or
as follows:
Scope of Work as specified in the Project Manual for this project, Section 00300.
ARTICLE 3
Date of Commencement and Substantial Completion
3.1 The date of commencement is the date to be fixed in a notice to proceed issued by the
Owner..
The Contractor shall achieve Substantial Completion of the entire Work not later than ninety
(90) calendar days after the date of commencement or issuance of a Notice to Proceed. The
time or times stipulated in the contract for completion of the work of the contract or of specified
phases of the contract shall be the calendar date or dates listed in the milestone schedule.
Liquidated damages will be based on the Substantial Completion Date for all work, modified by
ail approved extensions in time as set forth by the Director of Project Management's signature
of approval on the Certificate of Substantial Completion. The liquidated damages table below
shall be utilized to determine the amount of liquidated damages.
FIRST SECOND 31ST DAY &
CONTRACT AMOUNT 15 DAYS 15 DAYS THEREAFTER
Under$50,000.00 $50.00/Day $100.00/Day $250.00/Day
$50,000.00-99,999.00 100.00/Day 200.00/Day 750.00/Day
$100,000.00-499,999.00 200.00/Day 500.00/Day 2,000.00/Day
$500,000.00 and Up 500.00/Day 1,000.00/Day 3,500.00/Day
The Contractor's recovery of darn es and sole rem dy for.any delay cjV1qd_bX the Owner
shall be an extension of time on the Contract.
ARTICLE 4
Contract Sum
4.1 The owner shall pay the Contractor in current funds for the Contractor's performance of the
Contraact the Contract Sum of Six Hundred Eighty-Nine Thousand Seventy Dollars,
($689,070.00), subject to additions and deductions as provided in the Contract Documents.
4.2 The Contract Sum is based upon the following alternates, if any, which are described in
the Contract Documents and are hereby accepted by the Owner: N/A
� CONTRACT BETWEEN OWNER AND CONTRACTOR 2
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
4.3 Unit prices, if any, are as follows:
A. Underground electrical primary (trench, conduits, concrete protection)
Unit price per lineal foot of primary - Four Hundred Dollars and 00/100 ($400.00)
B. Underground electrical secondary
Unit price per lineal foot of secondary— Four Hundred Seventy-Five Dollars and
00/100 ($475.00)
C. Underground Sewer Line
Unit price per lineal foot of underground sewer line—Thirty-Five Dollars and
00/100 ($35.00)
D. Underground water line
Unit price per lineal foot of water line—Thirty-Five Dollars and 00/100 ($35.00)
E. Cost per foot of additional auger pile depth (assumed depth 10'-0" below existing
grade plus height of fill)
Unit price per additional lineal foot of pile—One Hundred Dollars and 00/100
($100.00)
The unit prices established above, and included in the response to proposals, shall be
used for scope of work that may be added beyond the original specifications as
determined by Owner.
ARTICLE 5
Progress Payments
5.1 Based upon Applications for Payment submitted by the Contractor to the Director of
Project Management, and upon approval for payment issued by the Director of Project
Management, the Owner shall make progress payments on account of the Contract Sum to the
contractor as provided below and elsewhere in the Contract Documents.
5.2 The period covered by each Application for payment shall be one calendar month ending
on the last day of the month, or as follows:
5.3 Payment will be made by the Owner in accordance with the Florida Local Government
Prompt Payment Act, section 218.735, Florida Statutes.
5.4 Each Application for Payment shall be based upon the Schedule of Values submitted by
the Contractor in accordance with the Contract Documents. The Schedule of Values shall
allocate the entire Contract Sum among the various portions of the Work and be prepared in
such form and supported by such data to substantiate its accuracy as the Director of Project
Management may require. This schedule, unless objected to by the Director of Project
Management, shall be used as a basis for reviewing the Contractor's Applications for Payment.
5.5 Applications for Payment shall indicate the percentage of completion of each portion of
the Work as of the end of the period covered by the Application for Payment.
5.6 Subject to the provisions of the Contract Documents, the amount of each progress
payment shall be computed as follows:
5.6.1 Take that portion of the Contract Sum properly allocable to completed Work as
determined by multiplying the percentage completion of each portion of the Work by the share
of the total Contract Sum allocated to that portion of the Work in the Schedule of Values, less
retainage. Pending final determination of cost to the Owner of changes in the Work, amounts
not in dispute may be included in applications for Payment. The amount of credit to be allowed
by the Contractor to the Owner for a deletion or change which results in a net decrease in the
Contract Sum shall be net cost to the Owner as indicated in the approved Schedule of Values
C,0N`I RAC I"BETWEEN OWNER.AND CONTRACTOR 3
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
for that line item as confirmed by the Director of Project Management. When both additions and
credits covering related Work or substitutions are involved in a change the allowance for
overhead and profit shall be figured on the basis of net increase, if any, with respect to that
change.
5.6.2 Add that portion of the Contract Sum properly allocable to materials and equipment
delivered and suitably stored at the site for subsequent incorporation in the completed
construction (or, if approved in advance by the Owner, suitably stored off the site at a location
agreed upon in writing), less retainage;
5.6.3 Subtract the aggregate of previous payments made by the Owner; and
5.6.4 Subtract amounts, if any, for which the Director of Project Management has withheld or
nullified a Certificate for Payment as provided in Paragraph 9.5 of the General Conditions.
5.7 Retainage will be withheld in accordance with section 218.735 (8), Florida Statutes
5.8 Reduction or limitation of retainage, if any, shall be as follows:
Monroe County is exempt from and not subject to Florida Statutes 255.078, "Public Construction
Retainage". Reduction or limitation of retainage, if any, shall be reduced incrementally at the
discretion of and upon the approval of the Director of Project Management.
ARTICLE 6
Final Payment
Final Payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the
Owner to the Contractor when (1) the Contract has been fully performed by the Contractor
except for the Contractor's responsibility to correct nonconforming Work as provided in
Subparagraph 12.2.2 of the General Conditions and to satisfy other requirements, if any, which
necessarily survive final payment, and (2) a final approval for payment has been issued by the
Director of Project Management. Such final payment shall be made by the Owner not more
than 20 days after the issuance of the final approval for payment. The following documents
(samples in Section 001027) are required for Final Payment:
(1) Application and Certificate for Payment
(2) Continuation Sheet
(3) Certificate of Substantial Completion
(4) Contractor's Affidavit of Debts and Claims
(5) Contractor's Affidavit of Release of Liens
(6) Final Release of Lien
ARTICLE 7
INSURANCE
7.1 The CONSULTANT shall obtain insurance as specified and maintain the required
insurance at all times that this Agreement is in effect. In the event the completion of the
project (to include the work of others) is delayed or suspended as a result of the
CONSULTANT'S failure to purchase or maintain the required insurance, the
CONTRACT BETWEEN
..OWNER AND CONTRACT..__
O 4
ADA COMPLIANCE SE
GMENT# 1 & 2 COMBINED
CONSULTANT shall indemnify the COUNTY from any and all increased expenses
resulting from such delay.
7.2 The coverage provided herein shall be provided by an insurer with an A.M. Best rating of
VI or better, that is licensed to business in the State of Florida and that has an agent for
service of process within the State of Florida. The coverage shall contain an
endorsement providing sixty (60) days notice to the COUNTY prior to any cancellation
of said coverage. Said coverage shall be written by an insurer acceptable to the
COUNTY and shall be in a form acceptable to the COUNTY.
7.3 CONSULTANT shall require its subconsultants to be adequately insured at least to the
Limits prescribed above, and to any increased limits of CONSULTANT if so required by
COUNTY during the term of this Agreement. COUNTY will not pay for increased limits of
Insurance for CONSULTANT or subconsultants.
7.4 CONSULTANT shall provide to the COUNTY certificates of insurance or a copy of all
insurance policies including those naming the COUNTY as an additional insured. The
COUNTY reserves the right to require a certified copy of such policies upon request.
7.5 If the CONSULTANT participates in a self-insurance fund, a Certificate of Insurance shall
be required. In addition, the CONSULTANT may be required to submit updated financial
statements from the fund upon request from the COUNTY.
7.6 INSURANCE REQUIREMENTS:
Worker's Compensation Statutory Limits
Employer Liability $1,000,000/$1,000,000/$1,000,000
General Liability, Including Premise Operation; Blanket Contractual, Expanded Definition of
Property Damage; Products and Completed Operations; Personal Injury; Underground,
Explosion and Collapse (XCU). $1,000,000 Combined Single Limit
Or
$ 500,000 per Person
$1,000,000 per Occurrence
$ 100,000 Property Damage
Monroe County BOCC must be named as additional) iris,red earn the General L.iabilit�loli
Vehicle Liability (Owned, nonowned, and hired vehicles)
$1,000,000 Combined Single Limit
Or
$ 500,000 per Person
$1,000,000 per Occurrence
$ 100,000 Property Damage
Monroe Count BOCC must be named as additionallv insured on the Vehicle Liabilit Policy.
Builders' Risk will be required on sites when there are structural alterations on a building.
Coverage shall include: Theft, Windstorm, Hail, Explosion, Riot, Civil Commotion, Aircraft,
Vehicles, Smoke, Fire, Collapse, and Flood. The policy limits shall be no less than the amount
of the finished project and coverage shall be provided on a completed value basis. Property
located on the construction premises, which is intended to become a permanent part of the
building, shall be included as property covered. The policy shall be endorsed permitting the
County to occupy the buiding prior to completion witout effecting the coverage.
.w .._. .. .. .. _....._ ........... .......
CONTRACT BETWEEN OWNER AND CONTRACTOR 5
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
Monroe County f O� C must be named as additionally insured and Loss Pa g on Builders"
Risk.
ARTICLE 8
Miscellaneous Provisions
8.1 Where reference is made in this Agreement to a provision of the General Conditions or
another Contract Document, the reference refers to that provision as amended or supplemented
by other provisions of the Contract Documents.
8.2 Payment shall be made according to the Florida Local Government Prompt Payment
Act.
8.3 Temporary facilities and services: As described in Section 01500 of the General
Requirements.
8.4 Monroe County's performance and obligation to pay under this contract is contingent
upon an annual appropriation by the Board of County Commissioners.
8.5 A person or affiliate who has been placed on the convicted vendor list following a
conviction for public entity crime may not submit a bid on a contract to provide any goods or
services to a public entity, may not submit a bid on a contract with a public entity for the
construction or repair of a public building or public work, may not submit Proposals on leases of
real property to public entity, may not be awarded or perform work as contractor, supplier,
subcontractor, or consultant under a contract with any public entity, and may not transact
'business with any public entity in excess of the threshold amount provided in Section 287.017,
for CATEGORY TWO for a period of 36 months from the date of being placed on the convicted
vendor list.
8.6 Contractor shall determine all permits, impact fees, inspections, testing and survey
(and fees required by same) required by Federal, State, Municipal or Utility bodies having
jurisdiction over the project. The cost of all such permits, impact fees, inspections, testing, and
surveys for the project site/building shall be paid by the Contractor. The Contractor is required
to secure all such.permits impact tees inspections, testin ,,_1yrve 9d to rovide all
_.
installation ermittin reqire fr,the execration of the Contract. The Contractor is responsible
for any and all building permit costs or impact fees required for the substantial completion of this
project.
8.7 The Contractor/Proposer shall be responsible to secure and pay for all testing services
of an independent testing laboratory to perform specified inspections and testing as indicated in
Technical Specification Sections and as required by the contract or governing authorities.
Contractor/Proposer shall include the cost of all inspection and testing fees in his proposal.
8.8 PUBLIC RECORDS: The Contractor agrees to comply with all requirements of Chapter
119 of the Florida Statutes and specifically:
(a) Keep and maintain public records that ordinarily and necessarily would be required
by the public agency in order to perform the service.
(b) Provide the public with access to public records on the same terms and conditions
that the public agency would provide the records and at a cost that does not exceed
the cost provided in this chapter or as otherwise provided by law.
(c) Ensure that public records that are exempt or confidential and exempt from public
records disclosure requirements are not_disclosd except as authorized by law.
.._.. CONT. r .cr BETWEENmOWNER AND CONTRACTOR a._. .� .. ... ._ _. ....U. ... . . ..........
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
(d) Meet all requirements for retaining public records and transfer, at no cost, to the
public agency all public records in possession of the Contractor upon termination of
the contract and destroy any duplicate public records that are exempt or confidential
and exempt from public records disclosure requirements. All records stored
electronically must be provided to the public agency in a format that is compatible
with the information technology systems of the public agency.
8.9 Individual Facility Substantial Completion, as used herein shall mean that point at
which, as approved in writing by Project Management, advising the Contractor that the
individual facility is at a level of completion such that the Owner or its designee can enjoy
beneficial use or occupancy and can use or operate it in all respects for its intended purpose.
This is separate and distinct from substantial completion of the entire project, and partial use or
occupancy of an individual facility shall not result in the Project being deemed substantially
complete and such partial use or occupancy shall not be evidene of Substantial Completion.
8.10 The following items are included in this contract:
a) Contractor shall maintain all books, records, and documents directly pertinent to
performance under this Agreement in accordance with generally accepted accounting principles
consistently applied. Each party to this Agreement or their authorized representatives shall
have reasonable and timely access to such records of each other party to this Agreement for
public records purposes during the term of the Agreement and for four years following the
termination of this Agreement. If an auditor employed by the County or Clerk determines that
monies paid to Contractor pursuant to this Agreement were spent for purposes not authorized
by this Agreement, the Contractor shall repay the monies together with interest calculated
pursuant to Sec. 55.03, FS, running from the date the monies were paid to Contractor.
b) Governing Law, Venue, Interpretation, Costs, and Fees: This Agreement shall be
governed by and construed in accordance with the laws of the State of Florida applicable to
contracts made and to be performed entirely in the State. In the event that any cause of action
or administrative proceeding is instituted for the enforcement or interpretation of this Agreement,
the County and Contractor agree that venue shall lie in the appropriate court or before the
appropriate administrative body in Monroe County, Florida. The Parties waive their rights to trial
by jury.
c) Severability. If any term, covenant, condition or provision of this Agreement (or the
application thereof to any circumstance or person) shall be declared invalid or unenforceable to
any extent by a court of competent jurisdiction, the remaining terms, covenants, conditions and
provisions of this Agreement, shall not be affected thereby; and each remaining term, covenant,
condition and provision of this Agreement shall be valid and shall be enforceable to the fullest
extent permitted by law unless the enforcement of the remaining terms, covenants, conditions
and provisions of this Agreement would prevent the accomplishment of the original intent of this
Agreement. The County and Contractor agree to reform the Agreement to replace any stricken
provision with a valid provision that comes as close as possible to the intent of the stricken
provision.
d) Attorney's Fees and Costs. The County and Contractor agree that in the event any
cause of action or administrative proceeding is initiated or defended by any party relative to the
enforcement or interpretation of this Agreement, the prevailing party shall be entitled to
reasonable attorney's fees and court costs as an award against the non-prevailing party, and
shall include attorney's fees and in appellate proceedings. Mediation proceedings initiated and
conducted pursuant to this Agreement shall be in accordance with the Florida Rules of Civil
__. _... _...... ..., .,. w.a�..... ..., .....,. ..... _
CONTRACT BETWEEN OWNER AND CONTRACTOR 7
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
Procedure and usual and customary procedures required by the Circuit Court of Monroe
County.
e) Binding Effect. The terms, covenants, conditions, and provisions of this Agreement
shall bind and inure to the benefit of the County and Contractor and their respective legal
representatives, successors, and assigns.
f) Authority. Each party represents and warrants to the other that the execution,
delivery and performance of this Agreement have been duly authorized by all necessary County
and corporate action, as required by law.
g) Claims for Federal or State Aid. Contractor and County agree that each shall be, and
is, empowered to apply for, seek, and obtain federal and state funds to further the purpose of
this Agreement; provided that all applications, requests, grant proposals, and funding
solicitations shall be approved by each party prior to submission.
h) Adjudication of Disputes or Disagreements. County and Contractor agree that all
disputes and disagreements shall be attempted to be resolved by meet and confer sessions
between representatives of each of the parties. If the issue or issues are still not resolved to the
satisfaction of the parties, then any party shall have the right to seek such relief or remedy as
may be provided by this Agreement or by Florida law. This Agreement is not subject to
arbitration.
i) Cooperation. In the event any administrative or legal proceeding is instituted against
either party relating to the formation, execution, performance, or breach of this Agreement,
County and Contractor agree to participate, to the extent required by the other party, in all
proceedings, hearings, processes, meetings, and other activities related to the substance of this
Agreement or provision of the services under this Agreement. County and Contractor
specifically agree that no party to this Agreement shall be required to enter into any arbitration
proceedings related to this Agreement.
j) Nondiscrimination. County and Contractor agree that there will be no discrimination
against any person, and it is expressly understood that upon a determination by a court of
competent jurisdiction that discrimination has occurred, this Agreement automatically terminates
without any further action on the part of any party, effective the date of the court order. County
or Contractor agree to comply with all Federal and Florida statutes, and all local ordinances, as
applicable, relating to nondiscrimination. These include but are not limited to: 1) Title VI of the
Civil Rights Act of 1964 (PL 88-352) which prohibits discrimination on the basis of race, color or
national origin; 2) Title IX of the Education Amendment of 1972, as amended (20 USC ss.
1681-1683, and 1685-1686), which prohibits discrimination on the basis of sex; 3)
Section 504 of the Rehabilitation Act of 1973, as amended (20 USC s. 794), which prohibits
discrimination on the basis of handicaps; 4) The Age Discrimination Act of 1975, as amended
(42 USC ss. 6101- 6107) which prohibits discrimination on the basis of age; 5) The Drug
Abuse Office and Treatment Act of 1972 (PL 92-255), as amended, relating to nondiscrimination
on the basis of drug abuse; 6) The Comprehensive Alcohol Abuse and Alcoholism Prevention,
Treatment and Rehabilitation Act of 1970 (PL 91-616), as amended, relating to
nondiscrimination on the basis of alcohol abuse or alcoholism; 7) The Public Health Service Act
of 1912, ss. 523 and 527 (42 USC ss. 690dd-3 and 290ee-3), as amended, relating to
confidentiality of alcohol and drug abuse patent records; 8) Title VIII of the Civil Rights Act of
1968 (42 USC s. et seq.), as amended, relating to nondiscrimination in the sale, rental or
financing of housing; 9) The Americans with Disabilities Act of 1990 (42 USC s, 1201 Note), as
maybe amended from time to time, relating to nondiscrimination on the basis of disability; 10)
CONTRACT BETWEEN OWNER AND CONTRACTOR 8
ADA COMPLIANCEwSE SEGMENT#.� COMBINED
rz,... .. .. ..................
Any other nondiscrimination provisions in any Federal or state statutes which may apply to the
parties to, or the subject matter of, this Agreement.
k) Covenant of No Interest. County and Contractor covenant that neither presently has
any interest, and shall not acquire any interest, which would conflict in any manner or degree
with its performance under this Agreement, and that only interest of each is to perform and
receive benefits as recited in this Agreement.
1) Code of Ethics. County agrees that officers and employees of the County recognize
and will be required to comply with the standards of conduct for public officers and employees
as delineated in Section 112.313, Florida Statutes, regarding, but not limited to, solicitation or
acceptance of gifts; doing business with one's agency; unauthorized compensation; misuse of
public position, conflicting employment or contractual relationship; and disclosure or use of
certain information.
m) No Solicitation/Payment. The County and Contractor warrant that, in respect to
itself, it has neither employed nor retained any company or person, other than a bona fide
employee working solely for it, to solicit or secure this Agreement and that it has not paid or
agreed to pay any person, company, corporation, individual, or firm, other than a bona fide
employee working solely for it, any fee, commission, percentage, gift, or other consideration
contingent upon or resulting from the award or making of this Agreement. For the breach or
violation of the provision, the Contractor agrees that the County shall have the right to terminate
this Agreement without liability and, at its discretion, to offset from monies owed, or otherwise
recover, the full amount of such fee, commission, percentage, gift, or consideration.
n) Public Access. The County and Contractor shall allow and permit reasonable access
to, and inspection of, all documents, papers, letters or other materials in its possession or under
its control subject to the provisions of Chapter 119, Florida Statutes, and made or received by
the County and Contractor in conjunction with this Agreement; and the County shall have the
right to unilaterally cancel this Agreement upon violation of this provision by Contractor.
o) Non-Waiver of Immunity. Notwithstanding the provisions of Sec. 768.28, Florida
Statutes, the participation of the County and the Owner in this Agreement and the acquisition of
any commercial liability insurance coverage, self-insurance coverage, or local government
liability insurance pool coverage shall not be deemed a waiver of immunity to the extent of
liability coverage, nor shall any contract entered into by the County be required to contain any
provision for waiver.
p) Privileges and Immunities. All of the privileges and immunities from liability,
exemptions from laws, ordinances, and rules and pensions and relief, disability, workers'
compensation, and other benefits which apply to the activity of officers, agents, or employees of
any public agents or employees of the County, when performing their respective functions under
this Agreement within the territorial limits of the County shall apply to the same degree and
extent to the performance of such functions and duties of such officers, agents, volunteers, or
employees outside the territorial limits of the County.
q) Legal Obligations and Responsibilities: Non-Delegation of Constitutional or Statutory
Duties. This Agreement is not intended to, nor shall it be construed as, relieving any
participating entity from any obligation or responsibility imposed upon the entity by law except
to the extent of actual and timely performance thereof by any participating entity, in which case
the performance may be offered in satisfaction of the obligation or responsibility. Further, this
Agreement is not intended to, nor shall it be construed as, authorizing the delegation of the
.. _mw.. ...�..... _ ....-_ .. _ .._. ...�..._.............. . . . ......_. .......
CONTRACT BETWEEN OWNER AND CONTRACTOR 9
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
constitutional or statutory duties of the County, except to the extent permitted by the Florida
constitution, state statute, and case law.
r) Non-Reliance by Non-Parties. No person or entity shall be entitled to rely upon the
terms, or any of them, of this Agreement to enforce or attempt to enforce any third-party claim or
entitlement to or benefit of any service or program contemplated hereunder, and the County and
the Contractor agree that neither the County nor the Contractor or any agent, officer, or
employee of either shall have the authority to inform, counsel, or otherwise indicate that any
particular individual or group of individuals, entity or entities, have entitlements or benefits under
this Agreement separate and apart, inferior to, or superior to the community in general or for the
purposes contemplated in this Agreement.
s) Attestations. Contractor agrees to execute such documents as the County may
reasonably require, to include a Public Entity Crime Statement, an Ethics Statement, and a
Drug-Free Workplace Statement.
t) No Personal Liability. No covenant or agreement contained herein shall be deemed
to be a covenant or agreement of any member, officer, agent or employee of Monroe County in
his or her individual capacity, and no member, officer, agent or employee of Monroe County
shall be liable personally on this Agreement or be subject to any personal liability or
accountability by reason of the execution of this Agreement.
u) Execution in Counterparts. This Agreement may be executed in any number of
counterparts, each of which shall be regarded as an original, all of which taken together shall
constitute one and the same instrument and any of the parties hereto may execute this
Agreement by signing any such counterpart.
v) Section Headings. Section headings have been inserted in this Agreement as a
matter of convenience of reference only, and it is agreed that such section headings are not a
part of this Agreement and will not be used in the interpretation of any provision of this
Agreement.
w) Disadvantaged Business Enterprise (DBE) Policy and Obligation. It is the policy of
the County that DBE's, as defined in C.F.R. Part 26, as amended, shall have the opportunity to
participate in the performance of contracts financed in whole or in part with County funds under
this agreement. The DBE requirements of applicable federal and state laws and regulations
apply to this Agreement. The County and its Contractor agree to ensure that DBE's have the
opportunity to participate in the performance of the Agreement. In this regard, all recipients and
contractors shall take all necessary and reasonable steps in accordance with applicable federal
and state laws and regulations to ensure that DBE's have the opportunity to compete and
perform contracts. The County and Contractor and subcontractors shall not discriminate on the
basis of race, color, national origin or sex in award and performance of contracts, entered
pursuant to this Agreement.
x) Hold Harmless and Indemnification: Notwithstanding any minimum insurance
requirements prescribed elsewhere in this agreement, the Contractor covenants and agrees that
he shall indemnify and hold the COUNTY and the COUNTY's elected and appointed officers
and employees harmless from and against (i) claims, actions or causes of action, (ii) litigation,
administrative proceedings, appellate proceedings, or other proceedings relating to any type of
injury (including death), loss, damage, fine, penalty or business interruption, and (iii) costs or
expenses that may be asserted against, initiated with respect to, or sustained by the County and
the COUNTY's elected and appointed officers and employees from liabilities damages, losses
,and costs, including butnot
Alimited
trvi~;�;ty®reasonable
�,r AND CONTRACTORo the extent caused by the
&DA COMPLIANCE SEGMENT# 1 & 2COMBINED
negligence, naok|eannaom, or intentional wrongful misconduct of the Contractor and persons
employed or utilized by the indemnifying party in the performance of the construction contract.
The monetary limitation of liability under this contract ahmU be not |emm than $1 million per
occurrence pursuant to F. S. 725.06. Insofar as the n|aim$, aCtionm, causes of action. |itigation,
prooemdingo, costs or expenses ne|mde to events #r circumstances that occur during the term of
this Amnaennent, this section will survive the expiration of the term of this Agreement or any
earlier termination of this Agreement.
|n the event the completion of the project (ino|udimgtheworkmfotMers) \mdm|ayedormuopended
mooresult of the Contractor's failure tm purchase mr maintain the required insurance, the
Contractor shall indemnify the County from any and all increased expenses resulting from such
delay.
|n the event the completion of the project (ino|udingthexxmrhof others) i8delayed or suspended
am@ result mfthe Contractor's failure to purchase or maintain the required insurance, the
Contractor shall indemnify the County from any and all increased expenses resulting from such
delay.
The first ten dollars ($10.00) of remuneration paid to the Contractor io for the indemnification
provided for above.
The extent of liability is in no way limited to, reduced, or lessened by the insurance requirements
contained elsewhere within this agreement.
(y) Agreements with Subcontractors. In the event that the Contractor subcontracts
any or all mf the work in this project tomnyth|ndparty. theContnmn1oropaoifiom||yagnaemto
identify the County mman additional insured on all insurance policies required by the County. In
addition, the Contractor specifically agrees that all agreements or contracts of any nature with
his subcontractors shall include the county am additional insured.
(o) Special Conditions, if any are detailed in Section OO9W0of the Project K8anua| for
this Project.
ARTICLE 9
Termination or Suspension
9.1 The Contract may be terminated bythe Owner as provided in Article 14mf the General
Conditions, orms outlined in Section 175O Department of Community Affairs CC)BG
Supplemental Conditions.
Article 10
Enumeration of Contract Documents
� 10.1 The Contract Documents, except for Modifications issued after execution of this
Aoreemont, are enumerated as follows:
(a) Project Manual dated January 2014
(b) Proposal Documents of February 13. 2O14
� (o) [:OBCS Supplemental Conditions
(d) SectimnO1750 C[]BC3 Supplemental Cmndidons|
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
(f) Drawings and Specifications prepared by mbi/k2m Architecure, Inc.
(g) Bonds and Insurance Requirements
10.1.1 The Agreement is this executed Standard Form of Agreement Between Owner and
Contractor.
10.1.2 The General Conditions are the General Conditions of the Contract for Construction;
10.1.3 The Supplementary and other Conditions of the Contract are those contained in the
Project Manual dated January, 2014.
10.1.4 The Specifications are those contained in the Project Manual dated January 2014.
As listed in Table of Contents, Section 00001 of the Project Manual for this project.
10.1.5 The Drawings issued by Project Management for the construction of the ADA
COMPLIANCE SEGMENT# 1 & 2 COMBINED
10.1.6 The Addenda, if any, are as follows:
Number Date Pages
1 January 15, 2014 1
2 February 3, 2014 7
10.1.7 The Alternates, if any, are as follows: N/A
END ALTERNATES
Portions of Addenda relating to bidding requirements are not part of the Contract Documents
unless the bidding requirements are also enumerated in this Article 10.
10.1.8 Other documents, if any, forming part of the contract Documents are as follows:
This Agreement is entered into as of the day and year first written above and is executed in at least four
original copies of which one is to be delivered to the Contractor, one to Project Management for use in the
administration of the Contract, and the remainder to the Owner.
Balance of Page Intentionally Left Blank
Signature Page to Follow
CONTRACT BETWEEN OWNER AND CONTRACTOR. 12
ADA COMPLIANCE SEGMENT# 1 &2 COMBINED
Execution by the Contractor must be by a person with authority to bind the entity.
SIGNATURE OF THE PERSON EXECUTING THE DOCUMENT MUST BE NOTARIZED AND
WITNESSED BY ANOTHER OFFICER OF THE ENTITY.
(SEAL) BOARD OF COUNTY COMMISSIONERS
Attest: Amy Heavilin, Clerk OF MONROE COUNTY, FLORIDA
By: _.. BY
Deputy ClerkMayor/Chairman
........ ..,.�.. ��p y Ma yor/Chairman
Date
(SEAL) CONTRACTOR
D.L. PORTER CONSTRUCTORS, INC.
