1st Change Order 03/09/2012 ONROE COUNTY ENGINEERING CONTRACT CHANGE ORDER PROJECT TITLE: No Name Key Bridge Emergency Repairs CHANGE ORDER NO: 1 INITIATION DATE: 3/9/12 TO CONTRACTOR: CONTRACT DATE: 2/3/12 The Contract is changed as follows: The original Contract Sum........................................................................$143,000.00 Net change by previously authorized Change Orders............................................$ 0.00 The Contract Sum prior to this Change Order was.........................................$143,000.00 The Contract Sum will be changed by this Change Order....................................$7,142.00 The new Contract Sum including this Change Order is...................................$150,142.00 The Contract Time will be increased by............................................................44 Days The date of Substantial Completion as of the date of this Change Order is .............. 4/30/12 Detailed description of Change Order and justification: As a result of a designed 3 ton weight limit restriction during bridge repairs, life safety and livelihood concerns were raised by the residents of No Name Key. Additional bridge deck support was required to eliminate the weight restriction. Time, materials and equipment were increased from the original bid amount. The following items are included in this Change Order: Dockage, maintenance of barges and equipment= $2,800.00 Additional jacks = $ 644.00 30 days rental on additional jacks = $2,340.00 14 days rental on existing jacks = $ 1,078.00 Shims =$ 280.00 Net Amount of this Change Order = $7,142.00 This Change Order is less than 5% of the original contract price. CONTRACTOR: oral Marine Construc ion Date ft i ENGINEERING SERVICES DIRECTOR: ' Ju ith S. Clarke, P.E. Date r PUBLIC WORKS & ENGINEERING DIVISION DIRECT _..._ri.: 01 ) vip i son, P Date COUNTY/DEPUTY ADMINISTRA OR: �s ate CORAL MARINE 0ONSTRUCT1, 0H a 10610 7TH AVE GULF, MARATHON, FL 33050 Ph: 305-743-0907 Fax: 305-743-0900 March 8, 2012 CHANGE ORDER REQUEST #1 Project: No Name Key Bridge Repair Monroe County Engineering Department 1100 Simonton Street Key West, FL 33040 1. Request for time extension on above mentioned project due to delay time as a result of weight restriction problems on the bridge. We request original contract be amended to a completion date of April 30, 2012. 2. Due to additional weight restriction compliance as well as a delay in start time we request additional funds to be added to original contract as follows: Dockage, Maintenance of Barges and Equipment 14 Days @ $200.00 $ 2,800.00 Additional Jacks $ 644.00 30 Days Rental on Additional Jacks $ 2,340.00 14 Days Rental on Existing Jacks $ 1,078.00 Shims $ 280.00 Total Additional Funds Requested $ 79142.00 George Steinmetz Coral Marine Construction, LLC