C21 Jacobs Project Management Co.'s Task Order No. 12/15-75 for the Airport Noise
Program Coordinator Services in the amount of$87,714.00.All project cost to he funded with
FAA Grant# 37-61 (10090.
Should you have any questions please feel free to contact me at(305) 292-3550.
cc: County Attorney
Finance
File
KEY WEST MARATHON PLANTATION KEY PK/ROTH BUILDING
500 Whitehead Street 3117 Overseas Highway 88820 Overseas Highway 50 High Point Road
Key West,Florida 33040 Marathon,Florida 33050 Plantation Key,Rorida 33070 Plantation Key,Florida 33070
305-294-4641 305-289-6027 305-852-7145 305-852-7145
MASTER AGREEMENT FOR PROFESSIONAL SERVICES
TASK ORDER FORM
Effective Date Upon execution Task Order No. 12/15-75 .
Client Project No.404-630202-GAKAI65 Engineer Project No. E9Y37975 .
This Task Order is entered into on the effective date noted above pursuant to the "Master
Agreement for Professional Services"between Monroe County,Florida("Client)and JACOBS
PROJECT MANAGEMENT CO. ("Consultant"),dated February 15,2017("Agreement"). The
Agreement is incorporated herein and forms an integral part of this Task Order.
Services Authorized—Airport Noise Program Coordinator Services
Client authorizes Consultant to perform the Services described in Exhibit A attached hereto and
incorporated herein, which Exhibit A is marked with the above noted Task Order No. and
consists of 1 page(s).
Pricing
N/A Time and Expense per Agreement and Appendix B to the Agreement.
X Finn Fixed Price of S 87.714.00 .
N/A Other(Describe): ,9)NRu COUNTY FORM
Schedule
�;. ices may commence on Execution
� � ASSI NTT ATTORNEY
`� -swill cease by 730 days • Date 7/28/20
-� -44
t ;�,
BOARD OF COUNTY COMMISSIONERS _
Ga Mayor/ hai -_ --' 73
CONSULTANT: :-c . = cm-,
JACOBS PROJECT MANAGEMENT CWi N O
<'�% � s w O
i�%/9 // / }Sl co
Witness it CAir CM Services Grow Leader
Date: 7/13/2020
File: MSTR APS—Monroe County
Page 1 of I
EXHIBIT A (12/15-75)
SCOPE OF SERVICES
Airport Noise Program Coordinator Services
Key West International Airport
Monroe County Airports
Jacobs Project Management Company will provide the services as outlined in the Fee Schedule and
Deborah Murphy Lagos &Associates' (DML&A) Scope of Services.
Provide Project Management and Airport Noise Program Coordinator Services required for the Noise
Insulation Program (NIP): Preparation of Final Bid Documents and Bid Process for Key West by the Sea
(KWBTS)Building A,Part 2 and Construction of KWBTS Building A,Part 1.
LIMITED AGENCY—BID &PROCUREMENT SERVICES
If this Agreement authorizes CONSULTANT to perform bid and/or procurement services, the following
terms will apply:
A. CLIENT appoints CONSULTANT as its Agent, and CONSULTANT accepts such appointment to
perform bid/procurement services on CLIENT's behalf in connection with the project.
B. Such services shall be performed under CLIENT's direction and in accordance to such forms,terms and
conditions, or modifications or revisions to same as CLIENT may in its sole discretion at any time instruct
CONSULTANT to use.All services shall be carried out in accordance with the procedures mutually agreed
upon by CLIENT and CONSULTANT.
C. CONSULTANT shall not have authority to accept or bind CLIENT in any way to changes,
modifications, revisions, alterations, amendments, or supplemental, additional, or different terms and
conditions (hereinafter referred to as "deviations") which may be submitted or requested by a vendor or
contractor. CONSULTANT shall immediately submit any deviations from CLIENT's standard terms and
conditions to CLIENT for review by CLIENT's Purchasing Manager or his representative and such
deviations shall not be accepted by CONSULTANT unless CONSULTANT receives express written
approval thereof from CLIENT's Purchasing Manager or his representative.
D. All documents issued by CONSULTANT hereunder shall be signed by CONSULTANT for CLIENT if
so directed. The ownership and title of all items purchased hereunder shall pass directly from the selling
party to CLIENT, and CONSULTANT shall at no time be a party to such transaction other than as agent
of CLIENT. CLIENT shall have the unilateral right to have the commitment authority of CONSULTANT,
its employee or this limited agency authorization in its entirety revoked and cancelled at any time, with or
without cause. CLIENT shall be obligated directly to the selling party for all payments for materials,
equipment, supplies and services procured hereunder.