Attest:
Print Name: Print name:
Title: Title:
Date; Date:
And: MONROE COUNTY ATTORNEY
By: PROVED tiS TO ip1 :
Print Name: NATILEENE
ASSISTANT COUNTY ATTORNEY
Title: ate </.....
Date:
STATE OF FLORIDA
to
COUNTY OF
On this_day of , 20_, before me,the undersigned notary public,
Personally appeared , known tome to be the
Person whose name is subscribed above or who produced,
As identification,and acknowledged that he/she is the person who executed the
above contract with Monroe County for the construction of ADA COMPLIANCE SEGMENT#1  COMBINED
for the purposes therein contained.
Notary Public
Print Name
My commission expires: .r __ Seal
� CONTRACT BETWEEN OWNER AND CONTRACTOR � 1 �3
ADA COMPLIANCE SEGMENT# 1 &2 COMBINED
General Conditions of the Contract for Construction
Where Project Management is Not a Constructor
Table of Articles
1. General Provisions Time
2. Owner 9. Payments and Completion
3. Contractor 1 . Protection of Persons and
Property
4. Administration of the Contract 11, Insurance and Bonds
5. Subcontractors 1 , Uncovering and Correction of Work
6. Construction by Owner or By Other 1 , Miscellaneous Provisions
Contractors
7. Changes in the Work 1 . Termination or Suspension of the
Contract
t
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
ARTICLE 1
GENERAL PROVISIONS
1.1 Basic Definitions
1.1.1 The Contract Documents: The Contract Documents consist of the Agreement
between Owner and Contractor, Conditions of the Contract (General, Supplementary and other
Conditions), preliminary Illustrations, Drawings, Specifications, addenda issued prior to
execution of the Contract, Contractors Proposal documents, Contractor's payment and
performance bond, other documents listed in the Agreement and Modifications issued after
execution of the Contract, and the Contractor's bid and supporting documentation. A
Modification is (1) a written amendment to the Contract signed by both parties, (2) a Change
Order, (3) a Construction Change Directive or (4) a written order for a minor change in the Work
issued by Project Management.
1.1.2 The Contract: The Contract represents the entire and integrated agreement between
the parties hereto and supersedes prior negotiations, representations or agreements, either
written or oral. The Contract may be amended or modified,only by a Modification entered into
bwith the same formality as this Agreement. The Contract Documents shall not be construed to
create a contractual relationship of any kind (1) between the Owner and a Subcontractor or(2)
between any persons or entities other than the Owner and Contractor. The Owner shall,
however, be entitled to enforce the obligations under the Contract intended to facilitate
performance of the duties of Contractor.
1.1.3 The Work: The term "Work" means the construction and services required by the
Contract Documents, whether completed or partially completed, and includes all other labor,
materials, equipment and services provided or to be provided by the Contractor to fulfill the
Contractor's obligations. The Work may constitute the whole or a part of the Project.
1.1.4 The Project: The Project is the total construction of which the Work performed under
the Contract Documents which may include construction by other Contractors and by the
Owner's own forces including persons or entities under separate contracts.
1.1.5 The Drawings: The Drawings are the graphic and pictorial portions of the Contract
Documents, wherever located and whenever issued, showing the design, location and
dimensions of the Work, generally including plans, elevations, sections, details, schedules and
diagrams.
1.1.6 The Specifications: The Specifications for this project shall be the latest requirements
for compliance with the Americans with Disabilities Act of 1990 (ADA) and ADA Amendments
Act of 2008, or applicable State law, whichever are the most stringent.
1.1.7 The Project Manual: The Project Manual is the volume usually assembled for the Work
which may include the bidding requirements, sample forms, Conditions of the Contract and
Specifications.
1.2 Execution, Correlation and Intent
i
2
GENERAL CQNDrrtoNS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINE . m
1.2.2 Execution of the Contract by the Contractor is a representation that the Contractor has
visited the site, become familiar with local conditions under which the Work is to be performed
and correlated personal observations with requirements of the Contract Documents.
1.2.3 The intent of the Contract Document is to include all items necessary for the proper
execution and completion of the Work by the contractor. The Contract Documents are
complementary, and what is required by one shall be as binding as if required by all;
performance by the Contractor shall be required only to the extent consistent with the Contract
Documents and reasonably inferable from them as being necessary to produce the intended
results.
1.2.4 Organization of the Specifications into divisions, sections and articles, and arrangement
of Drawings shall not control the Contractor in dividing the Work among Subcontractors or in
establishing the extent of Work to be performed by any trade.
1.2.5 Unless otherwise stated in the Contract Documents, words which have well-known
technical or construction industry meanings are used in the Contract Documents in accordance
with such recognized meanings.
1.2.6 Not used
1.3 Ownership and Use of The Architects Drawings, Specifications and Other
Documents
1.3.1 The Drawing, Specifications and other documents prepared by the Architect are
instruments of the Architect's service through which the Work to be executed by the Contractor
is described. The Contractor may retain one contract record set. Neither the Contractor nor
any Subcontractor, Sub-subcontractor or material or equipment supplier shall own or claim a
copyright in the Drawings, Specifications and other documents prepared by the Architect. All
copies of them, except the Contractor's record set, shall be returned or suitably accounted for to
Project Management, on request, upon completion of the Work. The Drawings, Specifications
and other documents prepared by the Architect, and copies thereof furnished to the Contractor,
are for use solely with respect to the Project. They are not to be used by the Contractor or any
Subcontractor, Sub-subcontractor or material or equipment suppliers unless they are granted a
limited license to use and reproduce applicable portions of the Drawings, Specifications and
other documents prepared by the Architect appropriate to and for use in the execution of their
Work under the Contract Documents. All copies made under this license shall bear the
statutory copyright notice, if any, shown on the Drawings, Specifications and other documents
prepared by the Architect. Submittal or distribution to meet official regulatory requirements or
for other purposes in connection with this Project is not to be construed as publication in
derogation of copyright or other reserved rights.
1.3.2 Unless otherwise provided in the Contract Documents, the Contractor will be furnished,
2 original copies and a CD, if requested, free of charge, of Drawings and reasonably necessary
for the execution of the Work. Additional copies may be obtained from Project Management at a
fee of$5.00 per page.
1.4 Capitalization
1.4.1 Terms capitalized in these General Conditions include those which are (1) specifically
defined, (2)the titles of numbered articles and identified references to Paragraphs,
Subparagraphs and Clauses in the document or(3) the titles of other documents published by
the American Institute of Architects.
3
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
1.5 Interpretation
1.5.1 In the interest of brevity the Contract Documents frequently omit modifying words such
as "all" and "any" and articles such as "the" and "an," but the fact that a modifier or an article is
absent from one statement and appears in another is not intended to affect the interpretation of
either statement.
ARTICLE 2
OWNER
2.1 Definition
2.1.1 The Owner is Monroe County. The term "Owner" means the Owner or the Owner's
authorized representative.
2.2 Information and Services Required of the Owner
2.2.2 The Owner has furnished project drawing containing necessary site conditions.
2.2.3 Except for permits and fees which are the responsibility of the Contractor under the
Contract Documents, the Owner shall secure and pay for necessary approvals, easements,
assessments and charges required for construction, use or occupancy of permanent structures
or for permanent changes in existing facilities.
2.2.4 Information or services under the Owner's control shall be furnished by the Owner with
reasonable promptness to avoid delay in orderly progress of the Work.
2.2.5 Unless otherwise provided in the Contract Documents, the Contractor will be furnished,
two (2) original sealed compies and one electronic copy of drawings, specifications and the
project manual free of charge for the execution of the work as provided in subparagraph 1.3.2.
2.2.6 The Owner shall forward all communications to the Contractor through Project
Management.
2.2.7 The foregoing are in addition to other duties and responsibilities of the Owner
enumerated herein and especially those in respect to Article 6 (Construction by Owner or by
Other Contractors), Article 9 (Payments and Completion) and Article 11 (Insurance and Bonds).
2.3 Owner's Right to Stop the Work
2.3.1 If the Contractor fails to correct Work which is not in accordance with the requirements of
the contract Documents as required by Paragraph 12.2 or persistently fails to carry out Work in
accordance with the Contract Documents, the Owner, by written order signed personally or by
an agent specifically so empowered by the Owner, may order the Contractor to stop the Work,
or any portion thereof, until the cause for such order has been eliminated; however, the right of
the Owner to stop the Work shall not give rise to a duty on the part of the Owner to exercise this
right for the benefit of the Contractor or any other person or entity.
2.4 Owner's Right to Carry Out the Work
2.4.1 If the Contractor defaults or neglects to carry out the Work in accordance with the
Contract Documents and fails within a three-day period after receipt of written notice from the
Owner to commence and continue correction of such default or neglect with diligence and
4
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
promptness, the Owner may after such three-day period give the Contractor a second written
notice to correct such deficiencies within a three-day period. If the Contractor within such
second three-day period after receipt of such second notice fails to commence and continue to
correct any deficiencies, the Owner may, without prejudice to other remedies the Owner may
have, correct such deficiencies., In such case an appropriate Change Order shall be issued
deducting from payments then or thereafter due the Contractor the cost of correcting such
deficiencies, including compensation for another contractor or subcontractor or Project
Management and their respective consultants' additional services and expenses made
necessary by such default, neglect or failure. If payments then or thereafter due the Contractor
are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner.
In the event of clean-up issues, Owner has right to provide a minimum of 24 hours notice. In
the event of safety issues determined to be of a serious nature, as determined by Project
Management, notice will be given, and contractor is required to rectify deficiency immediately.
ARTICLE 3
CONTRACTOR
3.1 Definition
3.1.1 The Contractor is the person or entity identified as such in the Agreement and is referred
to throughout this Agreement as if singular in number. The term "Contractor" means the
Contractor or the Contractor's authorized representative.
3.1.2 The plural term "Contractors" refers to persons or entities who perform construction
under Conditions of the Contract that are administered by Project Management, and that are
identical or substantially similar to these Conditions.
3.2 Review of Contract Documents and Field Conditions by Contractor
3.2.1 The Contractor shall carefully study and compare the Contract Documents with each
other and with information furnished by the Owner pursuant to Subparagraph 2.2.2 and shall at
once report to Project Management errors, inconsistencies or omissions discovered. The
Contractor shall not be liable to the Owner for damage resulting from errors, inconsistencies or
omissions in the Contract Documents unless the Contractor recognized such error,
inconsistency or omission and knowingly failed to report it to Project Management. If the
Contractor performs any construction activity knowing it involves a recognized error,
inconsistency or omission in the Contract Documents without such notice to Project
Management, the Contractor shall assume appropriate responsibility for such performance and
shall bear an appropriate amount of the attributable costs for correction.
3.2.2 The Contractor shall take field measurements and verify field conditions and shall
carefully compare such field measurements and conditions and other information known to the
Contractor with the Contract Documents before commencing activities. Errors, inconsistencies
or omissions discovered shall be reported to Project Management at once.
3.2.3 The Contractor shall perform the Work in accordance with the Contract Documents and
submittals approved pursuant to Paragraph 3.12.
3.3 Supervision and Construction Procedures
3.3.1 The Contractor shall supervise and direct the Work, using the Contractor's best skill and
attention. The Contractor shall be solely responsible for and have control over construction
5
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
means, methods, techniques, sequences and procedures and for coordinating all portions of the
Work under this Contract, subject to overall coordination of Project Management as provided in
Subparagraphs 4.2.3 and 4.2.5.
3.3.2 The Contractor shall be responsible to the Owner for acts and omissions of the
Contractor's employees, Subcontractors and their agents and employees, and other persons
performing portions of the Work under a contract with the Contractor.
3.3.3 The Contractor shall not be relieved of obligations to perform the Work in accordance
with the Contract Documents either by activities or duties of Project Management in their
administration of the Contract, or by test, inspections or approvals required or performed by
persons other than the Contractor.
3.3.4 The Contractor shall inspect portions of the Project related to the Contractor's Work in
order to determine that such portions are in proper condition to receive subsequent work.
3.3.5 The Contractor shall verify that the Construction Documents being worked with are the
most recent and updated available, including all Addenda information. Also the Contractor will
perform the work strictly in accordance with this contract.
3.4 Labor and Materials
3.4.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and
pay for labor, materials, equipment, tools, construction equipment and machinery, water, heat,
utilities, transportation, and other facilities and services necessary for proper execution and
completion of the Work, whether temporary or permanent and whether or not incorporated or to
be incorporated in the Work.
3.4.2 The Contractor shall enforce strict discipline and good order among the Contractor's
employees and other persons carrying out the Contract. The Contractor shall not permit
employment of unfit persons or persons not skilled in tasks assigned to them.
3.4.3 The Contractor is responsible for the conduct of his employees at all times. Misconduct,
destruction of property, unsafe practices, or violation of any Federal or State regulations
including abuse of alcohol or drugs, will be cause for permanent dismissal from the project. If
any Contractor's employee is determined to be detrimental to the Project, as deemed by Project
Management, the Contractor will remove and/or replace the employee at the request of Project
Management. Employees dismissed from the project will be transported from the job site at the
Contractor's expense.
3.4.4 The Contractor shall be totally responsible for the security of his work, materials,
equipment, supplies, tools, machinery, and construction equipment.
3.4.5 The Contractor shall be responsible for complete, timely and accurate field
measurements as necessary for proper coordination, fabrication and installation of his materials
and equipment. The Contractor agrees to cooperate with Project Management, if required, to
accommodate any discovered variations or deviations from the drawings and State and Federal
requiremetns so that the progress of the Work is not adversely affected.
3.5 Warranty
3.5.1 The Contractor warrants to the Owner that materials and equipment furnished under the
Contract will be of good quality and new unless otherwise required or permitted by the Contract
6
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
Documents, that the Work will be free from defects not inherent in the quality required or
permitted, and that the Work will conform with the requirements of the Contract Documents.
Work not conforming to these requirements, including substitutions not properly approved and
authorized, may be considered defective. The Contractor's warranty excludes remedy for
damage or defect caused by abuse, modifications not executed by the Contractor, improper or
insufficient maintenance, improper operation, or normal wear and tear under normal usage. If
required by Project Management, the Contractor shall furnish satisfactory evidence as to the
kind and quality of materials and equipment.
3.6 Taxes
3.6.1 The Contractor shall pay sales, consumer, use and similar taxes for the Work or portions
thereof provided by the Contractor which are legally enacted when bids are received or
negotiations concluded, whether or not yet effective or merely scheduled to go into effect.
3.7 Permits, Fees and Notices
3.7.1 The Contractor shall secure and pay for all permits, impact fees, governmental fees,
licenses, inspections and surveys required by Federal, State, or Municipal bodies having
jurisdiction over the project for the proper execution and completion of the Work which are
customarily secured after execution of the Contract and which are legally required at the time
Proposals are received. The Owner,twill,assess o nt uildin ermi't and Count im act fees
to CONTRACTOR. The Contractor will be responsible for any other building permit costs or
impact fees required for this project. The Contractor shall secure and pay for all building and
specialty permits including plumbing, electrical, HVAC, etc.
3.7.2 The Contractor shall comply with and give notices required by laws, ordinances, rules,
regulations and lawful orders of public authorities bearing on performance of the Work.
3.7.3 It is the Contractor's responsibility to ascertain that the Contract Documents are in
accordance with applicable laws, statutes, ordinances, building codes, and rules and
regulations. However, if the Contractor observes that portions of the Contract Documents are at
variance therewith, the Contractor shall promptly notify Project Management in writing, and
necessary changes shall be accomplished by appropriate Modification.
3.7.4 If the Contractor performs Work knowing it to be contrary to laws, statutes, ordinances,
building codes, and rules and regulations without such notice to Project Management, the
Contractor shall assume full responsibility for such Work and shall bear the attributable costs.
3.9 Superintendent
3.9.1 The Contractor shall employ a competent superintendent and necessary assistants who
shall be in attendance at the Project site during performance of the Work. The superintendent
shall represent the Contractor, and communications given to the superintendent shall be as
binding as if given to the Contractor. Important communications shall be confirmed in writing.
Other communications shall be similarly confirmed on written request in each case. The
superintendent shall be satisfactory to Project Management and shall not be changed except
with the consent of Project Management, unless the superintendent proves to be unsatisfactory
to the Contractor or ceases to be in his employ.
3.10 Contractor's Construction Schedule
7
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for
the Owner's information and approval a Contractor's Construction Schedule for the Work. Such
schedule shall not exceed time limits current under the Contract Documents, shall be revised at
appropriate intervals as required by the conditions of the Work and Project, shall be related to
the entire Project construction schedule to the extent required by the Contract Documents, and
shall provide for expeditious and practicable execution of the Work. This schedule, to be
submitted within fourteen (14) days after Contract Award, shall indicate the dates for the starting
and completion of the various stages of construction, shall be revised as required by the
conditions of the Work, and shall be subject to Project Management's approval.
3.10.2 The Contractor shall cooperate with Project Management in scheduling and performing
the Contractor's Work to avoid conflict, delay in or interference with the Work of other
Contractors or the construction or operations of the Owner's own forces.
3.10.4 The Contractor shall conform to the most recent schedules.
3.10.5 Project Management will schedule and conduct a project meeting at a minimum of one
meeting per month in each month with the Contractor shall attend. At this meeting, the parties
can discuss jointly such matters as progress, scheduling, and problems.
3.11 Documents and Samples at the Site
3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the
preliminary sketche, and photos, and any subsequent drawings, the Specifications, addenda,
Change Orders and other Modifications, in good order and marked currently to record changes
and selections made during construction, and in addition approved Shop Drawings, Product
Data, Samples and similar required submittals. These shall be available to Project
Management and shall be delivered to Project Management for submittal to the Owner upon
completion of the Work.
3.12 Shop Drawings, Product Data and Samples Submitted by Contrator
3.12.1 Shop Drawings are drawings, diagrams, schedules and other data specially prepared for
the Work by the Contractor or a Subcontractor, Sub-subcontractor, manufacturer, supplier or
distributor to illustrate some portion of the Work.
3.12.2 Product Data are illustrations, standard schedules, performance charts, instructions,
brochures, diagrams and other information furnished by the Contractor to illustrate materials or
equipment for some portion of the Work.
3.12.3 Samples are physical examples which illustrate materials, equipment or workmanship
and establish standards by which the Work will be judged.
3.12.4 Shop Drawings, Product Data, Samples and similar submittals are not Contract
Documents. The purpose of their submittal is to demonstrate for those portions of the Work for
which submittals are required the way the Contractor proposes to conform to the information
given and the design concept expressed in the Contract Documents. Review by Project
Management is subject to the limitations of Subparagraph 4.2.11.
3.12.5 The Contractor shall review, approve and submit to Project Management, in accordance
with the schedule and sequence approved by Project Management, Shop Drawings, Product
Data, Samples and similar submittals required by the Contract Documents. The Contractor
shall cooperate with Project Management in the coordination of the Contractor's Shop
Drawings, Product Data, Samples and similar submittals with related documents submitted by
s
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
other Contractors. Submittals made by the Contractor which are not required by the Contract
Documents may be returned without action.
3.12.6 The Contractor shall perform no portion of the Work requiring submittal and review of
Shop Drawings, Product Data, Samples or similar submittals until the respective submittal has
been approved by Project Management. Such Work shall be in accordance with approved
submittals.
3.12.7 By approving and submitting Shop Drawings, Product Data, Samples and similar
submittals, the Contractor represents that the Contractor has determined and verified materials,
field measurements and field construction criteria related thereto, or will do so, and has checked
and coordinated the information contained within such submittals with the requirements of the
Work and of the Contract Documents.
3.12.8 The Contractor shall not be relieved of responsibility for deviations from requirements of
the Contract Documents by Project Management's approval of Shop Drawings, Product Data,
Samples or similar submittals unless the Contractor has specifically informed Project
Management in writing of such deviation at the time of submittal and Project Management have
given written approval to the specific deviation. The Contractor shall not be relieved of
responsibility for errors or omissions in Shop Drawings, Product Data, Samples or similar
submittals by Project Management's approval thereof.
3.12.9 The Contractor shall direct specific attention, in writing or on resubmitted Shop
Drawings, Product Data, Samples or similar submittals, to revisions other than those requested
by Project Management on previous submittals,
3.12.10 Informational submittals upon which Project Management and is not expected to take
responsive action may be so identified in the Contract Documents.
3.12.11 When professional certification of performance criteria of materials, systems or
equipment is required by the Contract Documents, Project Management shall be entitled to rely
upon the accuracy and completeness of such calculations and certifications.
3.12.12 If materials specified in the Contract Documents are not available on the present
market, the Contractor may submit data on substitute materials to Project Management for
approval by the Owner.
3.13 Use of Site
3.13.1 The Contractor shall confine operations at the site to areas permitted by law, ordinances,
permits and the Contract Documents and shall not unreasonably encumber the site with
materials or equipment.
3.13.2 The Contractor shall coordinate the Contractor's operations with, and secure the
approval of, Project Management before using any portion of the site.
3.14 Cutting and Patching
3.14.1 The Contractor shall be responsible for cutting, fitting or patching required to complete
the Work or to make its parts fit together properly; He shall also provide protection of existing
work as required.
3.14.2 The Contractor shall not damage or endanger a portion of the Work or fully or partially
completed construction of the Owner's own forces or of other Contractors by cutting, patching,
excavating or otherwise altering such construction. The Contractor shall not cut or otherwise
9
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 &2 COMBINED
alter such construction by other Contractors or by the Owner's own forces except with written
consent of Project Management, Owner and such other contractors: such consent shall not be
unreasonably withheld. The Contractor shall not unreasonably withhold from the other
Contractors or the Owner the Contractor's consent to cutting or otherwise altering the Work.
When structural members are involved, the written consent of Project Management shall also be
required. The Contractor shall not unreasonably withhold from Project Management or any
separate contractor his consent to cutting or otherwise altering the Work.
3.14.3 The Contractor shall arrange for any blockouts cutout, or opening required for the
installation of his materials and equipment and the execution of his work, whether or not shown
or indicated on the Drawings. The Contractor shall be further responsible for sealing and/or
finishing, in an acceptable fashion and meeting any applicable code requirements, and such
block-out, cutout opening, or other hole in any fire-related floor, ceiling, wall, security wall, or
any other finished surface.
3.15 Cleaning Up
3.15.1 The Contractor shall keep the premises and surrounding area free from accumulation of
waste materials or rubbish caused by operations under the Contract. At completion of the Work
the Contractor shall remove from and about the project waste materials rubbish, the
Contractor's tools, construction equipment, machinery and surplus materials. Clean up shall be
performed to the satisfaction of the Owner or Project Management.
3.15.2 If the Contractor fails to clean up as provided in the Contract Documents, Project
Management may do so with the Owner's approval and the cost thereof shall be charged to the
Contractor.
3.16 Access to Work
3.16.1 The Contractor shall provide the Owner/Project Management access to the Work in
preparation and progress wherever located.
3.17 Royalties and Patents
3.17.1 The Contractor shall pay all royalties and license fees. The Contractor shall defend suits
or claims for infringement of patent rights and shall hold the Owner and Project Management
harmless from loss on account thereof, but shall not be responsible for such defense or loss
when a particular design, process or product of a particular manufacturer or manufacturers is
required by the Contract Documents. However, if the Contractor has reason to believe that the
required design, process or product is an infringement of a patent, the Contractor shall be
responsible for such loss unless such information is promptly furnished to the Project
Management.
3.18 Indemnification and Hold Harmless
3.18.1 Notwithstanding any minimum insurance requirements prescribed elsewhere in this
agreement, the Contractor covenants and agrees that he shall indemnify and hold the COUNTY
and the COUNTY's elected and appointed officers and employees harmless from and against (i)
claims, actions or causes of action, (ii) litigation, administrative proceedings, appellate
proceedings, or other proceedings relating to any type of injury (including death), loss, damage,
fine, penalty or business interruption, and (iii) costs or expenses that may be asserted against,
10
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
initiated with respect to, or sustained by the County and the COUNTY's elected and appointed
officers and employees from liabilities damages, losses and costs, including but not limited to,
reasonable attorney's fees, to the extent caused by the negligence, recklessness, or intentional
wrongful misconduct of the Contractor and persons employed or utilized by the indemnifying
party in the performance of the construction contract. The monetary limitation of liability under
this contract shall be not less than $1 million per occurrence pursuant to F. S. 725.06. Insofar as
the claims, actions, causes of action, litigation, proceedings, costs or expenses relate to events
or circumstances that occur during the term of this Agreement, this section will survive the
expiration of the term of this Agreement or any earlier termination of this Agreement.
In the event the completion of the project (including the work of others) is delayed or suspended
as a result of the Contractor's failure to purchase or maintain the required insurance, the
Contractor shall indemnify the County from any and all increased expenses resulting from such
delay.
In the event the completion of the project (including the work of others) is delayed or suspended
as a result of the Contractor's failure to purchase or maintain the required insurance, the
Contractor shall indemnify the County from any and all increased expenses resulting from such
delay.
The first ten dollars ($10.00) of remuneration paid to the Contractor is for the indemnification
provided for above.
ARTICLE_4
ADMINISTRATION OF THE CONTACT
4.1 Project Management
4.1.1 The term "Project Management" means Monroe County Project Management
Department or Project Management's authorized representative.
4.2 Administration of the Contract
4.2.1 Project Management will provide administration of the Contract as described in the
Contract Documents, and will be the Owner's representatives (1) during construction, (2) until
final payment is due and (3) with the Owner's concurrence, from time to time during the
correction period described in Paragraph 12.2. Project Management will advise and consult
with the Owner and will have authority to act on behalf of the Owner to the extent provided in
the Contract Document, unless otherwise modified by written instrument in accordance with
other provision of the Contract.
4.2.2 Project Management will determine in general that the Work is being performed in
accordance with the requirements of the Contract Documents, will keep the Owner informed of
the progress of the Work, and will endeavor to guard the Owner against defects and
deficiencies in the Work.
4.2.3 Project Management will provide for coordination of the activities of other Contractors
and of the Owner's own forces with the Work of the Contractor, who shall cooperate with theme
The Contractor shall participate with other Contractors and Project Management and Owner in
reviewing their construction schedules when directed to do so. The Contractor shall make any
revisions to the Construction schedule deemed necessary after a joint review and mutual
tt
GENERAL CONDITIONS
ADA COMPLIANCE GBGK8ENT# 1 & 2 C3K8B|NE[}
agreement. The construction schedules shall constitute the schedules bobe used bvthe
Contractor, other Contractors, Project Management and the Owner until subsequently revised.
4.2.4 Project Management will visit the site at intervals appropriate to the stage of construction
ta become generally familiar with the progress and quality of the completed Work and to
determine in general if the Work is being performed in a manner indicating that the Work, when
completed, will bein accordance with the Contract Documents. However, Project Management
will not be required to make exhaustive or continuous onsite inspections to check quality or
quantity of the Work.
4.2.5 Project Management will not have control over or charge of and will not baresponsible
for construction means, method, techniques, sequences or procedures, or for safety precautions
and pno8narnm in connection with the Work, since theme are solely the Contractor's responsibility
am provided in Paragraph 3.3. and neither will Project K8mnmgamentbenaepono|b|eforthe
Contractor's failure to carry out the Work in accordance with the Contract Documents. Project
Management will not have control over or charge of or be responsible for acts or omissions of
the Contractor, Subcontractors, or their agents or employees, or of any other persons
performing portions of the Work.
4.3.0 Communications Facilitating Contract Administration. Except as otherwise provided in
the Contract Documents or when direct communications have been specially authorized, the
Owner and Contractor shall communicate through Project K8mnmgennenLConnnnunicationnby
and with Subcontractors and material suppliers shall be through the Contractor.
Communications by and with other contractors hired directly by Owner or with the Owner's own
forces shall be through Project yNmnogomont.
4.2.7 Project Management will review and certify all Applications for Payment by the
Contractor, including final payment. Project Management will assemble each of the
Contractor's Applications for Payment with similar Applications from other Contractor into a
Project Application and Pr jootCert\fio*tmfnrPmymenL After reviewing and certifying the
amounts due the Contractors, the Project App|inadonandPr 'eotRequeotforPayment. m|onQ
with the applicable Contractors' Applications and Request for Payment, will be processed by
Project Management.
4.2.8 Based on Project K8mnm0emant'soboervadonamndeva|uobmnaofContrmutoro'
Applications for Payment, Project Management will certify the amounts due the Contractors and
Will issue m Project/\ppnmva| forPayment.
4.2.9 Project Management will have authority to rejectWork which does not conform to the
Contract C)oournonto, and to require additional inspection or testing, in accordance with
Subparagraphs 13.5.2mnd 13.5.3` whether or not such Work iafabricated, installed or
completed. Project Management will have the authority to rejectWork which does not conform
to the Contract Documents. Whenever Project K8anagmnmantconoidmrs |tneoemmoryor
advisable for implementation of the intent ofthe Contract Documents, Project Management will
have authority to require additional inspection or testing of the work in accordance with
SubporaQnapho13.5.2 and 13.5.3. whether or not such Work im fabricated, installed or
completed. The foregoing authority of Project &8anage,nentxvii| bemubieottotheproxioionmmf
Subparagraphs 4.2.16 through 4.2.17 inclusive. Hoxvever. Project Management's authority to
act under this Subparagraph 4.8.1Oora decision made by Project K8anagenlentingoodhaith
either tq exercise or not to exercise such authority shall not give rise tom duty or responsibility of
Project Management tmthe Contractor, Subcontrmctora, nnmtar|m| and equipment suppliers, their
agents or employees, or other persons performing any of the Work.
| 12
� GENERAL CONDITIONS
�
AOA COMPLIANCE SEGMENT# 1 {k3COMBINED
4.2.10 Project Management will receive from the Contractor and naviavv and approve all Shop
[}nawinQa. Product Data and Sannp|em, coordinate them with information received from other
Contractors, and transmit tothe Owner those recommended for approval. Project
Management's actions will be taken with such reasonable promptness as to cause no delay in
the Work of the Contractor orin the activities of other Contractors or the Owner.
4.2.11 Project Management will review and approve or take other appropriate action upon the
Contractor's submittals such as Shop Drawings, Product Data and Samples, but only for the
limited purpose of checking for conformance with information given and the design concept
expressed in the Contract Documents. Project Management's action will be taken with such
promptness consistent with the constraints mf the project schedule ammato cause no delay in
the Work of the Contractor or in the activities of the other Contractors or the Owner, while
allowing sufficient time in Project K8ona0ernent'sprofooeionm|judgnnanttoparnnit adequate
review. Review of such submittals is not conducted for the purpose of determining the accuracy
and completeness of other details such mm dimensions and quantities, or for substantiating
instructions for installation or performance of equipment or systems, all of which remain the
responsibility of the Contractor as Contractor as required by the Contract Documents. Project
Managemnent's review of the Contractor's submittals shall not relieve the Contractor of the
obligations under Paragraphs 3.3. 3.5 and 3.12. Project Management's review shall not
constitute approval of safety precautions or, unless otherwise specifically stated by Project
Management, of any construction means, methods, techniques, sequences or procedures.
Project Management's approval of a specific item shall not indicate approval of an assembly of
which the item ima component.
4.2.12 Project Management will prepare Change Orders and Construction Change Directives,
4.2.13 Fm||mxving consultation with the Owner, Project Management will take appropriate action
on Change Orders or Construction Change Directives in accordance with Article 7 and will have
authority to order minor changes in the Work as provided in Paragraph 7.4.
4,2.14 The Contractor will assist Project Mmnagennentinomnductin8inapectionmtodotmrnnina
the dates of Substantial completion and final comnp|mtion, and will receive and forward to Project
Management written warranties and related documents required by the Contract and assembled
by the Contractor. The Contractor will forward to Project K8ena8annentafinm| P jeot
Application for Payment upon compliance with the requirements of the Contract Documents.
4.2.15 Project Management will provide one or more pr jectneprmmentmUvasboaeo|atin
carrying out Owner's responsibilities ot the site.
4.2.16 Project Management will interpret and decide matters concerning performance under
and requirements of the Contract Documents upon request ofthe Owner mrContractor. Project
Management's response to such requests will be made with reasonable promptness and within
any time limits agreed upon. |fnm agreement iomade concerning the time within which
interpretations required ofProject Management shall be furnished in compliance with this
Paragraph, then delay shall not ba recognized on account of failure by Project K8anogennentto
furnish such interpretations until 15 days after written request is made for them.
4.2.17 Project Management's decisions on matters relating to aesthetic effect will he final if
consistent with the intent expressed |O the Contract Documents.
4.3 Claims and Disputes
4.3.1 Definition. A Claim ioa demand or assertion by one of the parties seeking, asamatter
of right, adjustment or interpretation of Contract ternne, payment of money, extension of time or
� 13
GENERAL CONDITIONS
AOA COMPLIANCE SEGMENT# 1 & 2COMBINED
other relief with respect ho the terms of the Contract. The term "C|aim^ also includes other
disputes and nnath*re in question between the Owner and Contractor arising out oforrelating to
the Contract. Claims must be made by written notice. The responsibility to substantiate Claims
shall rest with the party making the claim.
4.3.2 DNsmt and Confer. The Contractor and Project K8onogammntaMa||trytomyeo|vethe
claim or dispute with meet and confer sessions tobe commenced within 16 days of the dispute
or claim. Any claim or dispute that the parties cannot resolve shall be decided by the Circuit
Court, 16m Judicial Circuit, Monroe County, Florida.
4.3.3 Time Limits on Claims. Claims by either party must be made within 21 days after
occurrence ofthe event giving rise bo such Claim or within 21 days after the claimant first
recognizes the condition giving rise tm the Claim, whichever ialater. Claims must be made by
written notice. /\n additional Claim made after the initial Claim has been implemented by
Change Order will not be considered unless submitted in a timely manner. This notice is not a
condition precedent to any other legal action orsuit.
4.3.4 Continuing Contract Performance. Pending final neam|uUmn of Claim unless
otherwise agreed in writing the Contractor shall proceed diligently with performance of the
Contract and the Owner shall continue tm make payments in accordance with the Contract
Documents.
4.3.5 Waiver of Claims: Final Payment. The making of final payment mhm|| constitute m
waiver of Claim by the Owner except those arising from:
.1 liens, Claims, security interests or encumbrances arising out of the Contract and
unsettled;
.2 failure of the Work to omnnp|y with the requirements of the Contract Documents; or
.3 terms of special warranties required by the Contract Documents.
4.3.6 Claims for Concealed or Unknown Conditions. If conditions are encountered atthe
site which are (1) subsurface or otherwise concealed physical conditions which differ materially
from those indicated in the Contract Documents or /2> unknown physical conditions ofan
unusual naturo, which differ materially from those ordinarily found to exist and generally
recognized aa inherent in construction activities oY the character provided for in the Contract
Documents, then notice bythe observing party shall be given to the other party promptly before
conditions are disturbed and in no event later than 21 days after first observance of the
conditions. Project Management will promptly investigate such conditions, and the parties will
follow the procedure in paragraph 4.3.2.
4.3.7 Claims for Additional Cost. If the Contractor wishes to make C|$in)for an increase in
the Contract Sum, written notice aa provided herein shall be given before proceeding to execute
the Work. Prior notice is not naqu|nyd for Claims relating to an emergency endangering life or
property arising under Paragraph 10.3 |f the Contractor believes additional cost in involved for
reasons including but not limited to (1) avxritten interpretation from Project Management, (2) Not
Applicable (3) a written order for a minor change in the Work issued Uy Project K8anmQernmn1. (4)
failure of payment bythe Owner, /5\ harnninmtimn of the Contract by the Owner, (8) Ovvner'm
suspension or(7) other reasonable grounds, Claim shall be filed in accordance with the
procedure established herein.
4.3.8 Claims for Additional Time.
\4
GENERAL CONDITIONS
AOA COMPLIANCE SEGMENT# 1 & 2COMBINED
4.3.8.1. If the Contractor wishes to make Claim for an increase in the Contract Time, written
notice mm provided herein shall be given.
4.3.8.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim
shall be documented by data substantiating that weather conditions were abnormal for the
period of time and could not have been reasonably anticipated, and that weather conditions had
mn adverse effect on the scheduled construction.
4.3.9 Injury or Damage to Person on Property. |f either party to the Contract suffers injury
or damage to person or property because of an act or omission of the other party, of any of the
other party's employees or agents, or of others for whose acts such party is legally liable, written
notice mf such injury ordennaQe. vvhetMarornotinsuned. ohm|| beQiventmtheothmrpadyxvithin
m reasonable time not exceeding 21 days after first observance. The notice shall provide
sufficient detail to enable the other party tminvestigate the matter. |fe Claim for additional cost
or time related t¢ this Claim iotmbe asserted, it shall be filed ma provided inSubparagraphs
4.3.7or4.3.8.
ARTICLE 5
SUBCONTRACTORS
5'1 Definitions
5.1.1 /\Subcontractor immperson or entity who has a direct contract with the Contractor to
perform a portion mf the Work at the site. The barrn "Subcontractor" is referred to throughout the
Contract Documents as if singular in number and means a Subcontractor or an authorized
representative of the Subcontractor. The term "Suboontracto/' does not include other
Contractors or subcontractors of other Contractors.
5.1.2 A Sub-subcontractor|aa person or entity who has m direct mr indirect contract with a
Subcontractor to perform a portion of the Work mt the site. The term ^Sub-suboontraotor` io
referred to throughout the Contract Documents as if singular in number and means a Sub-
subcontractor or an authorized representative of the Sub-subcontractor.
5'2 Award of Subcontracts and Other Contracts for Portions of the Work
5.2.1 Unless otherwise stated in the Contract Documents orthe bidding requirements, the
Contractor, ma soon aepracticable after award nf the Contract, shall furnish inwriting to Project
Management for review by the Owner and Project N1anagernentthenamne$ ofporoonaor
entities (including those who are to furnish materials or equipment fabricated to a special
design) proposed for each principal portion of the Work. Project Management will promptly
reply to the Contractor in writing stating whether ornot the Owner or Project K8anagement. after
duo invmmbgst\on, has reasonable objection to any such proposed person or entity. Failure of
Project Management to reply promptly shall constitute notice ofno reasonable objection.
5.2.2 The Contractor shall not contract with a proposed person or entity to whom the Owner or
Project Management has made reasonable and timely objection. The Contractor shall not be
required to contract with anyone to whom the Owner or Project Mana8enmenthaon1ade
reasonable objection.
5.2.3 |f the Owner mr Project K8anagennentrefueestoaocmpt any person or entity onalist
submitted by the Contractor in response to the requirements of the Contract Documents, the
� Is
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
Contractor shall submit an acceptable substitute; however, no increase in the Contract Sum
shall be allowed for any such substitution.
5.2.4 The Contractor shall not change a Subcontractor, person or entity previously selected if
the Owner or Project Management makes reasonable objection to such change.
5.3 Subcontractual Relations
5.3.1 By appropriate written agreement, the Contractor shall require each Subcontractor, to
the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by
terms of the Contract Documents, and to assume toward the Contractor all the obligations and
responsibilities which the Contractor, by these Documents, assumes toward the Owner and
Project Management. Each subcontract agreement shall preserve and protect the rights of the
Owner and Project Management under the Contract Documents with respect to the Work to be
performed by the Subcontractor so that subcontracting thereof will not prejudice such rights.
When appropriate, the Contractor shall require each Subcontractor to enter into similar
agreements with Sub-subcontractors. The Contractor shall make available to each proposed
Subcontractor, copies of the Contract Documents which the Subcontractor will be bound, and,
upon written request of the Subcontractor, identify to the Subcontractor terms and conditions of
the proposed subcontract agreement which may be at variance with the Contract Documents.
Subcontractors shall similarly make copies of applicable portions of such documents available
to their respective proposed Sub-subcontractors.
5.4 Contingent Assignment of Subcontracts
5.4.1 Each subcontract agreement, for all or a portion of the Work, may assigned by the
Contractor to the Owner provided that:
.1 assignment is effective only after termination of all or a part of the Contract by the
Owner with the Contractor for cause pursuant to Paragraph 14.1 and only for those subcontract
agreements which the Owner accepts by notifying the Subcontractor in writing; and
.2 assignment is subject to the prior rights of the surety, if any, obligated under public
construction bond covering the Contract.
i. If the work has been suspended for more then 30 days, the
Subcontractor's compensation shall be equitably adjusted.
ARTICLE 6
CONSTRUCTION BY OWNER OR BY OTHER CONTRACTORS
6.1 Owner's Right to Perform Construction with Own Forces and to Award Other
Contracts
6.1.1 The Owner reserves the right to perform construction or operations released to the
Project with the Owner's own forces, which include persons or entities under separate contracts
not administrered by Project Management. The Owner further reserves the right to award other
conracts in connection with other portions of the Project or other construction or operations on
the site under Conditions of the Contract identical or substantially similar to these including
those portions related to insurance and waiver or subrogation.
16
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
6.1.2 When the Owner performs construction or operations with the Owner's own forces
including persons or entities under separate contracts, the Owner shall provide for coordination
of such forces with the Work of the Contractor who shall cooperate with them.
6.1.3 It shall be the responsibility of the Contractor to coordinate his work with the work of
other contractors on the site. The Owner and Project Management shall be held harmless for
any and all costs associated with improper coordination on the part of the Contractor.
6.2 Mutual Responsibility
6.2.1 The Contractor shall afford the Owner's own forces, Project Management and other
contractors reasonable opportunity for introduction and storage of their materials and equipment
and performance of their activities, and shall connect and coordinate the Contractor's
construction and operations with theirs as required by the Contract Documents.
6.2.2 If part of the Contractor's Work depends for proper execution or results upon
construction or operations by the Owner's own forces or other contractors, the Contractor shall,
prior to proceeding with that portion of the Work, promptly report to Project Management
apparent discrepancies or defects in such other construction that would render it unsuitable for
such proper execution and results. Failure of the Contractor so to report shall constitute an
acknowledgment that the Owner's own forces or other contractors' completed or partially
completed or partial completed construction is fit and proper to receive the Contractor's Work,
except as to defects not then reasonably discoverable.
6.2.3 Costs caused by delays or by improperly timed activities or defective construction shall
be borne by the Contractor. The Contractor's sole remedy as against the Owner for costs
caused by delays or improperly timed activities or defective construction shall be an extension
of time.
6.2.4 The Contractor shall promptly remedy damage wrongfully caused by the Contractor to
completed or partially completed construction or to property of the Owner or other contractors
as provided in Subparagraph 10.2.5.
6.2.5 Claims and other disputes and matters in question between the Contractor and other
contractors shall be subject to the provisions of Paragraph 4.7 provided the other contractors
have reciprocal obligations.
6.2.6 The Owner and other contractors shall have the same responsibilities for cutting and
patching as are described for the Contractor in Paragraph 3.14.
6.2.7 Should the Contractor contend that he is entitled to an extension of time for completion
of any portion or portions of the work, he shall, within (72) hours of the occurrence of the cause
of the delay, notify Project Management in writing, of his contention: setting forth (A) the cause
for the delay, (B) a description of the portion or portions of work affected thereby, and (C) all
details pertinent thereto. A subsequent written application for the specific number of days of
extension of time requested shall be made by the Contractor to Project Management within (72)
hours after the delay has ceased to exist.
.1 It is a condition precedent to the consideration or prosecution of any claim for an
extension of time that the foregoing provisions be strictly adhered to in each instance and, if the
Contractor fails to comply, he shall be deemed to have waived the claim.
.2 The Contractor agrees that whether or not any delay, regardless of cause, shall be
the basis for an extension of time he shall have no claim against the Owner or Project
Management for an increase in the Contract price, nor a claim against the Owner or Project
17
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
Management for a payment or allowance of any kind for damage, loss or expense resulting from
delays; nor shall the Contractor have any claim for damage, loss or expense resulting from
interruptions to, or suspension of, his work to enable other contractors to perform their work.
The only remedy available to the Contractor shall be an extension of time.
6.3 Owner's Right to Clean Up
6.3.1 If a dispute arises among the Contractor, other contractors and the Owner as to the
responsibility under their respective contracts for maintaining the premises and surrounding
area free from waste materials and rubbish as described in Paragraph 3.15, the Owner may
clean up and allocate the cost among those responsible as Project Managementdetermines to
be just.
ARTICLE 7
CHANGES IN THE WORK
7.1 Changes
7.1.1 Changes in the Work maybe accomplished after execution of the Contract, and without
invalidating the Contract, by Change Order, Construction Change Directive or order for a minor
change in the Work, subject to the limitations stated in this Article 7 and elsewhere in the
Contract Documents.
7.1.2 A Change Order shall be based upon agreement between Project Management and
Contractor; a Construction Change Directive requires agreement by Project Management and
may or may not be agreed to by the Contractor; an order for a minor change in the Work may be
issued by Project Management alone.
7.1.3 Changes in the Work shall be performed under applicable provisions of the Contract
Documents, and the Contractor shall proceed promptly, unless otherwise provided in the
Change Order, Construction Change Directive or order for a minor change in the Work.
7.1.4 If unit prices are stated in the Contract Documents or subsequently agreed upon, and if
quantities originally contemplated are so changed in a proposed Change Order or Construction
Change Directive that application of such unit prices to quantities of Work proposed will cause
substantial inequity to the Owner or Contractor, the applicable unit prices shall be equitably
adjusted.
7.2 Change Orders
7.2.1 A Change Order is a written instrument prepared by Project Management and signed by
the Owner and/or Project Management and Contractor, stating their agreement upon all of the
following:
.1 a change in the Work;
.2 the amount of the adjustment in the Contract Sum, if any; and
.3 the extent of the adjustment in the Contract Time, if any.
7.2.2 The cost or credit to the Owner resulting from a change in the Work shall be determined
in one or more of the following methods:
IS
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 &2 COMBINED
.1 mutual acceptance of lump sum properly itemized and supported by sufficient
substantiating data to permit evaluation and payment, and approved by the appropriate
authority in writing;
.2 unit prices stated in the Contract Documents or subsequently agreed upon, and
approved by the appropriate authority in writing;
.3 cost to be determined in a manner agreed upon by the parties and a mutually
acceptable fixed or percentage fee;
.4 or by method provided in subparagraph 7.2.3.
7.2.3 If none of the methods set forth in Clauses 7.2.1 or 7.2.2 is agreed upon, the Contractor,
provided a written order signed by the Owner or Project Management is received, shall promptly
proceed with the Work involved. The cost of such Work shall then be determined by daily force
accounts in a form acceptable to the Owner and Project Management. The daily force account
forms shall identify Contractor and /or Subcontractor personnel by name, total hours for each
man, each piece of equipment and total hours for equipment and all material(s) by type for each
extra Work activity claim. Each daily force account form shall be signed by the designated
Project Management's representative no later than the close of business on the day the Work is
performed to verify the items and hours listed. Extended pricing of these forms shall be
submitted to Project Management with all supporting documentation required by Project
Management for inclusion into a change order. Unless otherwise provided in the Contract
Documents, cost shall be limited to the following: cost of materials, including sales tax and cost
of delivery; cost of labor, including social security, old age and unemployment insurance, and
fringe benefits required by agreement or custom; works' or workmen's compensation insurance;
and the rental value of equipment and machinery. Markups for overhead and profit will be in
accordance with subparagraph 7.2.4. Pending final determination of cost, payments on account
shall be made as determined by Project Management. The amount of credit to be allowed by
the Contractor for any deletion or change, which results in a net decrease in the Contract Sum,
will be the amount of the actual net cost to the Owner as confirmed by Project Management.
When both additions and credits covering related Work or substitutions are involved in any one
change, the allowance for overhead and profit shall be figured on the basis of the net increase,
if any with respect to that change,
7.2.4 The actual cost of Changes in the Work may include all items of labor or material, power
tools, and equipment actually used, utilities, pro rata charges for foreman, and all payroll
charges such as Public Liability and Workmen's Compensation Insurance. No percentage for
overhead and profit shall be allowed on items of Social Security and Sales Tax. If deductions
are ordered the amount of credit shall be net cost as defined in section 7.2.3 of the Contract.
Items considered as overhead shall include insurance other than that mentioned above, bond or
bonds, superintendent, timekeeper, clerks, watchmen, use of small tools, miscellaneous
supplies, incidental job costs, warranties, and all general home/field office expenses. The
actual cost of Changes in the Work (other than those covered by unit prices set forth in the
Contract Documents) shall be computed as follows:
.1 if the Contractor performs the actual Work, the maximum percentage mark-up for
overhead shall be five percent (5%) and the maximum percentage for profit shall be five percent
(5%);
.2 if the Subcontractor performs the actual Work, the percentage mark-up for overhead
and profit shall be a maximum addition of ten percent (10%). If the Contractor does not perform
the Work, the maximum mark-up for managing the Work will be five percent (5%);
19
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
3. if the Subcontractor performs part of the actual Work, his percentage mark-up for
overhead and profit shall be a maximum addition of ten percent (10%) on his direct Work only. If
the Contractor performs part of the actual Work, his percentage mark-up for overhead and profit
shall be a maximum addition of ten percent (10%) on his direct Work only.
7.2.5 The Contractor shall furnish to the Owner through Project Management, an itemized
breakdown of the quantities and prices used in computing the value of any change that might be
ordered. Any additional supporting documentation requested by Project Management such as
certified quotations or invoices shall be provided by the Contractor to Project Management at no
additional cost to the Owner.
7.2.6 If the Contractor claims that any instructions given to him by Project Management, by
drawings or otherwise, involve extra Work not covered by the Contract, he shall give Project
Management written notice thereof within five (5) days after the receipt of such instructions and
before proceeding to execute the work, except in emergencies endangering life or property, in
which case the Contractor shall proceed in accordance with Paragraph 10.3.
.1 The written notice to Project Management for the Extra Work shall include a complete
description of the extra Work, the total cost and a detailed cost breakdown by labor, material
and equipment for each additional activity required to be performed. Mark-ups shall be limited
as specified elsewhere in this Article.
.2 Except as otherwise specifically provided, no claim for additional cost shall be
allowed unless the complete notice specified by this subparagraph is given by the Contractor.
7.2.7 Unless otherwise agreed in writing, the Contractor shall carry on the Work and maintain
its progress during any dispute or claim proceeding, and Owner shall continue to make
payments to the Contractor in accordance with the Contract Documents. Disputes unresolved
shall be settled in accordance with subparagraph 4.3. The Contractor shall maintain completed
daily force account forms in accordance with subparagraph 7.2.3 for any dispute or claim item.
7.4 Authority
7.4.1 Project Management will have authority to order minor changes in the Work not involving
adjustment in the Contract sum or extension of the Contract Time and not inconsistent with the
intent of the Contract Documents. Such changes shall be effected by written order issued
through Project Management and shall be binding on the Owner and Contractor. The Contractor
shall carry out such written order promptly.
ARTICLE 8
TIME
8.1 Definitions
8.1.1 Unless otherwise provided, Contract Time is the period of time, including authorized
adjustments, allotted in the Contract Documents for Substantial Completion of the Work.
8.1.2 The date of commencement of the Work is the date established in the Agreement. The
date shall not be postponed by the failure to act of the Contractor or of persons or entities for
whom the Contractor is responsible.
20
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
8.1.3 The date of Substantial Completion is the date certified by Project Management in
accordance with Paragraph 9.8.
8.1.4 The term "day" as used in the Contract Documents shall mean calendar day unless
otherwise specifically defined.
8.1.5 The Owner/Project Management shall be the final judge as to whether Substantial
Completion has been achieved and certifies the date to the Contractor.
8.2 Progress and Completion
8.2.1 Time limits stated in the Contract Documents are of the essence of the Contract. By
executing the Agreement the Contractor confirms that the Contract Time is a reasonable period
for performing the Work.
8.2.2 The Contractor shall not knowingly, except by agreement or instruction of the Owner in
writing, prematurely commence operations on the site or elsewhere prior to the effective date of
insurance required by Article 11 to be furnished by the Contractor. The date of commencement
of the Work shall not be changed by the effective date of such insurance.
8.2.3 The Contractor shall proceed expeditiously with adequate forces and shall achieve
Substantial Completion within the Contract Time.
8.3 Delays and Extensions of Time
8.3.1 If the Contractor is delayed, at any time, in the progress of the Work by any act or
neglect of the Owner, Project Management, or by any employee of either, or by any separate
contractor employed by the Owner, or by changes ordered in the Work, or by fire, unusual delay
in transportation, adverse weather conditions not reasonably anticipatable, unavoidable
casualties or any causes beyond the Contractor's control, or by delay authorized by the Owner,
Project Management, or by any other cause which Project Management determines may justify
the delay, then the Contract Time shall be extended by no cost Change Order for such
reasonable time as Project Management may determine, in accordance with subparagraph
6.2.7.
8.3.2 Any claim for extension of time shall be made in writing to Project Management not more
than seventy-two (72) hours after the commencement of the delay in accordance with
paragraph 6.2.7; otherwise it shall be waived. Any claim for extension of time shall state the
cause of the delay and the number of days of extension requested. If the cause of the delay is
continuing, only one claim is necessary, but the Contractor shall report the termination of the
cause for the delay within seventy-two (72) hours after such termination in accordance with
paragraph 6.2.7; otherwise, any claim for extension of time based upon that cause shall be
waived.
8.3.3 No claim for an increase in the Contract Sum for either acceleration or delay will be
allowed for extensions of time pursuant to this Paragraph 8.3 or for other changes in the
Construction Schedules.
8.3.4 If the Project is delayed as a result of the Contractor's refusal or failure to begin the
Work on the date of commencement as defined in Paragraph 8.1.2, or his refusal or failure to
carry the Work forward expeditiously with adequate forces, the Contractor causing the delay
shall be liable for, but not limited to, delay claims from other Contractors which are affected.
21
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
ARTICLE 9
PAYMENTS AND COMPLETION
9.1 Contract Sum
9.1.1 The Contract Sum is stated in the Agreement and, including authorized adjustments, is
the total amount payable by the Owner to the Contractor for performance of the Work under the
Contract Documents.
9.2 Schedule of Values
9.2.1 Before the first Application for Payment, the Contractor shall submit to Project
Management, a schedule of values allocated to various portions of the Work, prepared in such
form and supported by such data to substantiate its accuracy as Project Management may
require. This schedule, unless objected to by Project Management, shall be used as a basis for
reviewing the Contractor's Applications for Payment.
9.3 Applications for Payment
9.3.1 At least fifteen days before the date established for each progress payment, the
Contractor shall submit to Project.Management an itemized Application for Payment for Work
completed in accordance with the schedule of values. Such application shall be notarized and
supported by such data substantiating the Contractor's right to payment as the Owner or Project
Management may require, such as copies of requisitions from Subcontractors and material
suppliers, and reflecting retainage if provided for elsewhere in the Contract Documents.
.1 Such applications may include request for payment on account of changes in the
Work which have been properly authorized by Construction Change Directives but not yet
included in Change Orders.
.2 Such applications may not include requests for payment of amounts the Contractor
does not intend to pay to a Subcontractor or material supplier because of a dispute or other
reason.
9.3.2 Unless otherwise provided in the Contract Documents, payments shall be made on
account of materials and equipment delivered and suitably stored at the site for subsequent
incorporation in the Work. If approved in advance by the Owner, payment may similarly be
made for materials and equipment suitably stored off the site at a location agreed upon in
writing. Payment for materials and equipment stored on or off the site shall be conditioned upon
compliance by the Contractor with procedures satisfactory to the Owner to establish the
Owner's title to such materials and equipment or otherwise protect the Owner's interest, and
shall include applicable insurance, storage and transportation to the site for such materials and
equipment stored off the site.
9.3.3 The Contractor warrants that title to all Work covered by an Application for Payment will
pass to the Owner no later than the time of payment. The Contractor further warrants that upon
submittal of an Application for Payment all Work for which approval for payment have been
previously issued and payments received from the Owner shall, to the best of the Contractor's
knowledge, information and belief, be free and clear of liens, claims security interests or
encumbrances in favor of the Contractor, Subcontractors, material suppliers, or other persons or
entities making a claim by reason of having provided labor, materials and equipment relating to
the Work. All Subcontractors and Sub-subcontractors shall execute an agreement stating that
title will so pass, upon their receipt of payment from the Contractor. The warranties are for the
22
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 &2 COMBINED
administrative convenience of the Owner only and do not create an obligation on the part of the
Owner to pay directly any unpaid subcontractor, laborer or materialmen. Such persons must
seek payment from the Contractor or his public construction bond surety only.
9.4 Approval for Payment
9.4.1 Project Management will assemble a Project Application for Payment by combining the
Contractor's applications with similar applications for progress payments from other Contractors
and certify the amounts due on such applications.
9.4.2 After Project Management's receipt of the Project Application for Payment, Project
Management will either approve the Application for Payment, with a copy to the Contractor, for
such amount as Project Management determine is properly due, or notify the Contractor in
writing of Project Management's reasons for withholding approval in whole or in part as provided
in Subparagraph 9.5.1.
9.4.3 The issuance of a separate Approval for Payment will constitute representations made
by Project Management to the Owner, based on their individual observations at the site and the
data comprising the Application for Payment submitted by the Contractor, that the Work has
progressed to the point indicated and that, to the best of Project Management's knowledge,
information and belief, quality of the Work is in accordance with the Contract Documents. The
foregoing representations are subject to an evaluation of the Work for conformance with the
Contract Documents upon Substantial Completion, to results of subsequent tests and
inspections, to minor deviations from the Contract Documents correctable prior to completion
and to specific qualifications expressed by Project Management. The issuance of a separate
Approval for Payment will further constitute a representation that the Contractor is entitled to
payment in the amount approved. However, the issuance of a separate Approval for Payment
will not be a representation that Project Management has (1) made exhaustive or continuous
on-site inspections to check the quality or quantity of the Work, (2) reviewed the Contractor's
construction means, methods, techniques, sequences or procedures, (3) reviewed copies of
requisitions received from Subcontractors and material suppliers and other data requested by
the Owner to substantiate the Contractor's right to payment or (4) made examination to
ascertain how or for what purpose the Contractor has used money previously paid on account of
the Contract Sum.