E. CLIENT shall hold CONSULTANT and its employees harmless from any claims, suits or liabilities
arising out of any breach or other failure of performance by any contractor, vendor or supplier under any
contract or purchase order issued by CONSULTANT hereunder
JACOBS ENGINEERING GROUP JOB HOUR AND FEE ESTIMATE
Monroe County
Airport:
Key West International Airport
Project:
Airport Noise Program Coordinator Services(12/16-76)
FEE SUMMARY
BASIC SERVICES
Hours Fee DBE AMOUNT
Article A: Project Management and Administration $ 2,784
Article B: Noise Compatibility Program Coordinator Services $ 84,930
Total Basic Services Lump Sum Fee $ 87,714 $
TOTAL LUMP SUM PROJECT FEE $ 87,714
DBE Percentage
Page 1 of 3
JACOBS ENGINEERING GROUP JOB HOUR AND FEE ESTIMATE
Monroe County
Airport:
Key West International Airport
Project:
Airport Noise Program Coordinator Services(12115-75)
Article A:Project Management and Administration
Proj. Sr.Proj. Sr. Project Sr.CADD
WORKITEM Director Manager Engineer Engineer Engineer Designer Tech Clerical TOTAL
1 Project Management 4 4
2 Coordination with Subconsultant 4 4
3 Prepare and coordinate subconsultant contracts and 8 8
pay invoices
TOTAL HOURS 0 16 0 0 0 0 0 0 16
RATE $ 200.00 $ 174.00 $ 147.00 $ 121.00 $ 93.00 $ 76.00 $ 101.00 $ 54.00 -----
PAYROLL ESTIMATE $ - $ 2,784 $ - $ - $ - $ - $ - $ - $ 2,784
TOTAL PAYROLL FEE $ 2,784
Subcomultants $ -
TOTAL FEE
Page 2 of 3
JACOBS ENGINEERING GROUP JOB HOUR AND FEE ESTIMATE
Monroe County
4irport:
Key West International Airport
-roject:
Airport Noise Program Coordinator Services(12115-75)
Article B:Noise Compatibility Program Coordinator Services
Proj. Sr.Proj. Sr. Project Sr.CADD
WORKITEM Director Manager Engineer Engineer Engineer Designer I Tech I Clerical TOTAL
1 Project Management S See Deborah Murphy Lagos&Associates,LLC.below.
Review Proposed Acoustical Modifications with
2 Property Owners See Deborah Murphy Lagos&Associates,LLC.below.
3 Prepare Legal Documents See Deborah Murphy Lagos&Associates,LLC.below.
4 Update Bid Documents-KWBTS Building A,Part 1 See Deborah Murphy Lagos&Associates,LLC.below.
5 Bid Process-KWBTS Building A,Part 1 S See Deborah Murphy Lagos&Associates,LLC.below.
Analysis&Modeling of Pre-Construction Acoustical
6 Testing Data See Deborah Murphy Lagos&Associates,LLC.below.
7 Prperty Owner Pre-Construction Tasks See Deborah Murphy Lagos&Associates,LLC.below.
S Contractor Pre-Construction Tasks S See Deborah Murphy Lagos&Associates,LLC.below.
9 Daily Construction Management See Deborah Murphy Lagos&Associates,LLC.below.
10 Post-Construction Noise Testing and Analysis See Deborah Murphy Lagos&Associates,LLC.below.
11 Construction Closeout Tasks 2 See Deborah Murphy Lagos&Associates,LLC.below.
TOTAL HOURS 1 26 01 01 01 01 01 01 Oi
0
RATE 1$ 200.00 1$ 174.00 1$ 147.00 1$ 121.00 1$ 93.00 1$ 76.00 1$ 101.00 1$ 54.00 -----
PAYROLL ESTIMATE 1$ 5,200 1$ -I$ -I$ -I$ -I$ -I$ -I$ - $ 5,200
Task Sub-Consultants TOTAL PAYROLL FEE $ 5,200
Deborah Murphy Lagos&Associates,LLC Services $ 79,730 Subconsultants $ 79,730
$ 79,730
3 of 3
Key West International Airport
Noise Compatibility Program
2020-21 Scope of Work
Noise Compatibility Program Coordinator
Deborah Murphy Lagos & Associates (DML&A) will perform the following tasks, at the
direction of and on behalf of the Monroe County Director of Airports.