9.5 Decisions to Withhold Approval
9.5.1 Project Management may decline to approve an Application for Payment if, in its opinion,
the application is not adequately supported. If the Contractor and Project Management cannot
agree on a revised amount, Project Management shall process the Application for the amount it
deems appropriate. Project Management may also decline to approve any Application for
Payment because of subsequently discovered evidence or subsequent inspections. It may
nullify, in whole or part, any approval previously made to such extent as may be necessary in its
opinion because of: (1) defective Work not remedied; (2) third party claims filed or reasonable
evidence indicating probable filing of such claims; (3) failure of the Contractor to make
payments properly to Subcontractors or for labor, materials, or equipment; (4) reasonable
evidence that the Work cannot be completed for the unpaid balance of the Contract Sum; (5)
damage to Project Management, the Owner, or another contractor working at the project; (6)
reasonable evidence that the Work will not be completed within the contract time; (7) persistent
failure to carry out the Work in accordance with the Contract Documents.
23
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2COMBINED
No payment shall be made to the Contractor until certificates of insurance or other evidence of
compliance by the Contractor, with all the requirements of Article 11, have been filed with the
Owner and Project K8anagemnent.
8.5.2 When the above reasons for withholding approval are removed, approval will bmmade
for amounts previously withheld.
9.6 Progress Payments
9.8.1 After Project K8mnogomanthmaiasuedan8pprova| forPmymen1. the Owner shall make
payment in the manner and within the time provided in the Contract Documents, and shall so
notify Project K8anmgamant. From the total mf the amount determined tobe payable onm
progress payment, a retainagein accordance with the Florida Local Government Prompt
Payment Act, Chapter 218. Florida Statutes will be deducted and retained by the Owner until
the final payment |m made. The balance of the amount payable, less all previous payments, shall
be approved for payment.
.1 It is understood and agreed that the Contractor shall not be entitled to demand or
receive progress payment based on quantities of Work in excess of those provided in the
proposal or covered by approved change orders, except when such excess quantities have
been determined bv Project yNmna8emanttobe a part of the final quantity for the item of Work in
question.
.2 No progress payment shall bind the Owner to the acceptance of any materials or
Work in p|aoe, as to quality or quantity. All progress payments are subject to correction at the
time of final payments.
9.6.2 The Contractor shall promptly pay each Subcontractor, upon receipt of payment from the
Owner, out of the amount paid to the Contractor on account of such Subcontractor's portion of
the Work, the amount tm which said Subcontractor is entitled, reflecting percentages actually
retained from payments tothe Contractor on account of such Subcontractor's portion ofthe
Work. The Contractor shall, by appropriate agreement with each Subcontnmctor, require each
Subcontractor to make payments to Sub-subcontractors in similar manner.
9.6.3 Project Management will, on maqueot, furnish to a Suboontrootmr, if practicable,
information regarding percentages of completion or amounts applied for bythe Contractor and
action taken thereon by the Owner and Project K8anagennentonacoountofportion$ oftheVVork
done by such Subcontractor.
9.6.4 Neither the Owner or Project K8ana0ementnhm|| have an obligation to pay mrto see tO
the payment of money to a Subcontractor except as may otherwise be required by law.
9.6.5 Payment to material suppliers shall be treated in a manner similar to that provided in
Subparagraphs 9.8.2. 9.6.3snd 9.6.4.
9.6.6 /\progress payment, or partial or entire use or occupancy of the Project by the [}xvner
shall not constitute acceptance mfVVorh not in accordance with the Contract Documents.
9.6.7 All material and work covered by partial payments made shall thereupon become the
sole property of the Owner, and by this provision shall not be construed as relieving the
Contractor from the sole responsibility for the materials and Work upon which payments have
been made or the restoration for any damaged material, or as a waiver of the right of the Owner
or Project Management to require the fulfillment of all the terms of the Contract.
24
� GENERAL CONDITIONS
�
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
9.6.8 Except in case of bona fide disputes, or where the Contractor has some other justifiable
reason for delay, the Contractor shall pay for all transportation and utility services not later than
the end of the calendar month following that in which services are rendered and for all materials,
tools, and other expendable equipment which are delivered at the site of the Project. The
Contractor shall pay to each of his Subcontractors, not later than the end of the calendar month
in which each payment is made to the Contractor, the representative amount allowed the
Contractor on account of the Work performed by the Subcontractor. The Contractor shall, by an
appropriate agreement with each Subcontractor, also require each Subcontractor to make
payments to his suppliers and Sub-subcontractors in a similar manner.
9.7 Not Used
9.8 Individual Facility Substantial Completion, as used herein shall mean that point at
which, as approved in writing by Project Management, advising the Contractor that the
individual facility is at a level of completion such that the Owner or its designee can enjoy
beneficial use or occupancy and can use or operate it in all respects for its intended purpose.
This is separate and distinct from substantial completion of the entire project and partial use or
occupancy of an individual facility shall not result in the Project being deemed substantially
complete and such partial use or occupancy shall not be evidence of Substantial Completion.
9.8.1 Substantial Completion is the stage in the progress of the Work when the Work or
designated portion thereof is sufficiently complete in accordance with the Contract Documents
so the Owner can occupy or utilize the Work for its intended use.
9.8.2 When the Contractor considers that the Work, or a portion thereof which the Owner
agrees to accept separately, is substantially complete, the Contractor and Project Management
shall jointly prepare a comprehensive list of items to be completed or corrected. The Contractor
shall proceed promptly to complete and correct items on the list. Failure to include an item on
such list does not alter the responsibility of the Contractor to complete all Work in accordance
with the Contract Documents. Upon receipt of the list, Project Management, will make an
inspection to determine whether the Work or designated portion thereof is substantially
complete. If the inspection discloses any item, whether or not included on the list, which is not
in accordance with the requirements of the Contract Documents, the Contractor shall, before
issuance of the Certificate of Substantial Completion, complete or correct such item upon
notification by Project Management. The Contractor shall then submit a request for another
inspection by Project Management, to determine Substantial Completion. When the Work or
designated portion thereof is substantially complete, Project Management will prepare a
Certificate of Substantial Completion, shall establish responsibilities of the Owner and
Contractor for security, maintenance, heat, utilities, damage to the Work and insurance, and
shall fix the time within which the Contractor shall finish all items on the list accompanying the
Certificate. Warranties required by the Contract Documents shall commence on the date of
Substantial Completion of the Work or designated portion thereof unless otherwise provided in
the Certificate of Substantial Completion. The Certificate of Substantial Completion shall be
submitted to the Owner and Contractor for their written acceptance of responsibilities assigned
to them in such Certificate.
9.8.3 Upon Substantial Completion of the Work or designated portion thereof and upon
application by the Contractor and certification by Project Management, the Owner shall make
payment, reflecting adjustment in retainage, if any, for such Work or portion thereof as provided
in the Contract Documents.
9.9 Partial Occupancy or Use
25
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
9.9.1 The Owner may occupy or use any completed or partially completed portion of the Work
at any stage when such portion is designated by separate agreement with the Contractor,
provided such occupancy or use is consented to by the insurer as required under Subparagraph
11.3.1 and authorized by public authorities having jurisdiction over the Work. Such partial
occupancy or use may commence whether or not the portion is substantially complete, provided
the Owner and Contractor have accepted in writing the responsibilities assigned to each of them
for payments, retainage if any, security, maintenance, heat, utilities, damage to the Work and
insurance, and have agreed in writing concerning the period for correction of the Work and
commencement of warranties required by the Contract Documents. When the Contractor
considers a portion substantially complete, the Contractor and Project Management shall jointly
prepare and submit a list to Project Management as provided under Subparagraph 9.8.2.
Consent of the Contractor to partial occupancy or use shall not be unreasonably withheld. The
stage of the progress of the Work shall be determined by written agreement between the Owner
and Contractor or, if no agreement is reached, by decision of Project Management.
9.9.2 Immediately prior to such partial occupancy or use, the Owner, Project Management and
Contractor shall jointly inspect the area to be occupied or portion of the Work to be used in order
to determine and record the condition of the Work.
9.9.3 Unless otherwise agreed upon, partial occupancy or use of a portion or portions of the
Work shall not constitute acceptance of Work not complying with the requirements of the
Contract Documents.
9.10 Final Completion and Final Payment
9.10.1 Upon completion of the Work, the Contractor shall forward to Project Management a
written notice that the Work is ready for final inspection and acceptance and shall also forward
to Project Management a final Contractor's Application for Payment. Upon receipt, Project
Management will promptly make such inspection. When Project Management finds the Work
acceptable under the Contract Documents and the Contract fully performed, Project
Management will promptly issue a final Approval for Payment stating that to the best of their
knowledge, information and belief, and on the basis of their observations and inspections, the
Work has been completed in accordance with terms and conditions of the Contract Documents
and that the entire balance found to be due the Contractor and noted in said final Approval is
due and payable. Project Management's final Approval for Payment will constitute a further
representation that conditions listed in Subparagraph 9.10.2 as precedent to the Contractor's
being entitled to final payment have been fulfilled.
9.10.2 Neither final payment nor any remaining retained percentage shall become due until the
Contractor submits to Project Management (1) an affidavit that payrolls, bills for materials and
equipment, and other indebtedness connected with the Work for which the Owner or the
Owner's property might be responsible or encumbered (less amounts withheld by Owner) have
been paid or otherwise satisfied, (2) a certificate evidencing that insurance required by the
Contract Documents to remain in force after final payment is made, is currently in effect and will
not be canceled or allowed to expire until at least 30 days' prior written notice has been given to
the Owner, (3) a written statement that the Contractor knows of no substantial reason that the
insurance will not be renewable to cover the period required by the Contract Documents, (4)
consent of surety, if any, to final payment and (5), if required by the Owner, other data
establishing payment or satisfaction of obligations, such as receipts, releases and waivers of
liens, claims, security interests or encumbrances arising out of the Contract. The following
documents (samples included in Section 001027) are required for Final Payment:
26
GENERAL CONDrrIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
(1) Application and Certificate for Payment
(2) Continuation Sheet
(3) Certificate of Substantial Completion
(4) Contractor's Affidavit of Debts and Claims
(5) Contractor's Affidavit of Release of Liens
(6) Final Release of Lien
9.10.3 Acceptance of final payment by the Contractor, a Subcontractor or material supplier shall
constitute a waiver of claims by that payee except those previously made in writing and
identified by that payee as unsettled at the time of final Application for Payment. Such waivers
shall be in addition to the waiver described Subparagraph 4.3.5.
9.11 Payment of Subcontractors
9.11.1 Any requirement of this Article 9 that the Contractor furnish proof to the Owner and
Project Management that the subcontractors and materialmen have been paid is for the
protection and convenience of the Owner only. Unpaid subcontractors and materialmen may
only seek payment from the Contractor and the surety that provided the Contractor's Public
Construction Bond. The Contractor must insert this paragraph 9.11 in all its contracts with
subcontractors and materialmen.
ARTICLE 10
PROTECTION OF PERSONS AND PROPERTY
10.1 Safety Precautions and Programs
10.1.1 The Contractor shall be responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the performance of the Contract. The Contractor
shall submit the Contractor's safety program to Project Management for review and coordination
with the safety programs of other Contractors.
10.1.2 In the event the Contractor encounters on the site material reasonably believed to be
asbestos or polychlorinated biphenyl (PCB) which has not been rendered harmless, the
Contractor shall immediately stop Work in the area affected and report the condition to the
Owner and Project Management in writing. The Work in the affected area shall not thereafter
be resumed except by written agreement of the Owner and Contractor if in fact the material is
asbestos or polychlorinated biphenyl (PCB) and has not been rendered harmless. The Work in
the affected area shall be resumed in the absence of asbestos or polychlorinated biphenyl
(PCB), or when it has been rendered harmless, by written agreement of the Owner and
Contractor, or in accordance with final determination by Project Management.
10.1.3 The Contractor shall not be required pursuant to Article 7 to perform without consent any
Work relating to asbestos or polychlorinated biphenyl (PCB).
10.1.5 If reasonable precautions will be inadequate to prevent foreseeable bodily injury or death
to persons resulting from a material or substance encountered on the site by the Contractor, the
Contractor shall, upon recognizing the condition, immediately stop Work in the affected area
and report the condition to Project Management in writing. The Owner, Contractor and Project
Management shall then proceed in the same manner described in Subparagraph 10.1.2.
10.1.6 The Owner shall be responsible for obtaining the services of a licensed laboratory to
verify a presence or absence of the material or substance reported by the Contractor and, in the
event such material or substance is found to be present, to verify that it has been rendered
27
GENERAL CONDITIONS
AOA COMPLIANCE SEGMENT# 1 & 2COK8B|NEO
harmless. Unless otherwise required by the Contract Documents, the Owner shall furnish in
writing to the Contractor and Project K8mnmgennendtMenmmnemmndqua|ifiomt|onmofpenoonaor
entities who are tm perform tests verifying the presence orabsence of such material or
substance or who are to perform the task of removal or safe containment of such material or
substance. The Contractor and Project K8anagennentvvi|| pnomot|yrep|yto the Owner\nwriting
stating whether or not any of them has reasonable objection to the persons or entities proposed
by the Owner. |f the Contractor or Project K8anagemnontMaeanobiectiontompenaonorentity
proposed by the Owner, the Owner shall propose another to whom the Contractor and Project
Management have no reasonable objection.
'
10'2 Safety of Persons and Property
10.2.1 The Contractor shall take reasonable precautions for safety of, and shall provide
reasonable protection tm prevent damage, injury or|os$to:
.1 employees on the Work and other persons who maybe affected thereby;
.2 the Work and nnmter|a|e and equipment to be incorporated thmrein, whether in storage
on or off the site, under care, custody or control of the Contractor or the Contractor's
Subcontractors or@ub-nuboontraotora;
.3 other property at the site or adjacent thereto, such as trees, shrubs, |axvnm, vvo|km,
pavements, roadways, structures and utilities not designated for removal, relocation or
replacement in the course ofconstruction; and
4 construction or operations by the Owner or other Contractors.
10.2.2 The Contractor shall give notices and comply with applicable laws, ordinances, rules,
regulations and lawful orders of public authorities bearing on safety of persons or property or
their protection from damage, injury or loss.
10.2.3 The Contractor shall enact and nnairtain, as required by existing conditions and
performance of the Cmntraot, reasonable safeguards for mafmb/ and protection, including posting
danger signs and other warnings against hazards, promulgating safety regulations and notifying
owners and users of adjacent sites and utilities.
10.2.4 When use or storage of explosives or other hazardous materials or equipment or
unusual methods are necessary for execution of the Work, the Contractor shall exercise utmost
care and carry on such activities under supervision of property qualified personnel.
10.2.5 The Contractor shall promptly remedy damage and loss to property referred toin
Clauses 10.2.1.2. 10.2.1.3. 10.2.1.4 caused in whole or in part by the Contractor, a
Gubomntractor' a Sub-subcontractor, or anyone directly or indirectly employed by any of them, or
by anyone for whose acts they may be liable and for which the Contractor is responsible under
Clauses 10.2.1.2. 10.2.1.3 and 10.2.1.4. except damage or loss attributable tm acts oromissions
of the Owner, oranyone directly o[indirectly employed by the Owner, orbv anyone for whose
acts the Owner may be liable, and not attributable to the fault 0r negligence nf the Contractor.
The foregoing obligations of the Contractor are in addition tmthe Contractor's obligations under
ParGgraph3.18.
10.2.0 The Contractor shall designate a responsible member of the Contractor's organization at
the site whose duty shall be the prevention nfaccidents. This person shall be the Contractor's
superintendent unless otherwise designated by the Contractor in writing toProject
K8mnogmnnenL
28
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
10.2.7 The Contractor shall not load or permit any part of the construction or site to be loaded
so as to endanger its safety.
10.3 Emergencies
10.3.1 In an emergency affecting safety of persons or property, the Contractor shall act, at the
Contractor's discretion, to prevent threatened damage, injury or loss. Additional compensation
or extension of time claimed by the Contractor on account of an emergency shall be determined
as provided in Paragraph 4.3 and Article 7.
ARTICLE 11
INSURANCE AND BONDS
11.1.1 Prior to commencement of Work governed by this contract (including the prestaging of
personnel and material), the Contractor shall obtain, at its own expense, insurance as specified
in the schedule set forth in Section 00110 Proposal Form which are made part of this
Agreement. The Contractor will ensure that the insurance obtained will extend protection to all
subcontractors engaged by the Contractor. As an alternative the Contractor may require all
subcontractors to obtain insurance consistent with the attached schedules.
11.1.2 The Contractor will not be permitted to commence Work governed by the Agreement
(including pre-staging of personnel and material) until satisfactory evidence of the required
insurance has been furnished to the County as specified below. Delays in the commencement
of Work resulting from the failure of the Contractor to provide satisfactory evidence of the
required insurance shall not extend deadlines specified in this Agreement and any penalties and
failure to perform assessments shall be imposed as if the Work commenced on the specified
date and time, except for the Contractor's failure to provide satisfactory evidence of insurance.
11.1.3 The Contractor shall maintain the required insurance throughout the entire term of this
contract and any extensions specified in any attached schedules. Failure to comply with this
provision may result in the immediate suspension of all Work until the required insurance has
been reinstated or replaced. Delays in the completion of Work resulting from the failure of the
Contractor to maintain the required insurance shall not extend deadlines specified in this
Agreement and any penalties and failure to perform assessments shall be imposed as if the
Work commenced on the specified date and time, except for the Contractor's failure to provide
satisfactory evidence of insurance.
11.1.4 The Contractor shall provide, to the County in care of Project Management, as
satisfactory evidence of the required insurance, either:
Certificate of Insurance
or
A certified copy of the actual insurance policy
11.1.5 The County, at its sole option, has the right to request a certified copy of any or all
insurance policies required by this Contract.
11.1.6 All insurance policies must specify that they are not subject to cancellation, nonrenewal,
material change, or reduction in coverage unless a minimum of thirty (30) days prior notification
is given to the County by the insurer.
29
GENERAL CON [TIONS
ADA��K8PLk�NCE8BGK8ENT# 1 �k2COMB(y4B3
11.1.7 The acceptance and/or approval of the Contractor's insurance shall not be construed as
relieving the Contractor from any liability mr obligation assumed under this contract orimposed
by |mxv.
11.1.8 The Monroe County Board of County Commissioners, its employees and officials will be
included as "Additional Insured" on all policies, except for Worker's Compensation.
11.1.9 In addition, the County will be named as an additional insured and loss payee on all
policies covering County -owned property.
11.1.10 Any deviations from these General Insurance Requirements must ba requested |n
writing on the County prepared form entitled "Request for Waiver of Insurance Requirements"
and approved by the Monroe County's Risk Manager.
11'2 Builder's Risk Insurance
11.2.1 Builder's Fl|sh will be required on sites when there are structural alterations on a
building.
11'3 Public Construction Bond
11.3.1 The Owner shall require the Contractor to furnish a Public Construction Bond in the form
provided by the Owner as a guarantee for the faithful performance of the Contract (including
guarantee and maintenance provisions) and the payment of all obligations arising thereunder.
The Public Construction Bond shall be in an amount at least equal to the contract price. This
contract is subject tothe provisions of Section 255.05. Florida Statutea, which are incorporated
herein.
ARTICLE 12
UNCOVERING AND CORRECTION OF WORK
12'1 Uncovering of Work
121.1 |fa portion of the Work ia covered contrary to Project K8mnmgomont'oraquest or to
requirements specifically expressed in the Contract Documents, it must, if required in writing by
Project Management ba uncovered for their observation and be replaced a1the Contractor's
expense without change inthe Contract Time.
12.1.2 If a portion of the Work has been covered which Project K8anagemnonthamnot
specifically requested to observe prior to its being coxered. Project Management may request to
see such Work and it shall be uncovered by the Contractor, if such Work is in accordance with
the Contract Documents, costs ofuncovering and replacement shall, by appropriate Change
Order, be charged to the Owner, if such Work in not in accordance with the Contract
Documents, the Contractor shall pay such costs unless the condition was caused by the Owner
or one of the other Contractors in which event the Owner shall be responsible for payment of
such costs.
|
12'2 Correction of Work
12.2.1 The Contractor shall promptly correct Work rejectedby Project K8anagernontorhei|inQtm
| conform to the requirements of the Contract Oocurnentm, whether observed before or after
Substantial Completion and whether or not fabricated, installed or completed. The Contractor
� JO
' GENERAL CONDITIONS
&D�COMPL�NCESBGK8ENT# 1 & 2{�OMB|NEO
shall bear costs mfcorrecting such rejectedWork, including additional testing and inspections
and compensation for Project K8mnagemnent'ommrv|oysand $xpmnoaamadenmoeoearyMhereby.
12.2.2 If, within one year after the date cf Substantial Completion of the Work ordesignated
portion thereof, or after the date for commencement of warranties established under
Subparagraph 9.9. orbyterms of an applicable special warranty required by the Contract
Documents, any of the Work is found to be not in accordance with the requirements of the
Contract Documents, the Contractor shall correct it promptly after receipt of written notice from
the Owner todo so unless the Owner has previously given the Contractor a written acceptance
mf such condition. This period mf one year shall be extended with respect to portions ofWork
first performed after Substantial Completion by the period mf time between Substantial
Completion and the actual performance of the Work. This obligation under this Subparagraph
12.2.2 shall survive acceptance of the Work under the Contract and termination of the Contract.
The Owner shall give such notice promptly after discovery of the condition.
12.2.3 The Contractor shall remove from the site portions cf the Work which are not in
accordance with the requirements of the Contract Documents and are neither corrected by the
Contractor nor accepted by the Owner.
12.2.4 |f the Contractor fails to correct nonconforming Work within a reasonable time, the
Owner may correct it |n accordance with Paragraph 2.4. |f the Contractor does not proceed with
correction of such nonconforming Work within a reasonable time fixed by written notice from
Project Management, the Owner may remove it and store the salvable materials or equipment
at the Contractor's expense. If the Contractor does not pay costs of such nsnnovm| and storage
within ten days after written notice, the Owner may upon ten additional days' written notice sell
such materials and equipment at auction or at private sale and shall account for the proceeds
thereof, after deducting costs and damages that should have been borne by the Contractor,
including compensation for Project K8anaQernent'amen/\casondexpenamernadenaoeemary
thereby. If such proceeds of sale do not cover costs which the Contractor should have borne,
the Contract Sum shall be reduced by the deficiency. |f payments then mr thereafter due the
Contractor are not sufficient to cover such amount, the Contractor shall pay the difference tothe
Owner.
12.2.5 The Contractor shall bear the cost of correcting destroyed or damaged construction,
whether completed or partially completed, ofthe Owner mr other Contractors caused bythe
Contractor's correction or removal of Work which is not in accordance with the requirements of
the Contract Documents.
12.2.6 Nothing contained in this Paragraph 12.2 mho|| be construed toestablish m period of
limitation with respect tm other obligations which the Contractor might have under the Contract
Documents. Establishment of the time period of one year as described in Subparagraph 12.2.2,
relates only to the specific obligation of the Contractor to correct the Work, and has no
relationship to the time within which the obligation to comply with the Contract Documents may
be sought to be enforced, nor to the time within which proceedings may be commenced to
establish the Contractor's liability with respect to the Contractor's obligations other than
specifically to correct the Work.
12'3 Acceptance of Nonconforming Work
! 12�3�1 |f the ��wnerprefers to accept VVmrkwhich |o not in accordance xviththe requirannon1s of
|
| the Contract C)ocurnentm, the Owner may dm so instead of requiring its mmrnova| and mzrnaot|on.
in which case the Contract Sum will bmreduced as appropriate and equitable. Such adjustment
shall be effected whether or not final payment has been made.
\ 3|
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# I & 2 COMBINED
. ........... ............
ARTICLE 13
MISCELLANEOUS PROVISIONS
13.1 Governing Law
13.1.1 The contract shall be governed by the laws of the State of Florida. Venue for any claims
or disputes arising under this contract shall be in the Circuit Court of the 16th Judicial Circuit of
the State of Florida.
13.2 Successors and Assigns
13.2.1 The Owner or Project Management (as the case may be) and the Contractor each binds
himself, his partners, successors, assigns, and legal representatives of such other party in
respect to all covenants, agreements, and obligations contained in the Contract Documents.
Neither party to the Contract shall assign the Contract or sublet it as a whole without the written
consent of the other.
13.2.2 The Contractor shall not assign any monies due or to become due under this Contract
without prior written consent of the Owner or Project Management.
13.3 Written Notice
13.3.1 Any written notices or correspondence given pursuant to this contract shall be sent by
United States Mail, certified, return receipt requested, or by courier with proof of delivery. Notice
shall be sent to the following persons:
For Contractor: D.L. Porter Constructors, Inc.
6574 Palmer Park Circle
Sarasota, FL 34238
For Owner: Director of Project Management County Administrator
1100 Simonton St. Room 2-216 1100 Simonton St.
Key West, Florida 33040 Key West Florida 33040
13.4 Rights and Remedies
13.4.1 Duties and obligations imposed by the Contract Documents and rights and remedies
available thereunder shall be in addition to and not a limitation of duties, obligations, rights and
remedies otherwise imposed or available by law.
13.4.2 No action or failure to act by the Owner, Project Management, or Contractor shall
constitute a waiver of a right or duty afforded them under the contract, nor shall such action or
32
GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
failure to act constitute approval of or acquiescence in a breach thereunder, except as may be
specifically agreed in writing.
13.5 Tests and Inspections
13.5.1 Tests, inspections and approvals of portions of the Work required by the Contract
Documents or by laws, ordinances, rules, regulations or orders of public authorities having
jurisdiction shall be made at an appropriate time. Unless otherwise provided, the Contractor
shall make arrangements for such tests, inspections and approvals with an independent testing
laboratory or entity acceptable to the Owner, or with the appropriate public authority, and shall
bear all related costs of tests, inspections and approvals. The Contractor shall give Project
Management timely notice of when and where tests and inspections are to be made so Project
Management may observe such procedures. The Owner shall bear costs of test, inspections or
approvals which do not become requirements until after bids are received or negotiations
concluded.
13.5.2 If Project Management, Owner or public authorities having jurisdiction determine that
portions of the Work require additional testing, inspection or approval not included under
Subparagraph 13.5.1, Project Management will instruct the Contractor to make arrangements
for such additional testing, inspection or approval by an entity acceptable to the Owner, and the
Contractor shall give timely notice to Project Management of when and where tests and
inspections are to be made so Project Management may observe such procedures. The Owner
shall bear such costs except as provided in Subparagraph 13.5.3.
13.5.3 If such procedures for testing, inspection or approval under Subparagraphs 13.5.1 and
13.5.2 reveal failure of the portions of the Work to comply with requirements established by the
Contract Documents, the Contractor shall bear all costs made necessary by such failure
including those of repeated procedures and compensation for Project Management's services
and expenses.
13.5.4 Required certificates of testing, inspection or approval shall, unless otherwise required
by the Contract Documents, be secured by the Contractor and promptly delivered to Project
Management.
13.5.5 If Project Management is to observe tests, inspections, or approvals required by the
Contract Documents, CONTRACTOR will promptly notify Project Management of the date,
place and time of tests, inspections, or approvals, so that Project Management may observe.
13.5.6 Test or inspections conducted pursuant to the Contract Documents shall be made
promptly to avoid unreasonable delay in the Work.
13.7 Commencement of Statutory Limitation Period
13.7.1 The statute of limitations applicable to this contact are as provided in Section 95.11 (3)
(C), Florida Statutes.
ARTICLE 14
TERMINATION OR SUSPENSION OF THE CONTRACT
14.1 Termination by the Owner for Cause
14.1.1 The Owner may terminate the Contract if the Contractor:
33
GENERAL CONDITIONS
AO8 COMPLIANCE SEGMENT# I & 2 COMBINED
1 persistently or repeatedly refuses or fails to supply enough properly skilled workers or
proper materials;
.2 fails to make payment to Subcontractors for materials or labor in accordance with the
respective agreements between the Contractor and the Subcontractors;
.3 persistently disregards |mxva, ordinanneo, or rules, regulations ¢r orders ofo public
authority having juriodiction, with particular emphasis on the requirements for compliance with
the Americans with Disabilities Act of 1990 (ADA) and ADA Amendments Act of 2008, or
applicable State |mvv, whichever are the most stringent;
.or
.4 otherwise io guilty of substantial breach m/a provision mfthe Contract Documents.
14.1.2 When any of the above reasons exist, the Owner, after consultation with Project
Management, and upon certification by Project K8mnagemnentthmtmuffioientoauoeexiotetm
justify such action, may without prejudice toanyotherri8htoorremedieamftheOwnermndafter
giving the Contractor and the Contractor's surety, if any, 72 hours written notice, terminate
employment of the Contractor and may, subject bx any prior rights of the surety:
.1 take possession of the site and of all materials, equipment, tools, and construction
equipment and machinery thereon owned by the Contractor;
.3 accept assignment of subcontracts pursuant tm Paragraph 5.4; and
.3 finish the Work by whatever reasonable method the Owner may deem expedient.
14.1.3 When the Owner terminates the Contract for one of the reasons stated in Subparagraph
14.1.1, the Contractor shall not be entitled to receive further payment until the Work is finished.