Task 1 Project Management
Task 2 Review Proposed Acoustical Modifications with Property Owners
Task 3 Prepare Legal Documents
Task 4 Update Bid Documents - KWBTS Building A, Part 2
Task 5 Bid Process - KWBTS Building A, Part 2
Task 6 Analysis & Modeling of Pre-Construction Acoustical Testing Data
Task 7 Property Owner Pre-Construction Tasks
Task 8 Contractor Pre-Construction Tasks
Task 9 Daily Construction Management
Task 10 Post-Construction Noise Testing and Analysis
Task 11 Construction Closeout
TASK 1 PROJECT MANAGEMENT
October 1, 2020- September 30, 2021
Host Coordination / Progress Conference Calls - On behalf of the Monroe County Director
of Airports, DML&A will host and lead periodic conference calls for the project team (i.e.,
THC and their sub-consultants). DML&A will provide the team with the call-in number and
conference code, and will dial-in as the leader. The duration of each call will be
approximately 60 minutes. The FAA ADO will be invited to participate in these calls.
Attend KWIA Ad-Hoc Committee Meetings As directed by Monroe County's Director of
Airports, DML&A will prepare agenda packages for distribution in advance of meetings,
coordinate with airport staff regarding placement of newspaper advertisements for upcoming
meetings, attend meetings to present information on the status of the project, and prepare
meeting minutes. The FAA ADO will be invited to attend these meetings. The Ad-Hoc
Committee typically meets four times per year(e.g., October, December 2020, March, June,
2021).
Conduct KWBTS NIP Meetings
The NIP Program Manager will schedule and conduct nine (9) NIP Meetings for all KWBTS
property owners to present information on the status of the project.
On behalf of the Monroe County Director of Airports, DML&A will attend the NIP Meetings.
Four (4) of the meetings will be scheduled to coincide with Ad-Hoc Committee Meeting
dates.
Brief Director of Airports
While in Key West for the Ad-Hoc Committee Meetings and KWBTS NIP Meetings, DML&A
will brief the Director of Airports on the status of the project.
2020-21 SOW, NCP Coordinator Page 2 of 13
Daily Communication with Property Owners and Others
The NIP Program Managerwill be responsible for general communication requirements with
NIP participating property owners, City of Key West, Monroe County, FAA, product
manufacturers and general contractors.
On behalf of the Monroe County Director of Airports, DML&A will review draft written
communication as appropriate and provide comments to the NIP Program Manager.
Develop Scopes of Work — DML&A will provide support to Monroe County and Jacobs
Engineering by assisting in the development of the Scope of Work and reviewing the
proposed budget for the NIP Program Manager (THC, Inc.). DML&A will assist Jacobs
Engineering in obtaining the Independent Fee Estimate (IFE) for THC's Scope of Work. If
necessary, DML&A will attend a meeting with the FAA and THC in Orlando to discuss the
Scope of Work for implementation of the NIP. DML&A will also prepare the Scope of Work
and budget for the Noise Compatibility Program Coordinator.
Assist with Grant Application Process — DML&A will provide support to Monroe County and
Jacobs Engineering in the preparation of grant applications to the FAA for implementation
of the Noise Insulation Program, Avigation Easement Acquisition Program, and other AIP-
eligible measures that were approved by the FAA in the NCP ROA. In consort with Monroe
County, DML&A will coordinate with the FAA during the grant application review process to
address any questions that may arise during the FAA review and approval process. DML&A
will communicate with the FAA to ensure that all required documentation is provided.
Revise Information for JACIP — DML&A will provide support to Monroe County and Jacobs
Engineering by preparing revised project descriptions and dollar amounts for the JACIP,
based on updated cost estimates provided by the NIP Program Manager as well as PFC
funding availability projections provided by Monroe County.
Provide Information to the Public — At the direction of Monroe County, DML&A will provide
information to the public regarding the NCP, on behalf of the County, throughout the duration
of the NCP implementation. DML&A will answer telephone inquiries, meet with property
owners, and mail informational materials to interested residents. DML&A will provide
information to Monroe County for posting on the Ad-Hoc Committee and Key West
International Airport websites.