14'2 Suspension on Termination by the Owner for Convenience
14.2.1 The Owner may, without cause, order the Contractor in writing to terminate, suspend,
delay mr interrupt the Work in whole orinpart for such period of time am the Owner may
determine.
14.2.2 In the event of Termination the Owner shall pay for work completed to date of
Termination.
\
� 34
/ GENERAL CONDITIONS
ADA COMPLIANCE SEGMENT*1 &2 COMBINED
SECTION 01750
SUPPLEMENTAL CONDITIONS
Supplemental Conditions 01750- 1
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 1011/2011
(Construction Contracts)
The supplemental conditions contained in this section are intended to cooperate with, to supplement, and to modify the
general conditions and other specifications. In case of disagreement with any other section of this contract, the
Supplemental Conditions shall govern.
1. Termination(Cause and Convenience)
2. Access to Records
3. Retention of Records
4. Remedies
5. Environmental Compliance(Clean Air Act and Clean Water Act)
6. Energy Efficiency
7. Special Equal Opportunity Provisions
8. Conflict of Interest
9. Utilization of Minority and Women's Businesses
10. Federal Labor Standards Provisions(Davis-Bacon,Copeland, and Contract Work Hours Act)
11. Guidance to Contractor for Compliance with Labor Standards Provisions
1. TERMINATION(CAUSE AND/OR CONVENIENCE)
A. This contract may be terminated in whole or in part in writing by either party in the event of substantial failure by
the other party to fulfill its obligations under this contract through no fault of the terminating party,provided that
no termination may be effected unless the other party is given:
(1) not less than ten (10) calendar days written notice (delivered by certified mail, return receipt requested) of
intent to terminate;and
(2) an opportunity for consultation with the terminating party prior to termination.
B. This contract may be terminated in whole or in part in writing by the local government for its convenience,
provided that the other party is afforded the same notice and consultation opportunity specified in l(a) above.
C. If termination for default is effected by the local government, an equitable adjustment in the price for this
contract shall be made,but
(1) no amount shalt he allowed for anticipated profit on unperformed services or other work,and
(2) any payment due to the contractor at the time of termination may be adjusted to cover any additional costs to
the local government because of the contractor's default.
If termination for convenience is effected by the local government, the equitable adjustment shall include a
reasonable profit for services or other work performed for which profit has not already been included in an
invoice.
For any termination, the equitable adjustment shall provide for payment to the contractor for services rendered
and expenses incurred prior to receipt of the notice of intent to terminate, in addition to termination settlement
costs reasonably incurred by the contractor relating to commitments (e.g., suppliers, subcontractors) which had
become firm prior to receipt of the notice of intent to terminate.
15-1
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/1/2011
(Construction Contracts)
D. Upon receipt of a termination action tinder paragraphs (4) or (b) above, the contractor shall (1) promptly
discontinue all affected Work(unless the notice directs otherwise) and(2)deliver or otherwise make available to
the local government all data, drawings, reports specifications, Summaries and other Such information, as may
have been accumulated by the contractor in performing this contract,whether completed or in process.
E. Upon termination, the local government may take over the work and may award another party a contract to
complete the work described in this contract.
F. If, after termination for failure of the contractor to fulfill contractual obligations., it is determined that the
contractor had not failed to fulfill contractual obligations, the termination shall be deemed to have been for the
convenience of the local government. In such event, adjustment of the contract price shall be made as provided in
paragraph(c)above,
2. ACCESS TO RECORDS
The local government, the Florida Department of Economic Opportunity, the U.S. Department of Housing and Urban
Development, the Comptroller General of the United States, and any of their duly authorized representatives, shall have
access to any books, documents, papers, and records of the contractor which are directly pertinent to this contract for the
purpose of making audit,examination,excerpts,and transcriptions.
3. RETENTION OF RECORDS
The contractor shall retain all records relating to this contract for six years after the local government makes final
payment and all other pending matters are closed.
4. REMEDIES
Unless otherwise provided in this contract, all claims, counter-claims, disputes and other matters in question between the
local government and the contractor, arising out of or relating to this contract, or the breach of it, will be decided by
arbitration, if the parties mutually agree,or in a Florida court of competent jurisdiction.
S. ENVIRONMENTAL COMPLIANCE
If this contract exceeds $100,000, the contractor shall comply with all applicable standards, orders, or requirements
issued under section 306 of the Clean Air Act(42 U.S.C. 1857(h),section 508 of the Clean Water Act(33 U.S.C. 1368),
Executive Order 11738, and U.S. Environmental Protection Agency regulations(40 C.F.R. Part 15). The contractor shall
include this clause in any subcontracts over$100,000.
6. ENERGY EFFICIENCY
The contractor shall comply with any mandatory standards and policies relating to energy efficiency which are contained
in the state energy conservation plan issued in compliance with the Energy Policy and Conservation Act(Public Law 94-
163).
7. SPECIAL EQUAL OPPORTUNITY PROVISIONS
A. Activities and Contracts Not Subject to Executive Order 11246.as Amended
(Applicable to Federally assisted construction contracts and related subcontracts$10,000 and under.)
During the performance of this contract,the Contractor agrees as follows:
15-2
Department of Economic Opportunity-Community Development Block Grant Program
CDBG Supplemental Conditions 10/1/2011
(Construction Contracts)
(1) The Contractor shall not discriminate against any employee or applicant for employment because of race,
color, religion, sex, or national origin. The Contractor shall take affirmative action to ensure that applicants
for employment are employed, and that employees are treated during employment, without regard to their
race, color, religion, sex, or national origin. Such action shall include, but not be limited to, the following:
employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination;
rates of pay or other forms of compensation, and selection for training, including apprenticeship.
(2) The Contractor shall post in conspicuous places, available to employees and applicants for employment,
notices to be provided by Contracting Officer seeking forth the provisions of this nondiscrimination clause.
The Contractor shall state that all qualified applicants be considered without regard to race, color, religion,
sex or national origin.
(3) Contractors shall incorporate foregoing requirements in all subcontracts.
B. F,'xectitive Or 9r.I Lonu".1ac J?qyp-� o V0 )
(1) Section 202 Equal Opportunity Clause
During the performance of this contract, the contractor agrees as follows:
(a) The Contractor will not discriminate against any employee or applicant for employment because of
race, color, religion, sex, or national origin. The Contractor will take affirmative action to ensure
that applicants are employed, and that employees are treated during employment, without regard to
their race, color, religion, sex, or national origin. Such action shall include,but not be limited to, the
following: employment, upgrading, demotion, or transfer; recruitment, or recruitment advertising;
layoff or termination, rates of pay or other forms of compensation; and selection for training,
including apprenticeship. The Contractor agrees to post in a conspicuous place, available to
employees and applicants for employment, notices to be provided setting forth the provisions of this
nondi scri mi nation clause.
(b) The Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the
Contractor, state that all qualified applicants will receive consideration without regard to race, color,
religion,sex,or national origin.
(c) The Contractor will send to each labor union or representative of workers with which he has a
collective bargaining agreement or other contract or understanding a notice to be provided by the
Contract Compliance Officer advising the said labor union or worker's representatives of the
Contractor's commitment Linder this section,and shall post copies of the notice in conspicuous places
available to employees and applicants for employment.
(d) The Contractor will comply with all provisions of Executive Order 11246 of September 24, 1965,
and of the Rules, Regulations, and Relevant Orders of the Secretary of Labor.
(e) The Contractor will furnish all information and reports required by Executive Order 11246 of
September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant
thereto, and will permit access to his books, records, and accounts by the Department and the
Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations,
and others.
15-3
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 1011/2011
(Construction Contracts)
(f) In the event of the Conti-actor's noncompliance with the nondiscrimination clauses of this contract or
with any of the said rules, regulations, or orders,this contract may be canceled, be declared ineligible
for further Government contracts in accordance with procedures authorized in Executive Order
11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as
otherwise provided by law.
(g) The Contractor will include the Provisions of the sentence immediately preceding Paragraph (a) and
the provisions of Paragraphs (a)through (g) in every subcontract or purchase order unless exempted
by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section 204 of Executive
Order 11246 of September 24, 1965, so that such provisions will be binding upon each subcontractor
or vendor. The Contractor will take such action with respect to any subcontract or purchase order as
the Department may direct as a means of enforcing such provisions, including sections of
noncompliance. Provided, however, that in the event a Contractor becomes involved in, or is
threatened with, litigation with a subcontractor or vendor as a result Of Such direction by the
Department, the Contractor may request the United States to enter into such litigation to protect the
interest of the United States.
(2) Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity (Executive
Order 11246). (Applicable to contracts/subcontracts exceeding$10,000.)
(a) The Offerer's or Bidder's attention is called to the "Equal Opportunity Clause" and the "Standard
Federal Equal Employment Opportunity Construction Contract Specifications"set forth herein.
(b) The goals and timetables for minority and female participation,expressed in percentage terms for the
Contractor's aggregate workforce in each trade on all construction work in the covered area, are as
follows:
Female participation: 6.9%(statewide)
Minority participation (See Appendix at CDBG-25 for goals for each county)
These goals are applicable to all Contractor's construction work (whether or not it is federally-
assisted) performed in the covered area. If the Contractor performs construction work in a
geographic area located outside of the covered area, it shall apply the goals established for Such
geographic area where the work is actually performed. With regard to this second area, the
Contractor also is Subject to the goals for both its Federally involved and non-Federally involved
construction.
The Contractor's compliance with Executive Order and the regulations in 41 CFR Part 60-4 shall be
based on its implementation of the Equal Opportunity Clause, specific affirmative action obligations
required by the specifications set forth in 41 CFR 60-4.3 (a), and its efforts to meet the goals
established or the geographic area where the contract resulting from his solicitation is to be
performed. The hours of minority and female employment or training must be substantially uniform
throughout the length of the contract and in each trade the Contractor shall make a good faith effort
to employ minorities and women evenly on each of its projects. The transfer of minority or female
employees or trainees from Contractor to Contractor or from project to project for the Sole purpose of
meeting the Contractor's goals shall be a violation of the contract, the Executive Order, and the
regulations in 41 CFR Part 60-4. Compliance with the goals will be measured against the total work
hours performed.
15-4
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/1/2011
(Construction Contracts)
(c) The Contractor shall provide written notification to the Director of the Office of Federal Contract
Compliance Programs within 10 working days of award of any construction subcontract in excess of
$10,000 at any tier for construction work under the contract resulting from this solicitation. The
notification shall list the name, address, and telephone number of the subcontractor; employer
identification number; estimated dollar amount of the subcontract; estimated starting and completion
dates of the subcontract; and the geographical area in which the contract is to be performed. -
(d) As used in this Notice, and in the contract resulting from the solicitation, the "covered area" is the
county in which the contract work is being undertaken.
(3) Standard Federal Equal Employment Opportunity Construction Contract Specifications (Executive Order
11246).
(a) As used in these specifications:
1. "Covered area" means the geographical area described in the solicitation from which this
contract resulted;
2. "Director" means Director, Office of Federal Contract Compliance Programs, United States
Department of Labor, or any person to whom the Director delegates authority;
3. "Employer identification number" means the Federal Social Security number used on the
Employer's quarterly Federal Tax Return,U. S.Treasury Department Form 941.
4. "Minority" includes:
(1) Black(all persons having origins in any of the Black African racial groups);
(11) Asian and Pacific Islander(all persons having origins in any of the Far East, Southeast Asia,
the Indian Subcontinent,or the Pacific Island);and
(111) American Indian or Alaskan Native (all persons having origins in any of the original
peoples of North America and maintaining identifiable tribal affiliations through
membership and participation or community identification).
(4) Whenever the Contractor, or any Subcontractor at any tier, subcontracts a portion of the work involving any
construction trade, it shall physically include in each subcontract in excess of$10,000 the provisions of these
specifications and the Notice which contains the applicable goals for minority and female participation and
which is set forth in the solicitations from which this contract resulted.
(5) If the Contractor is participating (Pursuant to 41 CFR 60-4.5) in a Hometown Plan approved by the U. S.
Department of Labor in the covered area either individually or through an association, its affirmative action
obligations on all work in the Plan area(including goals and timetables) shall be in accordance with that Plan
for those trades which have unions participating in the Plan. Contractors must be able to demonstrate their
participation in and compliance with the provisions of any such Hometown Plan. Each Contractor or
Subcontractor participating in an approved Plan is individually required to comply with its obligations under
the EEO clause, and to make a good faith effort to achieve each goal under the Plan in each trade in which it
has employees. 'rhe overall good faith performance by other Contractors toward a goal in an approved Plan
does not execute any covered Contractor's or Subcontractor's failure to take good faith efforts to achieve the
Plan goals and timetables.
IS-5
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/1/2011
(Construction Contracts)
(6) The Contractor shall implement the specific affirmative action standards provided in paragraphs (9) (a)
through (p). of these specifications. The goals set forth in the solicitation from which this contract resulted
are expressed as percentages of the total hours of employment and training of minority and female utilization
the Contractor should reasonably be able to achieve in each construction trade in which it has employees in
the covered area. Covered construction contractors performing contracts in geographical -areas where they do
not have a Federal or Federally-assisted construction contract shall apply the minority and female goals
established for the geographic area where the contract is being performed. Goals are published periodically
in the Federal Register in notice form and such notices may be obtained from any Office of Federal Contract
Compliance Programs office or from Federal procurement contracting officers. The Conti-actor is expected
to make substantially uniform progress in meeting its goals in each craft during the period specified.
(7) Neither the provisions of any collective bargaining agreement, nor the failure by a union with whom the
Contractor has a collective bargaining agreement, to refer either minorities or women shall excuse the
Contractor's obligations under these specifications, Executive Order 11246, or the regulations promulgated
pursuant thereto.
(8) In order for the nonworking training hours of apprentices and trainees to be counted in meeting goals, such
apprentices and trainees must be employed by the Contractor during the training period, and the Contractor
must have made a commitment to employ the apprentices and trainees at the completion of their training,
subject to the availability of employment opportunities. Trainees must be trained pursuant to training
programs approved by the U. S.Department of Labor,
(9) The Contractor shall take specific affirmative actions to ensure equal employment opportunity. The
evaluation of the Contractor's compliance with these specifications shall be based upon its effort to achieve
maximum results from its actions. The Contractor shall document these efforts Wily, and shall implement
affirmative action steps at least as extensively as the following:
(a) EnSLAre and maintain a working environment free of harassment, intimidation, and coercion at all sites,
and in all facilities at which the Contractor's employees are assigned to work. The Contractor, where
possible, will assign two or more women to each construction project. The Contractor shall specifically
ensure that all foremen, superintendents, and other on-site supervisory personnel are aware of and carry
out the Contractor's obligation to maintain such a working environment, with specific attention to
minority or female individuals working at such sites in such facilities.
(b) Establish and maintain a current list of minority and female recruitment sources, provide written
notification to minority and female recruitment sources and to community organizations when the
Contractor or its unions have employment opportunities available, and maintain a record of the
organization's responses.
(c) Maintain a current file of the names, addresses, and telephone numbers of each minority and female off-
the-street applicant and minority or female referral from a union, a recruitment source, or community
organization and of what action was taken with respect to each such individual. If Such individual was
sent to the union hiring hall for referral and was not referred back to the Contractor by the union, or if
referred, not employed by the Contractor, this shall be documented in the file with the reason therefore,
along with whatever additional actions the Contractor may have taken.
15-6
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/112011
(Construction Contracts)
(d) Provide immediate written notification to the Director when the union or unions with which the
Contractor has a collective bargaining agreement has not referred to the Contractor a minority person or
woman sent by the Contractor, or when the Contractor has other information that the union referral
process has impeded the Contractor's efforts to meet its obligations.
(e) Develop on-the-job training opportunities and/or participate in training programs for the areas which
expressly include minorities and women, including upgrading apprenticeship,trainee and other programs
relevant to the Contractor's employment needs, especially those programs funded or approved by the
Department of Labor, The Contractor shall provide notice of these programs to the sources compiled
under 7b above.
(f) Disseminate the Contractor's EEO policy by providing notice of the policy to unions and training
programs and requesting their cooperation in assisting the Contractor in meeting its EEO obligations; by
including it in any policy manual and collective bargaining agreement; by publicizing it in the company
newspaper, annual report, etc.; by specific review of the policy with all management personnel and with
all minority and female employees at least once a year; and by posting the company EEO policy on
bulletin boards accessible to all employees at each location where construction work is performed.
(g) Review, at least annually, the company's EEO policy and affirmative action obligations under these
specifications with all employees having any responsibility for hiring,assignment, layoff,termination,or
other employment decisions including specific review of these items with on-site supervisory personnel
such as S uperintende tits, General Foremen, etc., prior to the initiation of construction work at any job
site. A written record shall be made and maintained identifying the time and place of these meetings,
persons attending,subject matter discussed, and disposition of the subject matter.
(h) Disseminate the Conti-actor's EEO policy externally by including it in any advertising in the news media,
specifically including minority and female news media, and providing written notification to and
discussing the Contractor's EEO policy with other Contractors and Subcontractors with whom the
Contractor does or anticipates doing business.
(i) Direct its recruitment efforts, both oral and written,to minority, female and community organizations,to
schools with minority and female recruitment and training organizations serving the Contractor's
recruitment area and employment needs. Not later than one month prior to the date for the acceptance of
applications for apprenticeship or other training by any recruitment source, the Contractor shall send
written notification to organizations such as the above, describing the openings, screening procedures,
and tests to be used in the selection process.
Encourage present minority and female employees to recruit other minority persons and women and,
where reasonable, provide after school, summer and vacation employment to minority and female youth
both on the site and in other areas of a Contractor's work force.
(k) Validate all tests and other selection requirements where there is an obligation to do so under
41 CFR 60-3.
(1) Conduct, at least annually, an inventory and evaluation at least of all minority and female personnel for
promotional opportunities and encourage these employees to seek or to prepare for, through appropriate
training,etc.,such opportunities.
15-7
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/112011
(Construction Contracts)
(in)Ensure that seniority practices,job classifications, work assignments and other personnel practices, (to
not have a discriminatory effect by continually monitoring all personnel and employment related
activities to ensure that the EEO policy and the Contractor's obligations under these specifications are
being carried out,
(n) Ensure that all facilities and company activities are nonsegregated except that separate or single-user
toilet and necessary changing facilities shall be provided to assure privacy between the sexes.
(o) Document and maintain a record of all solicitations of offers for subcontracts from minority and female
construction contractors and suppliers, including circulation of solicitations to minority and female
contractor associations and other business associations.
(p) Conduct a review, at least annually, of all supervisors adherence to and performance under the
Contractor's EEO policies and affirmative action obligations.
(10) Contractors are encouraged to participate in voluntary associations which assist in fulfilling one or more of
their affirmative action obligations (9) (a) through (p). The efforts of a contractor association, joint
contractor-union, contractor-community, or other similar group of which the Contractor is a member and
participant, may be asserted as fulfilling any one or more of its obligations Linder(9)(a)through(p)of these
Specifications provided that the Contractor actively participates in the group, makes every effort to assure
that the group has a positive impact on the employment of minorities and women in the industry, ensures
that the concrete benefits of the program are reflected in the Contractor's minority and female workforce
participation,makes a good faith effort to meet its individual goals and timetables,and can provide access to
documentation which demonstrates the effectiveness of actions taken on behalf of the Contractor. The
obligation shall not be a defense for the Contractor's noncompliance.
(11) A single goal for minorities and separate single goal for women have been established. The Contractor,
however, is required to provide equal employment opportunity and to take affirmative action for all minority
groups, both male and female, and all wornen, both minority and non-minority. Consequently, the
Contractor may be in violation of the Executive Order if a particular group is employed in a substantially
disparate manner (for example, even though the Contractor has achieved its goals for women generally, the
Contractor may be in violation of the Executive Order if a specific minority group of women is under
utilized).
(12) The Contractor shall not use the goals and timetables or affirmative action standards to discriminate against
any person because of race,color,religion, sex,or national origin.
(13) The Contractor shall not enter into any Subcontract with any person or firm debarred from Government
contracts pursuant to Executive Order 11246.
(14) The Contractor shall carry out sections and penalties for violation of these specifications and of the Equal
Opportunity Clause, including suspension, termination and cancellation of existing subcontracts as may be
imposed or ordered pursuant to Executive Order 11246, as amended, and its implementing regulations, by
the Office of Federal Contract Compliance Programs. Any Contractor who fails to carry out such sanctions
and penalties shall be in violation of these specifications and Executive Order 11246, as amended.
15-8
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 1 011120 1 1
(Construction Contracts)
(15) The Contractor, in fulfilling its obligations tinder these specifications, shall implement specific affirmative
action steps,at least as extensively as those standards prescribed in paragraph 7 of these specifications,so as
to achieve maximum results from its effort to ensure equal employment Opportunity. if the Contractor fails
to comply with the requirement of the Executive Order, the implementing regulations, or these
specifications,the Director shall proceed in accordance with 41 CFR 60-4.8.
(16) The contractor shall designate a responsible official to monitor all employment related activity to ensure that
the company EEO policy is being carried out, to submit reports relating to the provisions hereof as may be
required by the Government and to keep records. Records shall at least include for each employee, the
name, address, telephone numbers, construction trade, union affiliation, if any, employee identification
number where assigned, social security number, race, sex, status (e.g., mechanic, apprentice trainee, helper,
or taborer), dates of changes in status, hours worked per week in the indicated trade, rate of pay, and
location at which the work was performed. Records shall be maintained in an easily understandable and
retrievable form; however, to the degree that existing records satisfy this requirement, contractors shall not
be required to maintain separate records.
(17) Nothing herein provided shall be construed as a limitation upon the application of other laws which
C,
establish different standards of compliance and upon the application of requirements for the hiring of local
or other area residents (e.g., those under the Public Works Employment Act of 1977 and the Community
Development Block Grant Program).
C. Qqr6ficaflon of_M21).-S mie
_mLo -d m
By the submission of this bid, the bidder, offeror, applicant or subcontractor certifies that he/she does not
maintain or provide for his/her employees any segregated facility at any of his/her establishments,and that he/she
does not permit employees to perform their services at any location, under his/her control, where segregated
facilities are maintained. He/She certifies further that lie/she will not maintain or provide for employees any
segregated facilities at any of his/her establishments, and he/she will not permit employees to perform their
services at any location under his/her control where segregated facilities are maintained. The bidder, offeror,
applicant or subcontractor agrees that a breach of this certification is violation of the Equal Opportunity Clause
of this contract. As used in this certification, the term "segregated facilities" means any waiting rooms, work
eating areas, time clocks, locker rooms, and other storage or dressing areas, transportation and housing facilities
provided for employees which are in fact segregated on the basis of race, color, religion, or otherwise. He/She
further agrees that (except where he/she has obtained identical certifications from proposed subcontractors prior
to the award of subcontractors have submitted identical certifications for specific,time periods).
D. Civil Riahts Act of 1964
Under Title VI of the Civil Rights Act of 1964, no person shall, on the grounds of race, color, or national origin,
be excluded from participation in, be denied the benefits of, or be subjected to discrimination under any program
or activity receiving Federal financial assistance.
E. section 109 of file I-Iousing and Coninitylily Develovirient Act of 1974
No person in the United States shall on the grounds of race, color,national original,or sex be
excluded from participation in, be denied the benefits of, or be subjected to discrimination Linder any program or
activity funded in whole or in part with funds made available tinder this title.
15-9
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 1011/2011
(Construction Contracts)
F. ".SectioriJ"Co 11ii n 11 tile Provision 01'Trainbg,,,f-'
in a cc i [1tp1qY!!1gi1t ind Fikusi ss )pp�(Litunitics
(1) The work to be performed under this contract is Subject to the requirements of section 3 of the Housing and
Urban Development Act of 1968,as amended, 12 U.S.C. 1701 u(section 3).The purpose of section 3) is to
ensure that employment and other economic opportunities generated by HUD assistance or HUD-assisted
projects covered by section 3;shall,to the greatest extent feasible,be directed to low-and very low-income
persons,particularly persons who are recipients of HUD assistance for housing.
(2) The parties to this contract agree to comply with HUD's regulations in 24 CFR Part 135,which implement
section 3. As evidenced by their execution of this contract,the parties to this contract certify that they are
under no contractual or other impediment that Would prevent them from complying with the Part 135
regulations.
(3) The contractor agrees to send to each labor organization or representative of workers with which the
contractor has a collective bargaining agreement or other understanding, if any, a notice advising the labor
organization or workers'representative of the contractor's commitments Linder this section 3 clause,and will
post copies of the notice in conspicuous places at the work site where both employees and applicants for
training and employment positions can see the notice. The notice shall describe the section 3 preference,shall
set forth minimum number and job titles subject to hire, availability of apprenticeship and training positions,
the qualifications for each; and the name and location of the person(s)taking applications for each of the
positions; and the anticipated date the work shall begin.
(4) The contractor agrees to include this section 3 clause in every subcontract subject to compliance with
regulations in 24 CFR part 135,and agrees to take appropriate action,as provided in an applicable provision
of the subcontract or in this section 3 clause, upon a finding that the subcontractor is in violation of the
regulations in 24 CFR part 135.The contractor will not subcontract with any subcontractor where the
contractor has notice or knowledge that the subcontractor has been found in violation of the regulations in 24
CFR part 135.
(5) The contractor will certify that any vacant employment positions, including training positions,that are filled
(I)after the contractor is selected but before the contract is executed,and(2)with persons other than those to
whom the regulations of 214 CFR part 135 require employment opportunities to be directed,were not filled to
circumvent the contractor's obligations under 24 CFR part 135.
(6) Noncompliance with HUD's regulations in 24 CFR part 135 may result in sanctions,termination of this
contract for default,and debarment or Suspension from future HUD assisted contracts.
(7) With respect to work performed in connection with section 3 covered Indian housing assistance,section 7(b)
of the Indian Self-Determinationand Education Assistance Act(25 U.S.C.450e)also applies to the work to
be performed Linder this contract. Section 7(b)requires that to the greatest extent feasible(i)preference and
opportunities for training and employment shall be given to Indians,and(ii)preference in the award of
contracts and subcontracts shall be given to Indian organizations and Indian-owned Economic Enterprises.
Parties to this contract that are subject to the provisions of section 3 and section 7(b)agree to comply with
section 3 to the maximum extent feasible,but not in derogation of compliance with section 7(b).
15-10
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/1/2011
(Construction Contracts)
G. Section 503 Handicapped(Contracts$2,500 or Over)
(1) The Contractor will not discriminate against any employee or applicant for employment because of physical
or mental handicap in regard to any position for which the employee or applicant for employment is
qualified. The Contractor agrees to take affirmative action to employ, advance in employment and otherwise
treat qualified handicapped individuals without discrimination based upon their physical or mental handicap
in all employment practices such as the following: employment,upgrading, demotion or transfer,recruitment,
advertising, layoff or termination, rates of pay or other forms of compensation, and selection for training,
including apprenticeship.
(2) The Contractor agrees to comply with the rules, regulations and relevant orders of the Secretary of Labor
issued pursuant to the Act.
(3) In the event of the Contractor's noncompliance with the requirements of this clause, actions for
noncompliance may be taken in accordance with the rules,regulations,and relevant orders of the Secretary of
Labor issued pursuant to the Act.
(4) The Contractor agrees to post in conspicuous places, available to employees and applicants for employment,
notices in a form to be prescribed by the Director, provided by or through the contracting officer. Such
notices shall state the Contractor's obligation under the law to take affirmative action to employ and advance
in employment qualified handicapped employees and applicants for employment, and the rights of applicants
and employees.
(5) The Contractor will notify each labor union or representative of workers with which it has a collective
bargaining agreement or their contract understanding, that the contractor is bound by the terms of Section
503 of the Rehabilitation Act of 1973, and is committed to take affirmative action to employ and advance in
employment physically and mentally handicapped individuals.
(6) The Contractor will include the provisions of this clause in every subcontract or purchase order of$2,500 or
more unless exempted by rule,-,, regulations, or orders of the Secretary issued pursuant to Section 503 of the
Act, so that such provisions will be binding upon each subcontractor or vendor. The Contractor will take
such action with respect to any subcontract or purchase order as the Director of the Office of Federal
Contract Compliance Programs may direct to enforce such provisions,including action for noncompliance.
H. Age Discrimination Act of 1975
No person in the United States shall,on the basis of age be excluded from participation in,be denied the benefits
of,or be subjected to discrimination under, any program,or activity receiving Federal Financial assistance.
8. CONFLICT OF INTEREST OF OFFIC)ERS' OR EMPLOYEES OF THE LOCAL JURISDICTION,
MEMBERS OF THE LOCAL GOVERNING BODY,OR OTHER PUBLIC OFFICIALS
No officer or employee of the local jurisdiction or its designees or agents, no member of the governing body, and no
other public official of the locality who exercises any function or responsibility with respect to this contract, during
his/her tenure or for one year thereafter, shall have any interest,direct or indirect, in any contract or subcontract, or
the proceeds thereof, for work to be performed. Further, the Contractor shall cause to be incorporated in All
subcontracts the language set forth in this paragraph prohibiting conflict of interest.