Maintain Database of Potentially-Eligible Properties — DML&A will prepare and maintain a
database of properties that are potentially eligible for participation in the NIP / Avigation
Easement Acquisition Program. The database will include information such as: property
address, current owner(s), owner's address (if different from property address), year of
construction, size, type, number of bedrooms and bathrooms, roof type, roof cover,
foundation, exterior walls, type of HVAC, total building value, total improvement value, total
land value, total just market value, and total assessed value. This information will be
obtained from the Monroe County Property Appraiser's on-line database.
Prepare Project Invoicing — DML&A will prepare monthly invoices to Jacobs Engineering, as
required to manage the project.
2020-21 SOW, NCP Coordinator Page 3 of 13
Close Out Project — DML&A will provide support to Monroe County during close-out of the
FY'20 grant. DML&A will collect documentation from the NIP Program Manager that will be
required for grant close-out, and provide it to Jacobs Engineering. DML&A will communicate
with Jacobs Engineering to ensure that all required documentation is provided.
TASK 2 REVIEW PROPOSED ACOUSTICAL MODIFICATIONS WITH PROPERTY
OWNERS
In preparation for the bid of Building A, Part 2 (30 units), the NIP Program Manager will be
required to complete the individual 60-minute Review Meetings for each of the 30 Building
A, Part 2 Property Owners. In this task, the NIP Program Manager will mail proposed NIP
design documents to each of the 30 individual property owners and provide a written
summary of the tasks that will be completed at each individual Review Meeting. The NIP
Program Manager will schedule 90-minute appointments for each of the 30 Property Owners
and will provide an appointment reminder. At the scheduled Review Meeting, the NIP
Program Manager (Project Manager, Assistant Project Manager, Architect, and Engineer)
will provide a complete review of the proposed NIP design documents, make revisions based
on comments from Property Owners, make product selections and manage the signing of
all NIP legal documents. After the Review Meeting, the NIP Program Manager (Architect,
Engineer) will make final revisions to the design documents based on comments received
from the Property Owners during the meetings.
On behalf of the Monroe County Director of Airports, DML&A will attend the Review Meetings
and assist with the legal documents.
TASK 3 PREPARE LEGAL DOCUMENTS
In preparation for the bid of Building A, Part 2 (30 units), the NIP Program Manager will
prepare, distribute, collect, process, and file all required NIP legal documents for 30
individual properties to include-
- Property Owner Agreement
- Avigation Easement
- Notice of Commencement
- Subordination of Mortgage
- EPA Lead Paint Acknowledgement
- Property Owner Verification of Completed Work
- Hard-Wired Smoke Alarm Installation Confirmation
- Designated Furniture Storage Space Sketch
On behalf of the Monroe County Director of Airports, DML&A will review draft legal
documents as appropriate and provide comments to the NIP Program Manager.
2020-21 SOW, NCP Coordinator Page 4 of 13
TASK 4 UPDATE BID DOCUMENTS — KWBTS BUILDING A, PART 2
In preparation for the bid of KWBTS Building A, Part 2, the NIP Program Manager will be
required to complete several tasks:
Conduct NIP Orientation for all 30 Building A, Part 2 Property Owners
The NIP Program Managerwill prepare a NIP Orientation Presentation for all 30 participating
Building A, Part 2 Property Owners, which will provide an overview of the proposed Building
A, Part 2 scope of work, property owner requirements, design revisions and NIP policy
revisions. The NIP Program Manager will then schedule and conduct multiple NIP
Orientation Sessions during a 4-day period for all 30 property owners.
On behalf of the Monroe County Director of Airports, DML&A will attend the NIP Orientations.
Update Bidding Documents (Project Manual Volume 1 of 3)
The NIP Program Managerwill review and update the Bidding Documents developed for the
KWBTS Building A, Part 1 project (28 units) and incorporate changes based on the previous
KWBTS bid and construction experience (e.g., contractor minimum qualification
requirements, Unit Prices, Special Provisions). The Bidding Documents for KWBTS Building
A, Part 2 will meet all FAA requirements and the requirements of the local authorities and
will contain all information necessary for the formal bid process, including Bidding
Requirements and Contract Forms. Volume 1 will be approximately 240 pages printed on
8'/2"x11" paper.
On behalf of the Monroe County Director of Airports, DML&A will review the Bidding
Documents and provide comments to the NIP Program Manager.
Update Technical Specifications (Project Manual Volume 2 of 3)
The NIP Program Manager will review and update the Technical Specifications developed
for the Building A, Part 1 project (28 units) and incorporate changes that reflect KWBTS
Building A, Part 2 construction (e.g., contractor minimum requirements, construction
scheduling, construction staging requirements, construction safety plan, construction
manager staffing plan). Volume 2 will be approximately 290 pages printed on 8'/2"x11" paper.
On behalf of the Monroe County Director of Airports, DML&A will review the Technical
Specifications and provide comments to the NIP Program Manager.
Update Asbestos Remediation Specifications (Project Manual Volume 3 of 3) - Based on
previous laboratory test results for the 30 Building A, Part 2 condominiums, the NIP Program
Manager will review and update the Asbestos & Lead Based Paint Inspection Reports and
Asbestos Remediation Specifications, and provide a summary of laboratory testing of the
Building A, Part 2 asbestos sampling process, analysis of laboratory findings, respond to
RFIs from bidding contractors, provide required asbestos abatement procedures for worker
safety in condominiums that showed <1% level of asbestos containing materials (ACM),
develop required ACM abatement plan (only if required) and determine required on-site
inspection during the Building A, Part 1 construction. Volume 3 will be approximately 1,500
pages printed on 8'/2"x11" paper.
2020-21 SOW, NCP Coordinator Page 5 of 13
On behalf of the Monroe County Director of Airports, DML&A will review the Asbestos &
Lead-Based Paint Inspection Reports and Asbestos Remediation Specifications and provide
comments to the NIP Program Manager.
Revise Construction Drawings (Volume 1 of 1) —Using the final Acoustical Modification
Packages forthe 30 KWBTS Building A, Part 2 Units, the NIP Program Managerwill prepare
the Construction Drawings for the KWBTS Building A, Part 2 Bid Package and develop a
revised estimate of anticipate construction costs. The Construction Drawings will be
approximately 235 pages printed on 11"x17" paper.
On behalf of the Monroe County Director of Airports, DML&A will review the Construction
Drawings and provide comments to the NIP Program Manager.
TASK 5 BID PROCESS — KWBTS BUILDING A, PART 2
The bid process for KWBTS Building A, Part 2 will require that the NIP Program Manager
complete several tasks to include:
Prepare Bid Advertisement
After conducting outreach for Contractors who may be interested in bidding the project, the
NIP Program Manager will develop a bid advertisement notice for the Construction of
KWBTS Building A, Part 2 and provide it to Monroe County Attorney's Office for advertising.
On behalf of the Monroe County Director of Airports, DML&A will review the draft Bid
Advertisement and provide comments to the NIP Program Manager.
Contractor Request for Information
During the bid process, Monroe County will be responsible for all communication from
contractors who are interested in bidding the project. The NIP Program Manager will assist
Monroe County as requested. The NIP Program Manager will provide answers to bidder's
questions pertaining to the project relating to the design documents, schedule, specification
and/or contractor requirements.
On behalf of the Monroe County Director of Airports, DML&A will provide answers to
questions pertaining to the project relating to the Noise Compatibility Program.
Conduct Pre-Bid Meeting
Consistent with the formal bid advertisement, the NIP Program Manager will schedule and
conduct a mandatory pre-bid meeting in Key West for contractors who are interested in
bidding the project. At the pre-bid meeting, the NIP Program Manager will review all aspects
of the project including contractor minimum experience requirements, design documents,
safety plan, unit prices, contractor deficiency point system, construction scheduling, and
contractor expectations.
On behalf of the Monroe County Director of Airports, DML&A will attend the Pre-Bid Meeting.
2020-21 SOW, NCP Coordinator Page 6 of 13
Attend Bid Opening
The NIP Program Manager will coordinate with the Key West International Airport and
Monroe County to be available at the bid opening, as described in the bid advertisement.
DML&A will not participate in this task.
Review Bids and Prepare Award Recommendation
Upon the opening of the bids, the NIP Program Manager will conduct a detailed review of all
contractor bids received. After this review, the NIP Program Manager will provide an official
letter of contract award recommendation to Key West International Airport and Monroe
County, to the lowest, most responsive and most responsible bidder.
On behalf of the Monroe County Director of Airports, DML&A will review the bids, and
coordinate with the NIP Program Manager regarding recommendation for award.
Coordinate Contract Award
The NIP Program Manager will coordinate with the recommended General Contractor (GC)
to make sure the GC submits their completed contract documents to Monroe County
Department of Airports in a timely manner, such that the Board of County Commissioners
(BOCC) can schedule the award of contract on the same monthly agenda as acceptance of
the FAA grant.