15-[I
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/1/2011
(Construction Contracts)
9. UTILIZATION OF MINORITY AND WOMEN FIRMS(NIAVBE)
The contractor shall take all necessary affirmative steps to assure that M/WBE firms are utilized when possible as
suppliers and/or subcontractors, as applicable. Prior* to contract award, the contractor shall document efforts to
utilize M/WBE firms, including identifying what firms were solicited as suppliers and/or subcontractors, as
applicable. Information regarding certified M/WBE firms can be obtained from:
➢ Florida Department of Management Services,Office of Supplier Diversity,
➢ Florida Department of Transportation (construction services, particularly highway),
),I Minority Business Development Center in most major cities,and
Local government M/WBE programs in many large counties and cities.
A firm recognized as all M/WBE by any of the above agencies is acceptable for the CDBG program.
10. FEDERAL LABOR STANDARDS PROVISIONS
(Davis-Bacon Act,Copeland Act,and Contract Works Hours& Safety Standards Act) The Project to which the
construction work covered by this contract pertains is being assisted by the United States of America and the
In
following Federal Labor Standards Provisions are included in this Contract pursuant to the provisions applicable to
such Federal assistance_
A. (I) (a) Minimum Wages. All laborers and mechanics employed or working upon the site of the work (Or Linder
the United States Housing Act of 1937 or under the Housing Act of 1949 in the construction or
development of the project), will be paid unconditionally and not less often than once a week, and
without subsequent deduction or rebate on any account (except Such payroll deductions as are permitted
by regulations issued by the Secretary of Labor Linder the Copeland Act(29 CFR Part 3), the full amount
of wages and bona fide fringe benefits (or cash equivalents thereof.) due at time of payment computed at
rates not less than those contained in the wage determination of the Secretary of Labor which is attached
hereto and made a part hereof, regardless of any contractual relationship which may be alleged to exist
between the contractor and such laborers and mechanics. Contributions made or costs reasonably
anticipated for bona fide fringe benefits under Section I(b)(2) of the Davis-Bacon Act on behalf of
laborers or mechanics are considered wages paid to such laborers or mechanics, subject to the provisions
of 29 CFR 5.5(a)(1)(iv); also,regular contributions made or costs incurred for more than a weekly period
(but not less often than quarterly) under plans, funds, or programs, which cover the particular weekly
period,are deemed to be constructively made or incurred during such weekly period.
Such laborers and mechanics shall be paid the appropriate wage rate and fringe benefits on the wage
determination for the classification of work actually performed, without regard to skill, except as
provided in 29 CFR Part 5.5(a)(4). Laborers or mechanics performing work in more than one
classification may be compensated at the rate specified for each classification for the time actually
worked therein; provided, that the employer's payroll records accurately set forth the time spent in each
classification in which work is performed. The wage determination (including any additional
classification and wage rates conformed under 29 CFR Part S.5(a)(I)(ii) and the Davis-Bacon poster
(WH-1321)shall be posted at all times by the contractor-and its subcontractors at the site of the work in a
prominent and accessible place where it can be easily seen by the workers.
(b) (i) Any class of laborers or mechanics which is not listed in the wage determination and which is to be
employed under the contract shall be classified in conformance with the wage determination. HUD
shall approve an additional classification and wage rate and fringe benefits; therefore, only when the
following criteria have been met:
15-12
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/1/2011
(Construction Contracts)
(1) The work to be performed by the classification requested is not performed by a classification in
the wage determination; and
(2) The classification is utilized in the area by the construction industry; and
(3) The proposed wage rate, including any bona fide fringe benefits, bears a reasonable relationship
to the wage rates contained in the wage determination.
(ii) If the contractor and the laborers and mechanics to be employed in the classification(if known), or
their representatives, and HUD or its designee agree on the classification and wage rate (including
the amount designated for fringe benefits where appropriate), a report of the action taken shall be
sent by HUD or its designee to the Administrator of the Wage and Hour Division, employment
Standards Administration, U. S. Department of Labor, Washington, D. C. 20210. The
Administrator, or an authorized representative, will approve, modify, or disapprove every additional
classification action within 30 days of receipt and so advise HUD or its designee or will notify [IUD
or its designee within the 30-day period that additional time is necessary. (Approved by the Office
of Management and Budget under OMB control number 1215-0140.)
(iii) In the event that the Contractor, the laborers or mechanics to be employed in the Classification or
their representatives, and HUD or its designee do not agree on the proposed classification and wage
rate (including the amount designed -for fringe benefits, where appropriate), HUD or its designee
shall refer the questions, including the views of all interested parties and the recommendation of
HUD or its designee, to the Administrator for determination. The Administrator, or an authorized
representative, will issue a determination within 30 days of receipt and so advise HUD or its
designee or will notify HUD or its designee within the 30-day period that the additional time is
necessary. (Approved by the Office of Management and Budget under OMB Control Number 1215-
0140.)
(iv) The wage rate (including fringe benefits where appropriate) determined pursuant to subparagraphs
(b)(ii) or (iii) of this paragraph, shall be paid to all workers performing work in the classification
under this contract from the first day on which work is performed in the classification.
(c) Whenever the minimum wage rate prescribed in the contract for a class of laborers or mechanics includes
a fringe benefit which is not expressed as an hourly rate, the contractor shall either pay the benefit as
stated in the wage determination or shall pay another bona fide fringe benefit or an hourly cash
equivalent thereof.
(d) If the contractor does not make payments to a trustee or other third person, the contractor may consider
as part of the wages of any laborer or mechanic the amount of any costs reasonably anticipated in
providing bona fide fringe benefits under a plan or program. Provided, that the Secretary of Labor has
found, upon the written request of the contractor, that the applicable standards of the Davis-Bacon Act
have been met. The Secretary of Labor may require the contractor to set aside in a separate account
assets for the meeting of obligations under the plan or program. (Approved by the Office of Management
and Budget under OMB Control Number 1215-0140.)
15-13
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 101112011
(Construction Contracts)
(2) Withholding. HUD or its designee shall upon its own action or upon written request of an authorized
representative of the Department of Labor withhold or cause to be withheld from the contractor under this
contract or any other federal contract with the same prime contractor, or any other Federally-assisted contract
subject to Davis-Bacon prevailing wage requirements,which is held by the same prime contractor so much of the
accrued payments or advances as may be considered necessary to pay laborers and mechanics, including
apprentices, trainees and helpers employed by the contractor or any subcontractor the -full amount of wages
required by the contract. In the event of failure to pay any laborer or mechanic, including any apprentice, trainee
or helper, employed or working on the site of the work(or Linder the United States Housing Act of 1937 or under
the Housing Act of 1949 in the construction or development of the project), all or part of the wages required by
the contract, HUD, or its designee may, after written notice to the contractor, sponsor, applicant, or owners,take
such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds
until such violations have ceased. HUD or its designee may, after written notice to the contractor,disburse such
amounts withheld for and on account of the contractor or subcontractor to the respective employees to whom they
are due. The Comptroller General shall make such disbursements in the case of direct Davis-Bacon Act
contracts.
(3) (a) Payrolls and Basic Records. Payrolls and basic records relating thereto shall be maintained by the contractor
during the course of the work preserved for a period of three years thereafter for all laborers and mechanics
working at the site of the work(or under the United States Housing Act of 1937, or under the Housing Act of
1949, in the construction or development of the project). Such records shall contain the name, address, and
social security number of each such worker, his or her correct classification, hourly rates of wages paid
(including rates of contributions or costs anticipated for bona fide fringe benefits or cash equivalents thereof
of the types described in Section l(b)(2)(B) of the Davis-Bacon Act), daily and weekly number of hours
worked, deductions made and actual wages paid. Whenever the Secretary of Labor has found under 29 CFR
5.5(a)(1)(iv) that the wages of any laborer or mechanic include the amount of any costs reasonably
anticipated in providing benefits Linder a plan or program described in Section I(b)(2)(B)of the Davis-Bacon
Act, the contractor shall maintain records which show that the commitment to provide such benefits is
enforceable, that the plan or program is financially responsible, and that the plan or program has been
communicated in writing to the laborers or mechanics affected, and records which show the costs anticipated
or the actual cost incurred in providing such benefits. Contractors employing apprentices or trainees under
approved programs shall maintain written evidence of the registration of apprenticeship programs and
certification of trainee programs, the registration of the apprentices and trainees, and the ratios and wage
rates prescribed in the applicable programs. (Approved by the Office of Management and Budget under
OMB Control Nurnbers 1215-0140 and 1215-0017).
(b) (i) The contractor shall submit weekly for each week in which any contract work is performed a copy of all
payrolls to HUD or its designee if the agency is a party to the contract, but if the agency is not such a
party, the contractor will submit the payrolls to the applicant, sponsor, or owners, as the case may be, for
transmission to HUD or its designee. The payrolls submitted shall set out accurately and completely all
of the information required to be maintained under 29 CFR Part 5.5(a)(3)(l). This information may be
submitted in any form desired. Optional Form WH-347 is available for this purpose and may be
purchased from the Superintendent of Documents (Federal Stock Number 029-005-00014-1), U. S.
Government Printing Office, Washington, DC 20402, The prime contractor is responsible for the
submission of copies of payrolls by all subcontractors. (Approved by the Office of Management and
Budget under OMB Control Number 1215-0149).
(ii) Each payroll submitted shall be accompanied by a "Statement of Compliance", signed by the contractor
or subcontractor or his or her agent who pays or supervises the payment of the persons employed under
the contract and shall certify the following:
15-14
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/1/2011
(Construction Contracts)
(1) That the payroll for the payroll period contains the information required to be maintained under 29
CFR Part 5.5 (a)(3)(1)and that such information is correct and complete;
(2) That each laborer or mechanic (including each helper, apprentice, and trainee) employed on the
contract during the payroll period has been paid the full weekly wages earned, without rebate, either
directly or indirectly, and that no deductions have been made either directly or indirectly from the
full wages earned,other than permissible deductions as set forth in 29 CFR Part 3;
(3) That each laborer or mechanic has been paid not less than the applicable wage rates and fringe
benefits or cash equivalents for the classification of work performed, as specified in the applicable
wage determination incorporated into the contract.
(iii) The weekly submission of a properly executed certification set forth on the reverse side of Option Form
WH-347 shall satisfy the requirement for submission of the "Statement of Compliance" required by
paragraph A(3)(b)(ii)of this section.
(iv) The falsification of any of the above certifications may Subject the contractor or subcontractor to civil or
criminal prosecution under Section 1001 of Title 18 and Section 231 of Title 31 of the United States
Code.
(c) The contractor or Subcontractor shall make the records required under paragraph A(3)(a) of this section
available for inspection,copying,or transcription by authorized representatives of MUD or its designee or the
Department of Labor, and shall permit such representatives to interview employees during working hours on
the job. If the contractor or subcontractor fails to submit the required records or to make them available,
HUD or its designee may, after written notice to the contractor, sponsor, applicant,or owner,take such action
as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds.
Furthermore, failure to submit the required records upon request to rnake such records available may be
grounds for debarment action pursuant to 29 CFR Part 5.12.
(4) (a) Apprentices and't'rainces.
(i) Apprentices. Apprentices will be permitted to work at less than the predetermined rate for the work they
performed when they are employed pursuant to and individually registered in a bona fide apprenticeship
program registered with the U. S. Department of Labor, Employment and Training Administration,
Bureau of Apprenticeship and Training, or with a State Apprenticeship Agency recognized by the
Bureau, or if a person is employed in his or her first 90 days of probationary employment as all
apprentice in such an apprenticeship program, who is not individually registered in the program,but who
has been certified by the Bureau of Apprenticeship and Training or a State Apprenticeship Agency
(where appropriate) to be eligible for probationary employment as an apprentice. The allowable ratio of
apprentices to journeymen on the job site in any craft classification shall not be greater than the ratio
permitted to the contractor as to the entire work force under the registered program. Any worker listed
on a payroll at an apprentice wage rate, who is not registered or otherwise employed as stated above,
shall be paid not less than the applicable wage rate on the wage determination for the classification of
work actually performed. In addition, any apprentice performing work on the job site in excess of the
ratio permitted under the registered program, shall be paid not less than the applicable wage rate on the
wage determination for the work actually performed. Where a contractor is performing construction on a
project in a locality other than that in which its program is registered, the ratios and wage rates
(expressed in percentages of the journeyman's hourly rate) specified in the contractor's or
subcontractor's registered program shall be observed. Every apprentice must be paid at not less than the
rate specified in the registered program for the apprentice's level of progress, expressed as a percentage
of the journeymen hourly rate specified in the applicable wage determination. Apprentices shall be paid
fringe benefits in accordance with the provisions of the apprenticeship program. If the apprenticeship
15-15
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 1 01112 01 1
(Construction Contracts)
program does not specify fringe benefits, apprentices must be paid the full amount of fringe benefits
listed on the wage determination for the applicable classification. If the Administrator determines that a
different practice prevails for the applicable apprentice classification, fringes shall be paid in accordance
with the determination. In the event the Bureau, of Apprenticeship and Training, or a State
Apprenticeship Agency recognized by the Bureau,withdraws approval of an apprenticeship program, the
contractor will no longer be permitted to utilize apprentices at less than the applicable predetermined rate
for the work performed until an acceptable program is approved.
(ii) Trainees. Except as provided in 29 CFR 5,16, trainees will not be permitted to work at less than the
predetermined rate for the work performed unless they are employed pursuant to and individually
registered in a program which has received prior approval, evidenced by formal certification by the U. S.
Department of Labor, Employment and Training Administration. The ratio of trainees to journeymen on
the job site shall not be greater than permitted under the plan approved by the Employment and Training
Administration, Every trainee must be paid at not less than the rate specified in the approved program
for the trainee's level of progress, expressed as a percentage of the journeyman hourly rate specified in
the applicable wage determination. Trainees shall be paid fringe benefits in accordance with the
provisions of the trainee program. If the trainee program does not mention fringe benefits, trainees shall
be paid the full amount of fringe benefits listed on the wage determination unless the Administrator of
the Wage and Hour Division determines that there is an apprenticeship program associated with the
corresponding journeyman wage rate on the wage determination which provides for less than full fringe
benefits for apprentices. Any employee listed on the payroll at a trainee rate who is not registered and
participating in a training plan approved by the Employment and Training Administration shall be paid
not less than the applicable wage rate on the wage determination for the work actually performed. In
addition, any trainee performing work on the job site in excess of the ratio permitted under the registered
program shall be paid not less than the applicable wage rate on the wage determination for the work
actually performed. In the event the Employment and Training Administration withdraws approval of
training program the contract will no longer be permitted to utilize trainees at less than the applicable
predetermined rate for the work perfonned until an acceptable program is approved.
(iii) Equal Employment Opportunity. The utilization of apprentices, trainees and journeymen under this part
shall be in conformity with the equal employment opportunity requirements of Executive Order 11246,as
amended,and 29 CFR Pail 30,
(5) Compliance with Copeland Act Requirements. The contractor shall comply with the requirements of
29 CFR Part 3 which are incorporated by reference in this contract.
(6) Subcontracts. The contractor or subcontractor will insert in any subcontracts the clauses contained in
29 CFR 5.5(a)(1)through(10)and such other clauses as HUD or its designee may by appropriate instructions
require, and also a clause requiring the subcontractors to include these CIMSCS in any lower tier subcontracts.
The prime contract shall be responsible for the compliance by any Subcontractor or lower tier subcontractor
with all the contract clauses in 29 CFR Part 5.5.
Contract Termination, Debarment. A breach of the contract clauses in 29 CFR 5.5 may be grounds for
termination of the contr-actancl for debarment as a contractor and a subcontractor as provided in
29 CFR 5.12.
(8) Compliance with Davis-Bacon and Related_Act Requirements. All rulings and interpretations of the Davis-
Bacon and Related Acts contained in 29 CFR Parts 1, 3 and 5 are herein incorporated by referenced in this
contract.
15-16
Department of Economic,Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/112011
(Construction Contracts)
(9) Disputes Concerning Labor Standards. Disputes arising out of the labor standards provisions of this contract
shall not be subject to the genera[ disputes clause of this contract. Such disputes shall be resolved in
accordance with the procedures of the Department of Labor set forth in 29 CFR Parts 5, 6 and 7. Disputes
within the meaning of this clause include disputes between the contractor (or any of its subcontractors) and
I IUD or its designee,the U. S. Department of Labor, or the employees or their representatives.
(10) (a) Certification of Eli gihiii1y. By entering into this contract,the contractor certifies that neither it(nor he or
she)nor any person or firm who has an interest in the contractor's firm is a person or firm ineligible to be
awarded Government contracts by virtue of Section 3(a)of the Davis-Bacon Act or 29 CFR 5.12(a)(1)or
to be awarded I IUD contracts or participate in HUD programs pursuant to 24 CFR Part 24.
(b) No part of this contract shall be Subcontracted to any person or firm ineligible for award of a Government
contract by virtue of Section 3(a) of the Davis-Bacon Act or 29 CFR 5.12(a)(1) or to be awarded HUD
contracts or participate in HUD programs pursuant to 24 CFR Part 24.
(c) The penalty for making false statements is prescribed in the U. S. Criminal Code, 18 U. S. C. 1001.
Additionally, U. S. Criminal Code, Section 1010, Title 18, U. S. C., "Federal Housing Administration
transactions",provides in part"Whoever, for the purpose of... influencing in any way the action of such
Administration... makes, Litters or publishes any statement, knowing the same to be false ... shall be fined
not more than$5,000 or imprisoned not more than two years,or both."
(11) Complaints, Proceedings,..or Testimony by Enial2ygcs. No taborer or mechanic to whom the wage,salary, or
other labor standards provisions of this contract are applicable shall be discharged or in any other manner
discriminated against by the contractor or any subcontractor because such employee has filed any complaint
or instituted or caused to be instituted any proceeding or has testified or is about to testify in any proceeding
under or relating to the labor standards applicable Linder this contract to his employer.
B. Contract Work Hours and Safety St
andards Act. As used in the paragraph,the terms"laborers"and"mechanics"
include watchmen and guards.
(1) Overtime requirements. No contractor or subcontractor contracting for any part of the contract work which
may require or involve the employment of laborers or mechanics shall require or permit any such laborer or
mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in
such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-
half times the basic rate of pay for all hours worked in excess of forty hours in such workweek.
(2) Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth
in subparagraph (1) of this paragraph, the contractor and any subcontractor responsible therefore shall be
liable for the unpaid wages. In addition, such contractor and subcontractor shall be liable to the United States
(in the case of work done under contract for the District of Columbia or a territory,to such District or to Such
territory), for liquidated damages. Such liquidated damages shall be computed with respect to each
individual taborer or mechanic, including watchmen and guards, employed in violation of the clause set forth
in subparagraph(1) of this paragraph, in the sum of$10 for each calendar day on which such individual was
required or permitted to work in excess of the standard workweek of forty hours without payment of the
overtime wages required by the clause set forth in subparagraph(1)of this paragraph.
15-17
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/1/2011
(Construction Contracts)
(3) Withholding for unpaid wages and liquidated damages. HUD or its designee shall upon its own action or
upon written request of an authorized representative of the Department of Labor withhold or cause to be
withheld, from any moneys payable on account of work performed by the contractor or subcontractor under
any such contract or any other Federal contract with the same prime contract, or any other Federally-assisted
contract subject to the Contract Work Hours and Safety Standards Act , which is held by the same prime
contractor Such sums as may be determined to be necessary to satisfy any liabilities of such contractor or
subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in subparagraph
(2)of this paragraph.
(4) Subcontracts. The contractor Or subcontractor shall insert in any subcontracts the clauses set forth in
subparagraph(1)through (4) of this paragraph and also a clause requiring the subcontractors to include these
clauses in any lower tier subcontracts. The prime contractor shall be responsible for compliance by any
subcontractor or lower tier subcontractor with the clauses set forth in subparagraphs (1) through (4) of this
paragraph.
C. H.e.a...1-th-and Safety
...,........ -
(1) No laborer or mechanic shall be required to work in surroundings or Linder working conditions which are
unsanitary, hazardous, or dangerous to his health and safety as determined under construction safety and
health standards promulgated by the Secretary of Labor by regulation.
(2) The contractor shall comply with all regulations issued by the Secretary of Labor pursuant to Title 29 Part
1926 (formerly part 1518) and failure to comply may result in imposition of sanctions pursuant to the
Contract Work flours and Safety Standards Act(Public Law 91-54.83 State 96).
(3) The contractor shall include the provisions of this Article in every subcontract so that such provisions will be
binding oil each subcontractor. The contractor shall take such action with respect to any subcontract as the
Secretary of Housing and Urban Development or the Secretary of Labor shall direct as a means of enforcing
such provisions.
If. GUI DANC E'll'O CONTRACTOR FOR COMMANCE WITH 1,A11OR'STA1" DARMS PROVISIONS
A. Contracts with Two Wage Decisions
If the contract includes two wage decisions, the contractor, and each subcontractor who works on the site, must
submit either two separate payrolls (one for each wage decision) or one payroll which identifies each worker
twice and the hours worked Linder each wage decision. One single payroll, reflecting each worker once, may be
submitted provided the Contractor uses the higher rate in the wage decisions for each identical job classification.
However, where ajob classification is not listed in a wage decision and is needed for that portion of the work,the
classification must be added to the wage decision. A worker may not be paid at the rate for a classification using
the hourly rate for that same classification in another wage decision. After the additional classification is
approved,the contractor may pay the higher of the two rates and submit one payroll, if desired.
B. Complying with Minimum Hourly Amounts
(1) The minimum hourly amount due to a worker in each classification is the total of the amounts in the"Rates"
and"Fringe Benefits"(if any)columns of the applicable wage decision.
(2) The contractor may satisfy this minimum hourly amount by any combination of cash and bona fide fringe
benefits, regardless of the individual amounts reflected in the"Rates"and"Fringe Benefits"columns.
15-18
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 101112011
(Construction Contracts)
(3) A contractor payment for a worker which is required by law is not a fringe benefit in meeting the minimum
hourly amount due under the applicable wage decision. For example, contractor payments for FICA or
unemployment insurance are not a fringe benefit-, however, contractor payments for health insurance or
retirement are a fringe benefit. Generally, a fringe benefit is bona fide if(a) it is available to most workers
and(b)involves payments to a third party.
(4) The hourly value of the fringe benefit is calculated by dividing the contractor's annual cost (excluding any
amount contributed by the worker) for the fringe benefit by 2080. Therefore, for workers with overtime, an
additional payment may be required to meet the rninimum hourly wages since generally fringe benefits have
no Value for any time worked over 40 hours weekly. (if a worker is paid more than the minirrium, rates
required by the wage decision, this should not be a problem. As long as the total wages received by a worker
for straight time equals the hours worked times the minimum hourly rate in the wage decision, the
requirement of the Davis-Bacon and Related Acts has been satisfied.)
C. Overtime
For any project work over 40 hours weekly, a worker generally must be paid 150%of the actual hourly cash rate
received, not the minimum required by the wage decision. (The Davis-Bacon and related acts only establish
minimum rates and does not address overtime; the Contract Work Hours Act contains the overtime requirement
and uses "basic rate of pay" as the base for calculation, not the rninimurn rates established by the Davis-Bacon
and related acts.)
D. Deductions
Workers who have deductions, not required by law, from their pay must authorize these deductions in writing.
The authorization must identify the purpose of each deduction and the amount, which may be a specific dollar
arriount or a percentage. A copy of the authorization must be submitted with the first payroll containing the
deduction.If deducted amounts increase,another authorization must be submitted. If deducted amounts decrease,
no revision to the original authorization is needed. Court-ordered deductions, such as child support, may be
identified by the responsible payroll person in a separate document. This document should identify the worker,
the arriount deducted and the purpose. A copy of the court order should be submitted.
E. Classifications Not Included in the Wage Decision
If a classification not in the wage decision is required, please advise the owner's representative in writing and
identify the job classification(s) required. In some instances, the State agency may allow the use of a similar
classification in the wage decision.
Otherwise, the contractor and affected workers must agree on a minimum rate, which cannot be lower than the
lowest rate for any trade in the wage decision. Laborers(including any subcategory of the laborer classification)
and truck drivers are not considered a trade for this purpose. If the classification involves a power equipment
operator, the minimum cannot be lower than the lowest rate for any power equipment operator in the wage
decision. The owner will provide forms to document agreement on the minimum rate by the affected workers
and contractor.
The U.S. Department of Labor(USDOL) must approve the proposed classification and rate. The contractor may
pay the proposed rate until the USDOL makes a determination. Should the USDOL require a higher rate, the
contractor must make wage restitution to the affected worker(s) for all hours worked under the proposed rate.
15-19
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/1/2011
(Construction Contracts)
F. Supervisory Personnel
Foremen and other supervisory personnel who spend at least 80% of their time supervising workers are not
covered by the Davis-Bacon and Related Acts. Therefore, a wage decision will not include such supervisory
classifications and their wages are not subject to any minimums tinder the Davis-Bacon and Related Act or
overtime payments Under the Contract Work Hours and Safety Standards Act. However, foremen and other
supervisory personnel who spend less than 80% of their time engaged in supervisory activities are considered
workers/mechanics for the time spent engaged in manual labor and must be paid at least the minimum in the
wage decision for the appropriate classification(s)based on the work performed.
G. Sole ProprietorshilLs/Independent Contractors/Leased Workers
The nature of the relationship between a prime contractor and a worker does not affect the requirement to comply
with the labor standards provisions of this contract. The applicability of the labor standards provisions is based
on the nature of the work performed.
If the work performed is primarily manual in nature,the worker is subject to the labor standards provisions in this
contract. For example, if John Smith is the owner of ABC Plumbing and performs all plumbing work himself,
then Mr. Smith is subject to the labor standards provisions, including minimum wages and overtime. His status
as"owner" is irrelevant for labor standards purposes.
If a worker meets the IRS standards for being an independent contractor,and is employed as such, this means that
the worker must submit a separate payroll as a subcontractor rather than be included on some other payroll. The
worker is still subject to the labor standards provisions in this contract, including minimum wages and overtime.
If a contractor or subcontractor leases its workers, they are subject to the labor standards provisions in this
contract, including minimum wages and overtime. The leasing firm must submit payrolls and these payrolls must
reflect information required to determine compliance with the labor standards provisions of this contract,
including a classification for each worker based on the nature of the work performed, number of regular hours
worked, and number of overtime hours worked.
H. A imrentices/Helpers
A worker may be classified as an apprentice only if participating in a federal or state program.
Documentation of participation must be submitted. Generally, the apprentice program specifies that the
apprentice will be compensated at a percentage of the journeyman rate. For Davis-Bacon Act purposes, the
hourly rate cannot be lower than, the percentage of the hourly rate for the classification in the applicable wage
decision.
If the worker does not participate in a federal or state apprentice program, then the worker must be classified
according to duties performed. This procedure may require classification in the"trade"depending on tools used,
or as a laborer if specialized tools of the trade are not used. The contractor may want to consult with the Wage
and Hour Division of the U.S. Department of Labor located in most large cities regarding the appropriate
classification.
Presently,no worker may be classified as a"helper". As with apprentices not participating in a formal apprentice
program, the worker must be classified according to duties performed and tools used.
15-20
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 10/112011
(Construction Contracts)
Appendix
Minority Participation Goals
These are the goals, by county,for meeting the minority participation portion of Section 7-B(2)(b)of the CDBG
Supplemental Conditions. These are contractor workforce goals, not goals for subcontracting to minority and women
firms. Solicitation of minority and women firms as subcontractors is a separate federal requirement which the contractor
must document compliance with.
Tampa-St. Petersburg Area Percerttae
Hillsborough,Pinellas,Pasco I79
Charlotte,Citrus,Collier,DeSoto, 17.1
Hardee,Hernando,&Highlands (all seven)
Lee 15.3
Manatee 15.9
Polk 18,0
Sarasota 10.5
Tallahassee Area
Leon, Wakulla 24.3
Calhoun,Franklin,Gadsden,Jackson, 29.5
Jefferson,Liberty,Madison,&Taylor (all eight)
Pensacola-Panama City Area
Bay 14.1
Escambia, Santa Rosa 18.3
Gulf,Holmes,0kaloosa, 15.4
Walton,&Washington (al I five)
Jacksonville Area
Alachua 20.6
Baker,Clay,Duval, 21.8
Nassau,&St.Johns (all five)
Bradford,Columbia, Dixie,Gilchrist 22.2
Hamilton,Lafayette,Levy,Marion, (all H)
Putnam, Suwannee,&Union
15-21
Department of Economic Opportunity—Community Development Block Grant Program
CDBG Supplemental Conditions 101112011
(Construction Contracts)
Orlando-Daytona Beach Area Percentage
Volusia 15.7
Brevard 10.7
Orange,Osceola,Seminole 15.5
Flagler,Lake, Sumter 14.9
Miami-Fort Lauderdale Area
Dade 39.5
Broward 15.5
Palm Beach 22.4
Glades,Hendry,Indian River 30.4
Martin,Monroe,&Okeechobee, (all seven)
&St. Lucie
15-22
G,ene.ral. llhuvAoer� Fb1404 f,3 01/03/;01,4, F1163
S'Uperl•.Ieded Ge,,Inerzal Dec.iisior,�, NumI)er- FL20130063
!,.2,ta:l.-e,,. Florida
Cc,)ristr.ur,-tA,on 'rype- naildlhag
couxityt Monroe COU'Ity 'Am P'lor,"...da,
BUILDI33(.3 CONSTRUCTION PROJECTS (dot,�s not include singlc� family
howes c.)r apartments up Lo arld �w,-�ludin�, 4 su -ies)
1. j D.f
Modification Num)oer Puhlica�-Ion Date
Q 01/03/201,4
EIJECO349-003 OF9/01/21.112
Rates Fringes
ELEC'.'TRICIAN
Electrica]., c:orltracts
including oiatcials that
are c*a'ver $2,00(), (300 . . . . . . . v) 9.1.15 6
Electrical ccmtrac,.ts
incluc' inq mat eri.als r-hat
are under $2,000,00c),• 27.15 9. 18
R a t f,-7 Z4
OPERVITOR C r a z,e-,
All Cranes Over 15 Ton
Yard C-rarip, Hydraialic
Crane, Capacity L5 Ton, and
Undex.." . . .. . . . . . . . . . . . . . .. . . .$ 22,00 8.80
IRON0272-004 04/01/2013
IR..ateaaa Fringes
IRONWORKER, STRUCTURAL AND
REINFORCING— . . . . 5.93
ATR0365-004 09/01/20,3.1
Rates Fringes
PAINTER. Tltui,,Oi. "1 03
SFFL0821 -001 0811.21201.3
Rates Frii-ages
Ll?,,I IIKLE,R 3ll'l'11l,,,R 1117:izu
Spr as rtic]ers) . . . . . . . .