On behalf of the Monroe County Director of Airports, DML&A will assist the NIP Program
Manager to obtain BOCC approval of contract award and grant acceptance.
TASK 6 ANALYSIS & MODELING OF PRE-CONSTRUCTION ACOUSTICAL
TESTING DATA
The NIP Program Manager will complete the following tasks for KWBTS Building A, Part 2:
Data Analysis of the Pre-Construction Noise Measurements—The Consultant will first review
the previously completed pre-noise testing performed in 2017 in seven (7) Building A
condominium units (floors 1, 2, 3—entire building). Since the KWBTS Building A will be divided
into multiple projects, the Consultant will be required to perform pre-noise testing on an
additional seven (7) condominium units on the portion of the building that contains the 30 units
included in Building A — Part 2 to determine the measured NLR and interior DNL in each unit
prior to the addition of NIP acoustic modifications. In addition, to ensure conformance with FAA
guidelines, the Consultant will model the anticipated noise reduction in several representative
Building A condominiums to ensure that a minimum five (5) dB NLR will be achieved by the
proposed NIP design modifications. After the completion of this process, the Consultant will
prepare a technical memorandum summarizing the measured NLRs, interior DNLs, and
anticipated modeled results. Throughout the project, the Consultant will provide acoustical
support and handle acoustical questions or evaluate specific product alternatives as
necessary for the design on Building A — Part 2.
On behalf of the Monroe County Director of Airports, DML&A will review the technical
memorandum.
2020-21 SOW, NCP Coordinator Page 7 of 13
TASK 7 PROPERTY OWNER PRE-CONSTRUCTION TASKS
In preparation for the Construction of 28 properties in KWBTS Building A, Part 1, the NIP
Program Manager will be required to complete several Property Owner Pre-Construction
Tasks during a four (4) month period to include:
Conduct NIP Construction Orientation Sessions
The NIP Program Manager will prepare a NIP Construction Orientation Presentation for the
28 participating property owners and their tenants which will provide a complete review of
all NIP construction processes and procedures, anticipated schedules, safety requirements
and property owner responsibilities during the 10-month construction process. The NIP
Program Manager will then schedule and conduct multiple NIP Construction Orientation
Sessions during a 1-day period for all 28 participating property owners
On behalf of the Monroe County Director of Airports, DML&A will attend the NIP Construction
Orientation Sessions.
Prepare Designated Storage Space Sketches for all 28 Building A, Part 1 Condominiums
All 28 Building A, Part 1 condominium floor plans are completely different, including the types
and amounts of existing furniture. The Property Owner is responsible for removing all
excessive furniture and moving all remaining furniture to limited designated spaces within
each room of the condominium prior to start of their NIP construction. To assist the Property
Owner in the process to ensure they properly complete this task, the NIP Program Manager
will develop a unique Designated Storage Space Sketch for each of the 28 condominiums
which reflects the available spaces in all condominium rooms that will be available for
furniture storage, based on their unique proposed NIP scope of work. This scaled drawing
will also show the "clear areas" required for the contractor to perform their NIP work.
DML&A will not participate in this task.
Conduct Storage Space Site Visits at all 28 Condominiums
The NIP Program Manager will schedule and conduct a 15-minute visit at each of the 28
Building A, Part 1 condominiums to assess their existing furniture and assist the Property
Owner in the determination of"excessive" furniture that will be required to be removed from
their condominium prior to the start of NIP construction. In addition, the NIP Program
Manager will review their unique Designated Storage Space Sketch with the Property Owner
and communicate helpful tips to help simplify this process. During this site visit, the NIP
Program Manager will also provide a review of all property owner furniture moving
responsibilities including the required poly protection procedures for all stored furniture,
bathroom doors and closet doors.
DML&A will not participate in this task.
2020-21 SOW, NCP Coordinator Page 8 of 13
TASK 8 CONTRACTOR PRE-CONSTRUCTION TASKS
In preparation for the Construction of 28 properties in KWBTS Building A, Part 1, the NIP
Program Manager will be required to complete several Contractor Pre-Construction Tasks
during a four (4) month period to include:
Review Contractor Criminal Background Reports
After submission by the awarded contractor, the NIP Program Manager will review and
approve all Criminal background reports for all Contractor staff to include employees, 1099
workers, subcontractors and suppliers.
DML&A will not participate in this task.