1of4 1/3/2014 10:23 AM
u uv.rr ror r®w.ar uvdsvr r rev..wa a�.ua uwa uav mun+veua Lu.�.0 v u.v-»v
SHEE0032--003 08/12/2012
Rat.es Fringes
SFT.EtA°C.`METAL WORKER (TrVAC 011o't
Installation) — . . . . . . . . $ 23.65 12.03
CF:MR,T+7°C SON/C0TwGR9TE L INr£3HER. . .$ 12.45 0.00
FENCE ERECTOR. . - -. — . . . . - - - . . .$ 9.4 0.00
LABORER: Common or General. , . . . ,$ B.62 0.0 0
WAE34'AER.; Pipel.ayer. . . . . . . . . . — . .$ 10A5 t. A0
0T FF?ATOC2. T1ackhoe/Excavator, , a - .$ 16.98 0.00
OPRRATORc Paver (Asphalt,
degree ate, and Concrete) . . . . . . . . ,$ 9,58 0.00
C7TyF;FaWPOR: Pump. . . . . . . . . . . . . . . . .. .$ 11.00 0.00
PAIN—ER Roller and :31pray. . . . . . ,$ 1.1,2,1 0.00
PLUMBER. . . . . , . . . . . . . . 1.2,27 3.13
ROOFER: Tirxilt. up,
Composition, loot Tar and
Single Ply. . . . . . . . . . . . . . . ua : , , . W NTM 1.4A33 0.00
SHEET MRa.LT, WORKER, Excludes
HVAC Duct Tnstal l atll-on.. . . . . . . , ,. .. ..$ 14,41 3.61.
TRUCK ORIVER, Tncludes Dump
and 10 'Yard Haul Array. . . , . . , , , ..$ 8.00 0.15
WELDERS - Receive '.ante prescribed for craft performing
operation to which welding is incidental.
Unlisted classifications needed for work: not included within
the scope of the classifications listed may be added after
award only as provided :in the labor standards contract clauses
(29C»FP. 5.5 (a) (1) (iiy 1
The body of each gage determination lists the classification
and wage .rates that have Leen found to he prevailing for the
2 of 4 1/3/2014 10:23 AM
Imp'i I W WW'WUUI.8LjV)wutii/Nuilillc!51uaviboact)[1tri.0.3,UVD!V=U
cfted type(s) of construction in the area covered by the wage
determination. The c3aasifications are listed -In alphabetical
ord,er of "ideritiEiers" that-. indic,-i,te wheth(,'.sY the parti('.'.u.1ar
rate it, union or non-unioa..
Union Identif iers
An identifier enclosed in dotted lines beginning with.
characters at-her than IISUII den(.'ites thail- the 1,nliorl
t icat.ion ai)(I rate have found to be prevailing for tlu-v.
clasuiEication. Example: PLMM01,96-00S 07101'/2011� The fixst-
tour '1'ettero , PLUM, indicate the internar.Jonal union and the
ou fr-digit numher, 01.90, that fc,,llows indicates the local union.
numher or distzict anun.cil number where avplicable , I_e_
Plumbex.-s Local 0198 Tile next number, 005 in 0-ie ex-ample, is
Barn internal nuffiber used in processing the wage determination.
The date, D'7/01/2011, following these characters is they
effective date (.-)f the raost current negotiated rate/collect.ive
batgaining agreement which would be July 1, 201.1 in the above
example.
Cfnic)n. Prevailing wage ratrm,, wil] lbe.'k updated to reflect any
aaangLs in I-Ine collective bargaining agreements governing the
r a t e.,s,
0(,)00/999)-. weighted union wage i-alles will be. publls,�.u..!d annually
each January.
Non-Union Idenirifiero
Classifications liste(l under an IISUII identifie:r werF.� derived
from survey data by computing uveraL,je rates and are not union
rzALes,, however, thc--� data. used in computing these rat.u.3 may
include both union and non-union data. SO LAI 0 0 4-U 07
S/13/2010, SU indicates the ratcxs are not majority riater-ester:,
LA. indicates the State of Louisiana; 2004 is the yei,%r of the
surveyT and 007 iS an, interrUAI number uced in tproclucinq the
wage determination. A. 1993 or later. date, 5/1-3/2010, indicates
the cLissifications and ra dr tes une that i_drentiEier were issued
as a General Wage Detenwh'iatiov ion t13,1L. date
Survey wage rates will remain in effect ancl will not change
until.. a ii..ew survey Is conducted.
WAGE DETERMINNIVION APPEALS PROCESS
1. ) Has t1tere bpen an initial decision in the matter? This can
be.
* an existing published wage determination
* a survey underlying a wage deteratinat.ion
* a Kage and flour Division letter settLng to-t-th a position. cia
a waq't determinatLon matter
* a conformance (additional classificnatic�n and rate) ruiiri
3 U4 1/3/2014 10:23 AM
llLLP.11WWW.WUUl.80V/WLJUUSCal lJVSJUaVtSOUCOrl/l-1,0-1-UVO tV=U
On. sux.vpy relatc,,rl rziatr.,,ers, initial cantact, incl,nd.i.ng requests
for summaries of surveys, shrmild be with the Wage and Hour
Regiona.l Office ft-ar the, area in, whir,,wh the surw..--ay conducte-d
b(,.-2cKuse thase Regional, Offices have for tkn..�
Davis-Bacon survey program, If the -r-espansr from thi,-.; 1-nitial
con.tact i�,,; riot satlisfactoxy, then the process des.,ciribed in 2.)
and i. ) should be followed.
Witil regard to ,,-.iy)y other rwatlter not yet for tlac forma.l.
p:rocea,r4s (lesrribeil irlitial. (..�o-ntact ihrouLd he with t1ne
Branch of Construction wage Do-terri'driat.l.ons. to,
L'lran.ch of ,'oristruction Wage Determirtattor-a
Wage arld Hou-1- Divig.ion
U.S, Departrivient of Labcw
200 C(.anatituticn Avenue, N,W.
Taash.,Lngtan, DC 2021.0
2,,) Tf the answer to 1--he qtkestl,on in 's yes, then an.
interested party (those affecte(i by the action) can i,,equest
re.vtew and -47YOM tlu-, w age wad Hour Admin'l,oc.ra,tr,br
(See 29 CFR f,lart 1 8 and 29 CPR Part 7) to-
Wage and Hour Administ'rator
U-1.3. (,,'f Labor
200 (."on,,titution Avenue, M,W,
Thlash.i.ngton, IDC 20210
The request, 3hoA1d leas earn.-,�ompan-ied by a full of the
interested party's position and by any information, (wagaa
payTm:.,nt data, proje(�rt. description, a-rea prr-actice ma.te.rial,
that the reqw.,.Stnr considers releveint, to the Issule.
3.y if the decision. of the Administrator is riot favorabl", am.
intrirested party may appc-.,_al dIxectly to ;,-,-he P,,dininistrative
RevAlew Board (formerly the Wage Appeals write to:
Admin.i.strative Review Board.
Depa.7rtment of T,abar
200 l,,,,-,)rsrA.tutiq--)n Avenvie, N,.W.
Mashir).gton, DC.l. 2021(l
4 14,11 dcclsv:uis bv II hr,:a Adiml nistrative Reviwmf Boa.tA ainr firmlt
END OF GENAERA,ir, Dl,,?Cu S I ONO
4 of 4 1/3/2014 10:23 AM
nttp,//ww w.wdol.gov/wdol/scattles/davisbacon/F'Ll 90,dvb?v=C
General- Decision Number: rL140190 01/03/2014 PT,190
Superseded General Decision Number: FL20130249
State Florida
ConsLruction T,ype� Highway
County- Monroe County in Florida.
HIGHWAY CONSTRUCTION PROJ8CTS
madif icat,icri Number Publication Date
a 01/03/2014
13UFL20,13-008 (18/19/201.3
Ratew 1�'ringca
CPLRPENTER, rxicludes Form Work. . . .$ 1.1.95 1,44
CEMENT MASON/CONCRETE FINISHER— ,$ 13.65 0.00
HIGHHWAY/PARKING LOT STRIPJ',NG:
Operator (Striping Machine) _ —$ 12,70 0.00
HIGHWAY/P14RKING LOT STRIPING.
Operator (Spray Nozzleman) , . . . . . -$ 1.3108 0,00
INSTALLER - G11AR0RAIL. , . . - - , . .$ 14.44 0.0o
IRONWORKER, REINFORCIHG . . . - - -$ 1-3..85 0.00
LABORER-, Aupbalt, Includes
Raker, Shoveler, Spreader and
Distributcr. — — - - . — . . . . . . —$ 13o60 0.00
IABORF,Rz Comm an or General,—. . . .$ 11.96 2.90
1ABGRERt 9-87 0.00
LABORM Grade Checker. — , ., .. —$ 11.45 0.00
LABORM: Landscape &.
Trriqation. . . . . . . . . . . . . . .. . - -- $ 11-16 0.00
IABORER Pipelayer. ., . . . . . . . . . —$ 12.68 0.00
LABORER� Laborer-Corte s
Barricades/Barxels -
Se L ter/Move r/Sweepe r. 12.17 1.71
OPERATOR:
Backhoe/E)cc avert or/'I'irackhoe. . a.� .. . r$ 17.20 0.00
OPERA,rOR: Bobcat/Skid
Steeir/Skid Loader. . . . . . . , . 11,60 0.00
OPERATOR: Broom/Sweeper, L0.89 0.00
1of4 1/3/2014 10:IS AM
http:ilwww.wdol.gov/wdoUscatiles/davisbaconfFLI90.dvb?v=(
C)PFRA,.' P. €3u:lldarzera . .. . . . . . . . $ 13,90 0,00
0P B RA1°UR Crane. . . . . . . . . .. . . . . . . .7 17.63 0.00
OPERATOR: F^ca:rk'.k:i.F:t.. . . , , . . > 11 ,03 0.00
OPERf I'OR. t3'rzicler/131ade. . , . , , . , . .. 16.00 0,00
OP RATOR a L,a)a,der. . . .. „ . , . . . . . , . , 16.59 0.00
OPRRA'l"O Mechanic. . . . . . . . . . 13.t�5 0.00
C7PRR.3"s'`TO'R, Milling Machine. . 43.2:3 0.00
OPERATOR, Oiler- - . . . . . -- -$$ 12,61 0 00
OPIERATOR,. Paver (Asphalt,
lkgg.r:egate, and Clcrrro.r...rete) $ 3.13 17 0.00
OPERATOR., Roller. . . . . . . . . . . .- -$$ 13.28 2.39
C)PERATORc Tr's:acher.. . . . . . . . . . . . . .$ 7.6.00 0,00
T'tt.AFFIC S IGN&CST LATI ON e
``r:ra:ffica S:i.grra.l. Inst:a.11at:is:ana., . . . . .$ 19.03 0.00
'17RUCK, 1=')kRIV'R° dump Truck. . . , , . , .$ 12.60 0100
TRUCK i3RAa ERl Lowboy Truck. . , . , .$ :.14,94 0.00
TRUCK SORIVER: Wage=.r.. Truck. 3.3.05 0.00
WELDERS Receive Irate prescribed for craft: porforming
operation to which welding is incidental..
Un:d.:iste=rd classifications needed for work not included within.
the «scoj)e of the class if.icat.ions listed may be added after
award only as provided in the labor standards contract clauses
(29C FR .5,5 (a) W (Li) ) .
The body of each wage determination .lists the classification
and wage rates that have been found tea, he prevailing for the
cited type(s) of cons truct ion. in the area covered by the wage
determination. The classifications are 'listed in aalp alraet.,!.cal
order of fide nt:.3_i-:iers", Uaat indicate whether: the particular
:Kate :is ur.1:Y.o.n. or non-union.
Union Identifiers
2 of 4 1/3/2014 10:18 AM
An identific.'=r (,rx-jcj..aqed ir, dotted lin-e5 be gaining WiL,'.h
chararters other than "SU" denat,es that the union
a.l.assitication arid, rate. have found to be prenraili'n-,y for that
classification. Rxnmp,'-Lc�: P1M1',)M0j9t)-OOS 07/01/2011. 'Elie first
four letters , PLUM, in.dic'aLe th�- uni-an ,ind
four-digit rit.unber, o.198, tj iat fol.lows indicates the local uni(.x-1
riUmber or district council nuHber wh.rnra e,
Plumbers Local 01.90, Tlr:(,-, ii.ext nuimb(--,r, 005 in the example, Is
an numbeir usetl in prc..)cess i.rig the wage determinatLon.
The date, 07/01/201.1, fol.low-iji-q thes(° charaot.ers is the
effective date of the mnst cll.rx-nnt iv-,,�gnt-'Latnd. rate/collective.
barqainlng a., -eeawnt which wo�'Aid be July 2- 2o.111 ixi. th(,� above
jx
exam'ple.
Union prevail.i.ng wage rates w.-Ill be updated to reflect arry
changes tn tli.e col.I.dive b arga.LnLrlq agreements g over rriing Lhe
r a t.: S.
0000/9999! weic:lhted union wage rates, wi'1.1 be pub].Alsl-:tC!d annually
ea,ch January,
N(:)n-"Uniox1. Ident.ifiers
Clan-,�i.fications Listed under an "SU11 Identifier were derived
tinion,
f:ram survey dat'a t)y r.,ampattrig _j.vei.age� Y..,.ates and are aot
rate o; h<..swevex, the data u-9Qd in. cornputing theAe rates may
includ�-.:a k)oth union and non-union datn Rxampll e. SULA2004-01i7
S/1.3/20.10, SU indlcatc�r, the rates are not union majority rateS,
LA Lndiczates fhF: StAte of Loui.siana; 2004 is the year of thew::
survny; atir,-1 007 is an internal number used in prodtiring thc-.:
wage determination. A, 1993 or later dat'.e, indic-ar-es
r ho aIasqificatlons artcl rates under Oiat ideritifier 'Alk-re :Lssued
ar, a General wage ueterminat'lean an t-hat datre.
Survey weaqe ratos w.M. rf.,main in effect and w1.11 rioL chanq�-2
until a new survey is con&Icted.
WAGE.', DETERMINATION APPEALS PROCESS
1,) ilas there been an initial decision in the matter'? This can
be:
* an exist:jzIg p�..sbl.ished wage determination
* as surv,ey j.A..Tjder'j-yjj-jg a wage det earminat ion.
* a Wage and 1-1.our Divisiori. letter siettingl forth a position on
a wage determinati-on vwitter
* a conifform.ance (additional classification and rate) ruling
on survey related matters, initial contar,--,t, Inc.luding reqn�.--�atr-,
for stunmaries of ourv'eys, should be w.Lth the, Wage and T-T(.)ur
Regional for t-hr- arc,,a in which. the survey was conducted
because those 13.e2gional aff.lces have responsibility for the
Davls-[3acon survey, program.. If t1ri.p. response from this
cantact is not natisfactory, then the p.Y or-ess described in 2.
and 3.) should. be fol.].owed.
3 of 11312014 10:18 AM
I I LLIJ.11 W W%V.wU-6UV I WUVLPOL.O A IJLWU[Ly I aV9A%AJ1UL Is I 7%J.0 V U V—U
wi.rh rc.-.agard to any other rnai,,.tz2r not y(,.t, ripe for tlic formal
Process described here, initial contact mhou].d be wl-tea the
Branch of Cons t1inictian Wage Deter-minations,. Write ta.
Branch of Construction W,',..xqe Determinaticns
Wage and H<sur Divt—iion
TJ,P,. Departmex,'O-. of Labor
2(10 Canstiti..i.t.ion Avenu,�, DT,W.
W,'..'ishington., DC 2021.0
2,) if thme an. aaear t(,.) Lha question in. 1.) is ves, then ar.t
interested party (thase affected by the a(::tion) can request
review and re cons i de r,,-A t ion, frr,,.)rn the Wage. rand Hour Administrator
(See 29 CFR Part 1-8 and 29 ("'FR Vart 7) . Writ:e to-
Wage axi,d Hour Adimiaistrator
U.S. Dn-p,,,-.irtmPTLt of Labor
200 Cormstitution Avqmue, N.W,
Wanhinigtori, DC 202110
"'h( revque.st should be by a full statement of the.
interested party's and by any information. (wagn,
Eaayvient data, project description, area practice material,
etc, ) that the! reqL.iestor cxmaid.ers, re'levatat to the issue.
3 ) If the decision the is nr..)t f-avoral-31e_ art
interested party may appeal directly to thek
EZ(,wipw Board (formerly tlae Wage. Appe a-',,s noard , W r 1,t F- t
Admini,,-,tr.--itiv( Review nagar
E.T.S, DepartTment of Labor
200 C(.'.)n,3tituti.(.3n Avenue., U.W,
Washington., DC 20210
4-) All decisions by the A(z.1ministrati-ve Review BQ�-.krd are linal,
END OF GIENSRAE. nR,CISr.ON
4of4 113/2014 10:18 AM
{p
ADA COMPLIANCE SEGMENT# 1 &2 COMBINED
SECTION 00110
PROPOSAL.
The Proposal shall be submitted on the forms included in this section of the Proposing
Documents as previously instructed herein.
Item Description Pages
1. Proposal Form 3-7
2. Bid Bond 8
3, Non-Collusion Affidavit 9
4. Lobbying and Conflict of Interest Clause 10
5. Drug-Free Workplace Form 11
6. Sub-Contractor Listing Form 12
7. Insurance Agent and Proposer's Statements 13-15
8, Contractor License
Current Copy to Be Submitted with Bid
Subcontractor Licenses to Be Submitted Prior to
Award of Notice to Proceed
9. In order to determine if the persons or entity submitting Proposals are
responsible, all Proposals for contracts to be awarded under this section must
contain the following information:
A. A list of the entity's shareholders with five (5) percent or more of the stock or, if a
general partnership, a list of the general partners; or, if a limited liability company, a
list of its members; if a solely owned proprietorship, names(s) of owner(s). A copy of
documentation demonstrating that the entity is a legally viable entity shall be
attached. See attached 2014 for Profit Corp. annual report.
B. A list of the officers and directors of the entity; See attached 2014 annual report.
C. Relevant Experience: The number of years the person or entity has been operating
and, if different, the number of years it has been providing the service, goods, or
construction services called for in the specifications (include a list of similar projects);
See attached.
D. The number of years the person or entity has operated under its present name and
any prior names; D.L. Porter Constructors, Inc. (16 yrs)
D.L. Porter Construction, Inc. (37 yrs)
E. Answers to the following questions regarding claims and suits:
PROPOSAL FORM 00110-1
ADA COMPLIANCE SEGMENT 41 &2 COMBINED
1. Has the person, principals of the entity, entity or its officers, major
shareholders or directors, ever failed to complete work or provide the goods for
which it has contracted? (if yes, provide details.) No
2. Are there any judgments, claims, arbitration proceeding or suits pending or
outstanding against the person, principal of the entity, or entity, or its officers,
directors, or general partners (this specifically includes any present or prior
entities in which the person, principal, entity, officer, director or general partner of
the proposing entity has been involved as a person, principal, entity, officer,
director or general partner in the last five (5)years)? (If yes, provide details.) No
3. Has the person, principal of the entity, entity, or its officers, major
shareholders or directors within the last five (5) years, been a party to any law
suits or arbitrations with regard to a contract for services, goods or construction
services similar to those requested in the specifications with private or public
entities? This specifically includes any present or prior entities in which the
person, principal, entity, officer, director or general partner of the proposing entity
has been involved as a person, principal, entity, officer, director or general partner
in the last five(5)years. (If yes, provide details.) See attached letter dated 2/13/14.
4. Has the person, principal of the entity, or its officers, owners, partners, major
shareholders or directors, ever initiated litigation against the County or been sued
by the County in connection with a contract to provide services, goods or
construction services? This specifically includes any present or prior entities in
which the person, principal, entity, officer, director or general partner of the
proposing entity has been involved as a person, principal, entity, officer, director
or general partner in the last five (5)years. (If yes, provide details.)
Yes, Gato Bldg. Final Order of Dismissal 4/15/09.
5. Whether, within the last five (5) years, the Owner, an officer, general partner,
principal, controlling shareholder or major creditor of the person or entity was an
officer, director, general partner, principal, controlling shareholder or major
creditor of any other entity that failed to perform services or furnish goods similar
to those sought in the request forbids; No
6. Customer references(minlmum of three), including name, current address
and current telephone number; See attached.
7. Credit References (minimum of three), including name, current address and
current telephone number; See attached.
8. Financial statements for the prior three years (Please provide in a separate
sealed envelope for the Contractor's confidentiality).
Any financial statement that an agency requires a prospective Proposer to
submit in order to prequalify for Proposing or for responding to a Request for
Proposal for a road or any other public works project is exempt to the extent
stated in s. 119.07(1) and s.24(a), Art. 1 of the State Constitution. Enclosed separately.
9. Subcontractor Listing Form. See attached.
PROPOSAL FORM 00110-2
ADA COMPLIANCE SEGMENT#1 &2 COMBINED
SECTION 00110
PROPOSALFORM
PROPOSAL TO: MONROE COUNTY BOARD OF COUNTY
COMMISSIONERS
c/o PURCHASING DEPARTMENT
1100 SIMONTON STREET
ROOM 1-213
KEY WEST,FLORIDA 33040
PROPOSAL FROM; „ D.L. PORTER MNSTRULIM INC.
a x Par R _Cr_6 e
Sarasota FL 34238
The undersigned, having carefully examined the Scope of Work and reference Drawings,
Speoifioatlons, Proposal, and Addenda thereto and other Contract, Documents for the
construction of,
ADA COMPLIANCE
"SEGMENTS 1 AND 2 COMBINED"
Repairs to 37 Monroe County Facilities
From Key Largo to Key West
and having carefully examined the site where (lie Work is to be performed, having become
familiar with all local conditions Including labor affecting the cost thereof,and having familiarized
himself with material availability, Federal, State, and Local laws, ordinances, rules and
regulallons affecting performance of the Work, does hereby propose to furnish all labor,
mechanics, superintendents, tools, material, equipment, transportalton services, and all
Incidentals necessary to perform and complete said Work and work Incidental hereto, In a
workman-like manner, In conformance with said Drawings, Specifications, and other Contract
Documents Including Addenda Issued thereto.
The undersigned further certifies that he has personally Inspected the actual location of where
the Work Is to be performed, together with the local sources of supply and that he understands
the conditions under which the Work is to be performed. The successful Proposer shall assume
the risk of any and all costs and delays arising from the existence of any subsurface or other
latent physioal condition which could be reasonably anticipated by reference to documentary
Informallon provided and made available,and tom inspection and examination of the site.
The Proposal shall be furnished below In words and numbers. If there is an
Inconsistency between the two the Proposal In words shall control.
Hundred and 00/100
Nine Hundred Eight Thousand One Hun_.
(Total Base Proposal-words)
908,100.00
(Total Base Proposal--numbers)
PROPOSAL FORM 00110-3
A COMPLIANCE SEGMENT#1 &2 COMBINED
I acknowledge Alternates as follows:
ADD ALTERNATE NO. 1:
Reworking of handloapped bathroom at Veterans park located at Mile marker 42 along the
Overseas Highway to provlce ADA Accessablilly and accessible featuros. Rework existing
accessible sidewalk and plcnic bench to ensure accessababliily.
Eighteen Thousand Nine Hundred Thirteen and 0+01100
(Total Bass Proposal Words)
18,913.00
(Total Base proposal—Numbers)
ADD ALTERNATE NO.2:
Reworking of Big Pine Senior Center to provide an ADA Compliant accessible ramp, accessible
parking space,connected to the accessible route to the front door,compliant entry to the facility
and a compliant restroom.
Forte-Seven Thousand Two Hundred Seven! -E1 ht and 00/100 D
(Total Base Proposal Words)
ll' 47,278.00
(Total Base proposal—Numbers)
ADD ALTERNATE NO. 3:
Renovations to the Historic East Martelio Tower Port. Provide and Install an ADA Complaint
parking space and accessible rout to the entrance of the historic fort. Provide and Install an ADA
complaint Wselchalr lift at front entrance stalrs(thls will require demolition of part of the existing
stalrway. Provide a compliant transition and ramp to the center courtyard of the East Martello
Fort.
One Hundred Twenty-Five Thousand Four Hundred Ninety-One and 00110
(Total Base Proposal—Words)
;L 125,491.00
(Total Base Proposal Numbers)
ADD ALTERNATE NO.4:
Instllalion of an ADA Compliant picnic table and shade structure at Sunset Point Park, In Key
Largo.
Twelve Thousand Seven Hundred Et h -Five and 001100
(Total Base Proposal--Words)
12,785.00
(Total Base Proposal—Numbers)
PROPOSAL FORM 00110-4
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
ADD ALTERNATE NO. 5:
Addition of a new handicap accessible ramp at the Big/Pine Community Park in Big Pine Key.
Installation includes removal of the existing door thresholds at the public meeting room on the
second floor and ptoviding /then installing an ADA compliant threshold and transition.
vau'rTe l -lVlwas.
(Total Base Proposal-Words)
S6 .0
(Total Base Proposal-Numbers)
I acknowledge receipt of Addenda No.(s)
No.1 Dated 1/1 sh 4
No.2 Dated 2/3/14
No. ®Gated' .... _.
No. Dated.""
No. Dated
1 have included pages 00110 - 3 through 22of the Proposal which entails the Proposal
Form x , and the required Bid/Proposal Security, the Non-Collusion Affidavit_, the
Lobbying and Conflict of Interest Clause x , the Drug-Free Workplace Form x , and the
Subcontractor Listing Form x. In addition, I have included a certified copy of Contractor's
License, Monroe County Occupational License, Insurance Requirements- Hold Harmless
Statement and an Insurance Agent's Statement(pages 00110-*k0 through lc2).
13 15
(Check mark items above as a reminder that they are included.)
Mailing Address: D.L. PORTER CONSTRUCTORS, INC.
6574 Palmer Park Circle
Sarasota, FL 34238
Phone Number: 941-929-9400
Date. j3j-L4 Signed:
C. Marshall White
(Name)
Vice President
(Title) r
Zo
Witness: „
Pate ette Jewell
(Seal)
PROPOSAL FORM 00110-5
ADA COMPLIANCE SEGMENT#1 &2 COMBINED
SCOPE OF WORK
As referenced Its the Proposal documents,please list costs as per plans and s eoltloallons on h
"site by site"basis on the list below.The allached drawings are In order as follows;
1. Key Largo Animal Shelter $ 17,,985.00
2, Key Largo Harry Harris Park v 23,4t1.00
3. Plantation Key Annex(Jerry Dills Bldg.) $ 32,421.00
4. Plantation Key Government Center(Courthouse) $ 25,655.00
S. Plantation Key Publio Works/Social Services 27,09500
6. Plantation Key Roth Building $ 20,0 11 63.00
7. Cslamorada Library $ 10,268.00
8. Marathon Govemment CenterAnnex $ 57,516.00
9. Marathon Animal Shelter $ 35,694.00
10.Marathon Drivers'License $ 13,537.000
11.Marathon Senior Center $ 9,816.00
12,Marathon Health Department 14,846.00� M
13.Marathon Library $ 19,525.00
14.Bayshore Manor(Stook Island) $ 18,095.00
15.Marathon Government Center(EOC) $_ 22,568.00
16.Palm Villa Park(Big Pine They) $ 15,217.00
17.Blue Heron Park(Blg pine Key) $ 13,123.00
18.Old Stigl ttz House(Big Pine Key) $ 11,093.00
19.Freeman Sheriff Substation(Cudjoe Key) 13„774.00
20,Daypoint Park(Bay Point) $ 40,494,00
21.Wiilielmina Harvey.Park(Big Coppitt) $, '11 022.00
22.Key West Animal Shelter(Stock Island) It— 98—.00
23.Department of Juvenile Justice building(Stock Island) $� 16,64$.00
PROPOSAL FORM -- ... 00110-0
ADA COMPLIANCE SEGMENT#1 &2 COMBINED
24.Stock Island Detention Center(Stook Island) 3 1 1.