Review Contractor 12-Panel Drug Testing Reports
After submission by the awarded contractor, the NIP Program Manager will review and
approve all 12-Panel Drug Testing reports for all Contractor staff to include employees, 1099
workers, subcontractors and suppliers.
DML&A will not participate in this task.
Develop and Issue ID Badging for all Contractor Staff
After successful review and approval of Criminal Background and 12-Panel Drug Test
Reports, the NIP Program Manager will create and issue NIP Construction site ID badges
for all Contractor staff to include employees, 1099 workers, subcontractors and suppliers.
DML&A will not participate in this task.
Review Contractor Submittals
The NIP Program Manager will review all Contractor Submittals for windows, prime entry
doors, sliding patio doors, electrical equipment, mechanical equipment, construction
materials, scaffolding, and vertical lifts.
DML&A will not participate in this task.
Conduct Final Measurement Walk-Through Inspections — The NIP Program Manager will
conduct Final Measurement Walk-Through Inspections with the Contractor and Product
Manufacturers in all 28 participating condominiums. This 30-minute visit at each
condominium will include final measurements of all windows and doors, review of ERV &
ductless AC installation process, review of asbestos abatement containment and staging
plan, verification of property owner "pre-work" requirements and verification of finishes,
colors and styles.
DML&A will participate in this task to the extent that it occurs during the trip for the Pre-
Construction Conference.
Conduct Pre-Construction Conference — The NIP Program Manager will schedule and
conduct a Pre-Construction Conference with the Contractor, subcontractors, and suppliers
to review the NIP KWBTS construction of 28 properties, discussing contractor requirements,
sequencing plans, construction schedule, asbestos abatement plan, safety requirements
2020-21 SOW, NCP Coordinator Page 9 of 13
and construction staging plans. In addition, the Pre-Construction Conference will include
project goals, property owner communication plan, review of acoustic scope of work,
submittal requirements, scheduling and phasing of trades, workmanship requirements,
progress payments, unit prices, and final closeout documentation requirements
On behalf of the Monroe County Director of Airports, DML&A will attend the Pre-Construction
Conference.
Perform Review and Approval of Contractor Final Construction Schedule—The NIP Program
Manager will review and approve the Contractor's final proposed construction schedule for
NIP KWBTS Building A, Part 1.
On behalf of the Monroe County Director of Airports, DML&A will review the Contractor's
proposed construction schedule and provide comments to the NIP Program Manager.
Conduct Product Inspections
The NIP Program Manager will conduct inspections of all windows and door products to
ensure compliance with specification requirements.
DML&A will not participate in this task.
Conduct Lift Inspections
The NIP Program Manager will conduct inspections of all proposed lift sites to ensure
compliance with specification requirements.
DML&A will not participate in this task.
Review Contractor Deficiency Point System — The NIP Program Manager will develop a
Contractor Deficiency Notice that will define the construction site deficiency areas that could
be utilized by the Construction Manager if contractor performance failures occur during the
construction period. Areas of contractor deficiency will include failure relating to: project
specifications, window / door installations, contract completion time requirements, worker
safety and project safety plan, property owner communication, and/or subcontractor
payments. Each specified deficiency area will be assigned points which, when tallied, could
lead to disqualification to participate in future NIP construction projects.
On behalf of the Monroe County Director of Airports, DML&A will review the Contractor
Deficiency Notice and provide comments to the NIP Program Manager.
City of Key West Permitting Process
The NIP Program Manager will provide to the Contractor, two sets of signed and sealed final
design drawings of each of the 28 KWBTS Building A, Part 1 condominium units to assist in
obtaining a building permit from the City of Key West Building Department. The NIP Program
Manager will respond in writing to any comments issued by the City of Key West Building
Department during its plan review.
On behalf of the Monroe County Director of Airports, DML&A will coordinate with the NIP
Program Manager regarding comments from the City of Key West Building Department.
2020-21 SOW, NCP Coordinator Page 10 of 13
TASK 9 DAILY CONSTRUCTION MANAGEMENT TASKS
The NIP Program Manager will perform all daily construction management tasks during a
five (5) month construction period for the 28 Building A, Part 1 condominiums. These tasks
will include the following:
Perform Daily Site Visits — The NIP Program Manager will provide daily construction
observation services and conduct field inspections to help ensure quality control. The NIP
Program Manager will utilize the Project Architect to assist in the administration and
completion of all necessary change orders, review and approval of shop drawings, and
review and approval of materials and products. Daily site visit tasks include review and
processing of all submittals and shop drawings, review materials before they are installed to
ensure that they comply with the approved submittals, review work covered by shop
drawings to ensure that it complies with the Contract Documents, coordinate with the
Contractors to insure that all appropriate building permits have been secured, observe the
work in progress to verify that it meets the requirements and intent of the Contract
Documents, issuance of Deficiency Points, review all work to ensure all safety practices are
in place and ensure that the Contractor is adhering to the written safety plan.