25, Sheriffs Headquarters(StockIsland) 30 21100
27.Key Test Driver's License Brarich(Key West) $ 3i 578,00
29.Gato Buitding(Key West) $_ 14,118,00
29,Harvey Govermient Center(Key West) $ 20,770.00 -
30.Senior Nutrition Center(Key West) ,$ ,_22,661.00
3).LesterBuilding(Key LVcst) $ 17,474.00
32.Old Courthouse(Key Nest) �8,062.00
33.May Hill Key West Library(Key West) $ —34,479.00
34,Veterans Park(mile marker 42)—Alternate R $ 1,y8,913.00 �
35.Big Pine Key Senior Center—Alternate#2 $ 47,27&00
36.Last Martello ToNver Dort(Key West)—Alternate 93 $ 125,491.00
37.Sunsct Point Park(Key Largo)—Alternate 04 $ 12,785.00
26.Big Pine Key Community Park A.lteninte#5 14,563.00
S�dga ., ODD
0
oo . oD 4WL
PROPOSAL FORM 00110-7
ADA COMPLIANCE SEGMENT#1 &2 COMBINED
SECTION 00310
SUPPLEMENTARY PROPOSAL FORM FOR UNIT PRICES
TO, Monroe County
Herein called"Owner"
1. The undersigned, having examined the proposed Contract Documents titled:
REQUEST FOR PROPOSALS
ADA COMPLIANCE
"SEGMENTS 1 AND 2 COMBINED"
Repairs to 37 Monroe County Facilities
From Key Largo to Key West
and having visited the site and examined the conditions affecting the Work, hereby proposes
and agrees to furnish all labor, materials,equipment,and appliances,and to perform operations
necessary to complete the Work as required by said proposed Contract Documents.
The following prices include all General contractor mark-up and are net to the Owner.
2. Should additional concrete repairs be required,the undersigned proposes the following
unit prices.
A. Underground electrical primary(trench,conduits,concrete protection).
1. Unit price per lineal foot of primary.
Four Hundred and 00/100 per LF
DOLLARS( 400.0 0 )
B. Underground electrical secondary.
1. Unit price per lineal foot of secondary.
Four Hundred Seventy-Five and 00/100
per LF DOLLARS($ 4 «00
C. Underground sewer line.
1. Unit price per lineal foot of underground sewer line.
Thirty--Five and 00/100 per LF
SUPPLEMENTARY PROPOSAL FORM FOR UNIT PRICES 00310-1
I
. ... _..m.. .. ®COMPLIANCE SEGMENTf 1 COINED
ADA t & 2 COMBINED
COMPLI„ __. a. _...... _ ... e�.
_. _.... ,,.,...... I)OLLARS ('�..3..5_. 0 0 .. _... _....
D. Underground water line,
1, Unit price per lineal foot of water line.
Thirty-Five and 00/100 per LF
_........__...DOLLARS ( 35. 00
E, Cost per ft. of additional auger pile depth.
(Assumed depth 10'-D" below existing grade plus height of fill)
1, Unit price per additional lineal foot of pile.
One Hundred and 00 1 00 der Lk'
. m..m._._D0LLARS
3. The undersigned understands and agrees to comply with and to be bound by any
instructions to Proposers issued for this Work.
Q. The undersigned acknowledges receipt of Addenda:
No. 1 DATED: /14 NO. DATED:
No, DATED: 2 3 1 NO. DATED:
No.—DATED:— NO. DATED:
PROPOSERD.L. o .'ter Con truci.'ors® Inc.
ADDRESS: 6574 Palmer Park Circle
Sarasota, FL 34238
LICENSE NO. CA51 06
LICENSETYPE Class A Contractor
y dated this 1 3L•h _day of February 2 1 ,
END F SECTION 00310
SUPPLEMENTARY PROPOSAL FOR FOR UNIT PRICES __.. _._m...._.._. __ _... ....-.....
0031010-2
i
ADA COMPLIANCE SEGMENT# 1 &2 COMBINED
BID BOND
KNOW ALL MEN BY THESE PRESENTS,that we
(Here insert name and address or I Ir J t l Contractor)
as Principal,hereinafter called the Principal,and 0
(Here insert fts name an (It ss or legal title of Surety)
I
a corporation duty organized under the laws of the State of as Surety 1, inafter called the Surety,are held and
firmly bound unto
�Ile ri full name and address or legal title of Owner)
,($),,for the payment of which sum well and truly to
as Obligee,hereinafter called the Obligee,in URI Mr as
be made,the said Principal and the said"aaarea w i is I as elves,our heirs,executors,administrators,successors and
assigns,jointly and serverally,firmly by these e en
WHEREAS,the Principal has submitted a bid fo
(Here insert full name,address and description of project)
NOW,THEREFORE,if the�alil c s ,II accept the bid of the Principal shall enter into a Contract with the Obligee
in accordance with the terms ol'sueb Q,and give such bond or bonds as may be specified in the bidding or
Contract Documents with good an I sufflicient surety for the faithful performance of such Contract and for the
prompt payment OA'�or o d is ^rial furnished in the prosecution thereof,or in the event of the failure of the
Principal to ca(w such G e and give such bond or bonds,if the Principal shall pay to the Obligee the difference
not to exceed than wn r of between the amount specified in said bid and such larger amount for which the
Obligee may in good 14,1 ontact with another party to perform the Work covered by said bid,then this obligation
shall be null and voi,, at erwise to remain in full force and effect. Any action instituted by a claimant under this
bond must be in accoa iiec with the notice and time limitations provisions in Section 255.05(2),Florida Statutes.
(Principal) (Seat)
(Witness)
.................
(Title)
(Surety) (Seat)
............
(Witness)
(Title)
PROPOSAL FORM 00110-8
U
ADA COMPLIANCE SEGMENT# 1 &2 COMBINED
SECTION 00110'
NON-COLLUSION AFFIDAVIT
I` C. Marshall White of the city_____5gkrasota
_._....m.�a
according to law on my oath, and under penalty of perjury,depose and say that:
1„ jam, Vice P_re.esident .� . ,....,�.,.�.. ..._ ......... .. �.,_.�...-
of the firm of n Porter Constructors, Inc.
the bidder makin them Pro-o osal for thW1 ro�ect described in the not.
-ice.
p p ce for calling for bids for:
Monroe County Board of County Commissioners
and that I executed the said proposal with full authority to do so;
2. The prices in this bid have been arrived at independently without collusion, consultation,
communication or agreement for the purpose of restricting competition, as to any matter relating to
such prices with any other bidder or with any competitor;
I Unless otherwise required by law, the prices which have been quoted in this bid have not been
knowingly disclosed by the bidder and will not knowingly be disclosed by the bidder prior to bid
opening,directly or indirectly,to any other bidder or to any competitor;and
4. No attempt has been made or will be made by the bidder to induce any other person,partnership or
corporation to submit, or not to submit,a bid for the purpose of restricting competition;and
5. The statements contained in this affidavit are true and correct, and made with full knowledge that
said project.
_.
•�°� ' 2/13/14
Si nature of Bidders (..._
( 9 )� � (Date)
STATE OF: Florida
COUNTY OF: Sarasota
PERSONALLY APPEARED BEFORE ME,the undersigned authority,. C. Marshall White
who,after first being sworn by me,(name of individual signing)affixed his/her signature in the space provided above
on this 13th day of February 14
�6�TARUBLIC ��
My commission expires: JEWELL
fPNdHYHY COMMISSION q EE210508
UHUC EXPIRES JULY 16 2016
kT 60NDEDTHR000H
Iku INSURANCE COMPANY
PROPOSAL FORM 00110-9
I
ADA COMPLIANCE SEGMENT# 1 &2 COMBINED
SECTION 00110
LOBBYING AND CONFLICT OF INTEREST CLAUSE
SWORN STATEMENT UNDER ORDINANCE NO. 010-1990
MONROE COUNTY, FLORIDA
ETHICS CLAUSE
D.L. POR= CONSTRUCTORS, INC.
(Company)
warrants that he/it has not employed, retained or otherwise had act on his/its behalf any former County
officer or employee in violation of Section 2 of Ordinance No.010-1990 or any County officer or employee in violation
of Section 3 of Ordinance No. 010-1990. For breach or violation of this provision the County may, in its discretion,
terminate this contract without liability and may also, in its discretion, deduct from the contract or purchase price, or
otherwise recover, the full amount of any fee, commission, percentage, gift, or consideration paid to the former
County officer or employee".
(Signature)C. Marshall white, VP
Date. 2/13/14w w
STATE OF: Florida
COUNTY OF: Sarasota
( ) 2 14 ...._._ . ... (date)
Subscribed and sworn to or affirmed before me on w,,,,,w� 1 _m,mmm_ -�_�.
b C. Marshall White name of affiant.y _ w _ITIT ,ITITIT_ITm ( ) Hel>�14e is personally known to me
or has produced INDCK30= as identification. (Type of
identification) _
NOTARY PUBLIC
My commission expires: [1T'67QA160FEXPIRES
AULME JEWELLC q EE21Q508
DULY L6 2016
NONDED THROUGH
RII INSURANCE COMPANY
m
PROPOSAL FORM 00110-10
ADA COMPLIANCE SEGMENT# 1 & 2 COMBINED
DRUG-FREE WORKPLACE FORM
The undersigned vendor in accordance with Florida Statute 287.087 hereby certifies that:
D.L. PORTER CONSTRUCTORS, INC.
(Name of Business)
1. Publishes a statement notifying employees that the unlawful manufacture, distribution,
dispensing, possession, or use of a controlled substance is prohibited in the workplace and
specifying the actions that will be taken against employees for violations of such prohibition.
2. Informs employees about the dangers of drug abuse in the workplace, the business's
policy of maintaining a drug-free workplace, any available drug counseling, rehabilitation, and
employee assistance programs, and the penalties that may be imposed upon employees for
drug abuse violations.
3. Gives each employee engaged in providing the commodities or contractual services that
are under bid a copy of the statement specified in subsection (1).
4. In the statement specified in subsection (1), notifies the employees that, as a condition
of working on the commodities or contractual services that are under bid, the employee will
abide by the terms of the statement and will notify the employer of any conviction of, or plea of
guilty or nolo contendere to, any violation of Chapter 893 (Florida Statutes) or of any controlled
substance law of the United States or any state, for a violation occurring in the workplace no
later than five (5) days after such conviction.
5. Imposes a sanction on, or require the satisfactory participation in a drug abuse
assistance or rehabilitation program if such is available in the employee's community, or any
employee who is so convicted.
6. Makes a good faith effort to continue to maintain a drug-free workplace through
implementation of this section.
As the person authorized to sign the statement, I certify that this firm complies fully with the
above requirements.
Proposer s Signature
2/13/14
Date
I
PROPOSAL FORM 00110-11
ADA COMPLIANCE SEGMENT#12 COMBINED
SUBCONTRACTOR LISTING FORM
Ph N Warea
Div. Subcontractor Contact Person code Fax: Cell; Address
xxx-xxx-�atxx x�.e-xxx-rx�e xa^r-xxx-xxxx
6574 Palmer Park Circle,Sarasota,FL 34238(Hdgl)
2 D.L.Porter Constructors,Inc. Marshall White 941-929-9400 941-929-9500 941-650-3311 302 Southard St.,Suite 209,Key West,PL33040
3 Hatntner Scotts Inc. Gone Lenhart 727-595-4304 813-477-2736 12419 Chickasaw Tr.,Largo,FL 33774
5 Global Boundaries Ran Gentil 941-927-6000 941.794-0733 941-962-9140 1234 S,Commerce Blvd.,Sarasota,FL 34243
6574 Palmer Park Circle,Sarasota,FL 34238(11dgl)
6 D.L.Porter Constructors Inc. Marshall White 941-929-9400 941-929-9500 941-650-3311 302 Southard St Suite 209,Key West,12L 33040
i
i
oo11a-12
PROPOSAL FORM
ADA COMPLIANCE SEGMENT## 1 & 2 COMBINED
BIDDER'S/PROPOSER'S INSURANCE AND INDEMNIFICATION STATEMENT
INSURANCE REQUIREMENTS
Worker's Compensation Statutory Limits
Employers Liability $1,000,000/1,000,000/1,000,000
General Liability, including $1,000,000 Combined Single Limit
Premise Operation_ or
Blanket Contractual $500,000 per Person
Expanded Definition of Property Damage $1,000,000 per Occurrence
Products and Completed Operations $100,000 Property Damage
Personal Injury
Underground, Explosion and Collapse(XCU)
Vehicle Liability (Owned, nonowned, and hired vehicles) $1,000,000 Combined Single Limit
or
$500,000 per Person
$1,000,000 per Occurrence
$100,000 Property Damage
Builders' Risk
Builder's Risk will be required on sites when there are structural alterations on a
building.
Coverage shall include:
Theft, Windstorm, Hail, EFxplosion, Riot, Civil Commotion, Aircraft, Vehicles, Smoke,
Fire, Collapse, and Flood.
The policy limits shall be no less than the amount of the finished project and coverage shall be
provided on a completed value basis.
Property located on the construction premises, which is intended to become a permanent part of
the bulding, shall be included as property covered.
The policy shall be endorsed permitting the County to occupy the building prior to completion
without effecting the coverage.
The Monroe County Board of County Commissioeers shall be named as Additional Insured and
Loss Payee.
INDEMNIFICATION AND HOLD HARMLESS FOR CONSTRUCTION CONTRACTORS AND
SUBCONTRACTORS
The Contractor covenants and agrees to indemnify and hold harmless Monroe County Board of
County Commissioners from any and all claims for bodily injury (including death), personal
injury, and property damage (including property owned by Monroe County) and any other
losses, damage, and expenses (including attorney's fees, court costs and expenses) which
arise out of, in connection with, or by reason of services provided by the contractor or any of its
Subcontractor(s) in any tier, occasioned by the negligence, errors, or other wrongful act or
omission of the contractor or its Subcontractor(s) in any tier, their employees, or agents.
In the event the completion of the project (to include the work of others) is delayed or
suspended as a result of the Contractor's failure to purchase or maintain the required insurance,
the Contractor shall indemnify the County from any and all increased expenses resulting from
such delay.
PROPOSAL FORM 00110-13
........ .. ADA COMPLIANCE SEGMENT# 1 &2 COMBINED m m v ww„
The first ten dollars ($10.00) of remuneration paid to the contractor is for the indemnification
provided for above.
The extent of liability is in no way limited to, reduced, or lessened by the insurance requirements
contained elsewhere within this agreement.
PROPOSAL FORM 00110-14
ADA COMPLIANCE SEGMENT#1 &2 COMBINED
PROPOSER'S STATEMENT
I understand the insurance that will be mandatory If awarded the contract and will comply In full
with all the requirements.
D.L. PORTER CONSTRUCTORS, INC. ��
Proposer Signature
INSURANCE AGENT'S STATEMENT
I have reviewed the above requirements with the Proposer named above. The following
deductibles apply to the corresponding policy.
POLICY DEDUCTIBLES
WC208074501 $0
GL2059363 $0
CA20593610601 $0
Liability policies are X Occurrence Claims Made
Bouchard Insurance -4A
a ems.
Insurance Agency Signature
INSURANCE REQUIRMENTS AND FORMS O400-8
CT,
STA
E PARTMENT OF, BUSINESS AND PROFESSIONAL REGULATION
CON` TRUgT ON ND ' T Y L CEN SINS I�OARD, SEW LT2o9010119Q
,MOTO �, CENSE NEB
1 M7
tinder S O o f ChapL6;' 4�89 E .
Expiratign date., AUG ,31,, , �2 014
LOER,% &NARY ' SCAN
L R ''ER CON"STR 'CTOIRSO INC
6574 A' MER PARK CIRCLE
SARASOTA, ." S
RICK ,SCOT" - KEN LAWSON
GOVERNOR, . SECRETARY
2013 / 2014
MONROE COUNTY BUSINESS TAX RECEIPT
EXPIRES SEPTEMBER 30, 2014
RECEIPT#30140-60602
Business Name: D L PORTER CONSTRUCTORS INC
Owner Name: GARY A LOER QUALIFIER Business Location: MO CTY
Mailing Address: KEY WEST,FL 33040
302 SOUTHARD ST STE 209 Business Phone: 941-929-9400
KEY WEST, FL 33040 Business Type: CONTRACTOR(GENERAL CONTRACTOR
CGCO51066)
Employees 20
STATE LICENSE: CGCA51066
Collection Cost ota Pa i
Transfer Fee Sub Total Penalt Prior Years Tax Amount
50.00 0.00 50.00 0.00 0,00 50.00
.......... ......
Paid 000-12-00007332 08 20/2013 50.00
THIS RECEIPT MUST BE POSTED CONSPICUOUSLY IN YOUR PLACE OF BUSINESS
THIS BECOMES A TAX RECEIPT Danise D. Henriquez, CFC,Tax Collector THIS IS ONLY A TAX.
WHEN VALIDATED PO Box 1129, Key West,,FL 33041 YOU MUST MEET ALL
COUNTY AND/OR
MUNICIPALITY PLANNING
AND ZONING REQUIREMENTS.
MONROE COUNTY BUSINESS TAX RECEIPT
P.O. Box 1129, Key West, FL 33041-1129
EXPIRES SEPTEMBER 30, 2014
Business Name: D L PORTER CONSTRUCTORS INC RECEIPT# 30140-60602
Business Location- MO CTY
Owner-Name. GARYA LOER QUALIFIER KEY WEST, FL 33040
Mailing Address:302 SOUTHARD ST STE 209 Business Phone. 941-929-9400
KEY WEST,FL 33040 Business Type: CONTRACTOR(GENERAL CONTRACTOR
CGCO51066)
Employees 20
STATE LICENSE: CGCA51066
_riai�a Sub Total EoFf,,tlon Cost T 1d�
�en Tax Amount [i'ransfer Fee a
_�o
�_tE
50.00 0.00 0.00 50.00
.0)p 0 0
0.1
Paid 000-12-00007332 08/20/2013 50.00
"ARI ()Ic FILED
VALM 1-j L L r DOCUM Fab 07,2014ENTO P98000042047 Secretary of State
Entity Name: D.L.PORTER CONSTRUCTORS,INC. CC2778886878
Current Principal Place of Business:
6574 PALMER PARK CIR
SARASOTA, FL 34238
Current Mailing Address:
6574 PALMER PARK CIR
SARASOTA, FL 34238
FEI Number:65-0848440 Certificate of Status Desired: Na
Name and Address of Current Registered Agent:
WHITE,C.MARSHALL
6574 PALMER PARKCIRCLE
SARASOTA,FL. 34238 US
The abays named entity surbvnits this 51afemardlbrfhepurpm cfchwVb;its registered oforr-ewferedagent orbvib,fa the Shia&Rbfida.
SIGNATURE:
Electronic Signature of ReglateredAgent
Officer/Director Detail :
Title VP Tale p
Name WHITE,C.MARSHALL Name LDF R,GARY A
Address 6574 PALMER PARK CIR Address 6574 PAL161ER PARK CIR
City-State-Zip: SARASOTA FL 34233 City-State-Zip: SARASOTA FL 34238
Title S Title T
Name JEWELL,PAULETTE Name WHITE,C.MARSHALL
Address 6574 PALMER PARK CIRCLE Address 6574 PALMER PARK CIRCLE
City-State-Zip: SARASOTA FL. 34238 City-State-Zip: SARASOTA FL 34238
wpiabyCarmytwMe wMawa xqlv"� 05 10amm awhamave wmwwwas
ow.A--als r4artm r.WVWbyULNW4M1,F&M S=fts;aW=,TV=4 Moa*aWV4 aron mawAvatwman
SIGNATURE: PAULETTE JEWELL CORPORATE SECRETARY 02107121314
........... ...........
Electronic Signature of Signing OfficarlDirector Detail Date
I
9.C.
RELEVANT EXPERIENCE
ADA COMPLIAN'Clr,S GMI TMi'I I &2 COMBINENI
PROJECT OWNER/ARCHITECT
Aids Memorial Addition Monroe County Board of Cty Commissioners
Granite Memorial Bench mbi-k2m Architecture,Inc.
* Key West,FL($159,000) Key West,FL
Ash Transfer Center City of Key West
Key West,FL
* Key West($854,041)
M2 Coppitt Fire Facility Monroe County Board of Cty Commissioners
Morrison/Knudsen Gerrits
Big Coppitt Key,FL ($1,043,000) Key West,FL
Buquebus Ferry Terminal City of Key West
T Peter Pike&Associates
Key West,FL($2,261,997) Key West,FL
Courthouse Annex Renovation Monroe County Board of Cty Commissioners
Gonzalez Architects
* Key West,FL($584,484) Key West,FL
Crawl KelFire Training Addition Monroe County Board of Cty Commissioners
Key West,FL
* Crawl Key,FL($54,860)
Department of Homeland Security Key West GSA,LLC
'Pampa,FL
* Key West,FL($2,545,711) RMJ Architects
Tampa,FL
FL Keys Mosquito Control Hangar FL Keys Mosquito Control District
Thomas E.Pope,P.A.
" Key West,FL($7,545,222) Key West,FL
Fort Village&Robert Gabriel Housing Housing Authority of the City of Key West
Complex(Doors&Windows Replacement) Key West,FL
12 Bldgs
* Key West,FL($570,453)
Freeman Justice Center Drug Court Monroe County Board of Cty Commissioners
Renovations Currie Sowards Aguilla Arch.
* Key West,FL($512,998) Delray Beach,FL
i
Gato Bldg.Interior Renovation Florida Department Of Health
Bender&Assoc.,Architects
* Key West,FL($1,812,444) Key West,FL
Gato Bldg.Exterior Restoration Monroe County Board of Cty Commissioners
(Historic Preservation) Bender&Assoc.,Architects
* Key West,FL($4,027,200) Key West,FL
Key West Biaht,Public Restrooms City of Key West
Gonzalez Architects
* Key West,FL ($246,000) Key West,FL
Key West International Airport Monroe County Board of Cty Commissioners
Baggage Claim Hall Renovations Key West,FL
Jacobs
* Key West,FL ($1,044,404) Miami,FL
Ka West International Airport Monroe County Board of Cty Commissioners
Hangar Development,Taxiways&Aprons Key West,FL
URS Corporation
* Key West,FL ($3,431,000) Miami,FL
Key West International Airport Monroe County Board of Cty Commissioners
Addition&Renovation Key West,FL
Gonzalez Architects
* Key West,FL($3,629,050) Key West,FL
Kev West International Airport Monroe County Board of Cty Commissioners
Generator w/Ruilding Key West,FL
URS Corporation
* Key West,FL($270,650) Miami,FL
Key West International Airport Monroe County Board of Cty Commissioners
Miscellaneous Improvements Key West,FL
URS Corporation
*Key West,FL($198,000) Miami,FL
Lester Building Enclosure Monroe County Board of Cty Commissioners
Gonzalez Architects
* Key West,FL ($319,796) Key West,FL
Little Hamaca Park City of Key West
Key West,FL
* Key West,FL($149,780)
Mallory Square Restroom City of Key West
Gonzalez Architects
* Key West,FL($224,173) Key West,FL
Mallory Square Seawall&Plaza City of Key West
and Sculpture Garden Gonzalez Architects
* Key West,FL($2,900,000) Key West,FL
Marathon Airport Sheriff s Hanear Monroe County Sheriff s Office
Simulator Classroom Monroe County Board of Cty Commissioners
* Marathon,FL($103,779) Marathon,FL
lhrlwt�a;�tee f;`au � ' 1rientiarn «" ailit Manatee County Board of Cty Commissioners
Centex Rooney Constr. Co.
* Port Manatee,FL($3,480,000) Lake City,FLP
Marathon Diesel General Florida Keys Electric Coop
Generating Plant Marathon,FL
* Marathon,FL($862,000)
Marathon Hangar Building Monroe County Board of Cty Commissioners
Key West,FL
* Marathon Key,FL($374,980) Rosenblatt-Naoeri Associates
Summerland Key,FL
Monroe County Detention Monroe County Board of Cty Commissioners
Facility-Key West Key West,FL
* Concrete Pkg.($1,071,286) Morrison-.Knudsen/Gerrits
* Masonry Pkg. ($1,079,555) Construction Managers
Monroe County Detention Monroe County Board of Cty Commissioners
Facility-Foundation Pkg. Key West,FL
Hansen Lind Meyer
* Key West,FL($506,103) Orlando,FL
Monroe County Detention Monroe County Board of Cty Commissioners
Sheriffs Headquarters Morrison-Knudsen Gerrits
Key West,FL
* Key West,FL($3,472,000)
Monroe County Library Monroe County Board of Cty Commissioners
Thomas E.Pope,AlA
* Key West,FL($652,773) Key West,FL
Monroe County Public Service Facility Monroe County Board of Cty Commissioners
Asbestos Abatement Demolition Key West,FL
* Key West,FL($429,339)
Monroe County Sheriffs Han ar Monroe County Board of Cty Commissioners
Marathon Airport URS Corporation
Miami,FL
Marathon,FL($1,569,414)
Monroe Sheriffs Substation& Monroe County Board of Cty Commissioners
Tax Collectoes Offices Bender&Associates Architect
Key West,FL
* Marathon,FL($733,000)
Naval Air Station United States Navy-SOUTHDIV
Restroom Renovations A 931 Key West,FL
* Key West,FL($46,058)
Naval Air Station United States Navy-SOUTHDIV
Repairs&Alterations A-149 Key West,FL
* Key West,FL($10,700)
Naval Air Station United States Navy-SOUTHDIV
Addition to Bldg A1019 Key West,FL
* Key West,FL($120,806)
Naval Air Station-Indoor United States Navy-SOUTHDIV
Racquetball Courts Key West,FL
* Key West,FL($142,715)
Old Mariner's hospital Renovation Monroe County Board of Cty Commissioners
Plantation Key Sheriffs Substation Bender&Associates Architect
* Key West,FL($3,015,400) Key West,FL
Parr and Ride Parking Garage City of Key West
Key West,FL
* Key West,FL($3,597,557)
Public Service Facility City of Key West
Fire Station#1 Phase I Key West,FL
Gonzalez Architects
* Key West,FL($2,027,000) Key West,FL
Public Service Facility City of Key West
Police Station—Phase H Key West,FL
Gonzalez Architects
*Key West,FL($4,230,038) Savannah,GA
Retail Store Expansion City of Key West
201 William St. Key West,FL
Peter Pike Architect
*Key West,FL($122,796) Key West,FL
Roof Canopy at SWTE City of Key West
CH2M Hill,Architect
* Key West,FL($82,025) Gainesville,FL
Senior Citizens Plaza Concrete Repair Housing Authority of the City of Key West
Wiss,Jenney,Elstner Assoc.
* Key West, FL($7,841,206) Northbrook,IL
West Martello Public Restrooms Monroe County Board of Cty Commissioners
Key West,FL
*Key West,FL($159,900) William P. Horn Architect
Key West,FL
D.L. Porter
(OnstructOr$, Inc. Innovation on a Solid Foundation
February 13,2014
Monroe County Board of County Commissioners
c/o Purchasing Department
1100 Simonton St.,Room 1-213
Key West, FL 33040
RE: ADA Compliance"Segments 1 and 2 Combined"
Repairs to 37 Monroe County Facilities
From Key Largo to Key West
Litigation Summary
D.L. Porter Constructors,Inc.hereby acknowledges that it has a pending
arbitration action with the Florida Keys Mosquito Control District with pending
depositions and mediation due later this year.
C.Marshall White,Vice President
6574 Palmer Park(ircle,Sarasota,Florida 34238 �L) Office(941)929-9400 Fax(941)929-9500
dlporter.com
9.E.6 7
CUSTOMER REFERENCES
lot_ _e Address Phone
r
onroe County BOCC 1100 Simonton St, 305-292-4468
TTN: Mike Nate a C :e West,FL 33040
ZRancho Motel _ 830 Truman Ave. 305-304-8140
TN: Tejas Soni Key West,FL 33040
111 Gonzalez Architects 32 E. Bay St. 912-201-9888
,ATTN: Jose Gonzalez Savannah, GA 31401
�Bender&Associates 410 Angela St. 305-296-1347
ATTN: Bert Bender Ke West,FL 33040
CREDIT REFERENCES
Name Address Phone
Power Air Conditioning, Inc. 1525 N. Osprey Ave. 941-362-8801
ATTN: Bob Cast°iglioaae Sarasota, FL 34236
Florida Keys Electric,Inc. 5730 2nd Ave.: 305-296-402
A"l�m: Raymond Vaarciatez Key West, FL 33040
'3C Construction Corporation 3601 NW 55 St., Suite 201 305-638-5511
ATTN: Orlando Cas<arie o Miami, FL 33142
Douglas H. Kresge LLC 1915 11th St. 941-376-1580
ATTN: Doug Kresge Sarasota,FL 34236
D.L. Porter Constructors, Inc.