DML&A will not participate in this task.
Conduct Weekly Progress Meetings with Contractor—The NIP Program Manager will attend,
conduct and document weekly construction progress meetings with the Contractors and
Subcontractors. These meetings will help to notify the General Contractor of any part of the
work in progress that does not conform to approved submittals, shop drawings, or Contract
Documents, review and evaluate any Contractor's suggestions for modifications to the
Contract Documents, review Contractor's RFIs and change order requests and update
issued Deficiency Points.
On behalf of the Monroe County Director of Airports, DML&A will participate in weekly
progress meeting via teleconference.
Provide Proper Property Owner Communication — The NIP Program Manager will provide
all required daily communication as required with the 28 participating property owners with
respect to schedules, work progress, and the scheduling of substantial and final inspections.
DML&A will not participate in this task.
Coordinate with NIP Design Team to Develop Solutions to Unforeseen Conditions
The NIP Program Manager will coordinate with the NIP Design Team to develop solutions
to unforeseen conditions that may arise with window & door openings, ceiling obstructions,
electrical revisions and mechanical revisions.
On behalf of the Monroe County Director of Airports, DML&A will participate in the
coordination effort.
2020-21 SOW, NCP Coordinator Page 11 of 13
Coordination and Safety Escorting Non-Participating Property Owners on Each Building A
Floor
The NIP Program Manager will coordinate the construction schedules for each non-
participating Building A Property Owners to ensure they are aware of construction activity.
In addition, The NIP Program Manager will act as a safety escort for all non-participating
Property Owner when the construction activity on each of the floors impedes with their ability
to access their condominium.
DML&A will not participate in this task.
Monitor Adherence to Construction Safety & Phasing Plan
The NIP Program Manager will review and monitor the Contractor's assigned safety
procedures (as determined by the Contractor's assigned Construction Safety Manager) on
a daily basis to ensure conformance with the approved Construction Safety & Phasing Plan.
DML&A will not participate in this task.
Maintain Construction Files
The NIP Program Manager will establish and maintain files and records of all pertinent
documents including submittals, shop drawings, addenda, meeting minutes and reports.
DML&A will not participate in this task.
Contractor Payment Review and Processing — The NIP Program Manager will perform
general project-related coordination with the preparation of monthly invoices and progress
reports and schedule updates. The NIP Program Manager will review applications for
payments from the General Contractor to ensure that they agree with the work done and
materials received.
On behalf of the Monroe County Director of Airports, DML&A will review all applications for
payments from the General Contractor and make recommendations to the Director of
Airports.
Conduct Substantial Completion Inspections — The NIP Program Manager will conduct
Substantial Completion Inspections at all condominiums and will prepare punch lists at the
appropriate time for each property. The NIP Program Manager will distribute the punch lists
to the General Contractor for execution, verify that punch list items are complete, and then
verify the General Contractor's final invoice for payment.
On behalf of the Monroe County Director of Airports, DML&A will participate in some
Substantial Completion Inspections, if they occur during another scheduled trip.
Conduct Completion Inspections—The NIP Program Managerwill conduct Final Inspections
upon completion of all outstanding punch list items for a condominium or single-family home.
The NIP Program Manager will also verify that all items identified on the punch list have
been addressed, that all work has been performed in accordance with the Contract
Documents and Specifications, and that the work meets project standards for workmanship
and quality.
2020-21 SOW, NCP Coordinator Page 12 of 13
On behalf of the Monroe County Director of Airports, DML&A will participate in some Final
Inspections, if they occur during another scheduled trip.
Administration of Construction Documents
The NIP Program Managerwill be responsible for the weekly preparation and administration
of all construction documents to include daily site reports, photographs, change orders,
contractor invoices, punch-lists, substantial completion certificates and final completion
certificates.
On behalf of the Monroe County Director of Airports, DML&A will review construction
documents
TASK 10 POST-CONSTRUCTION NOISE TESTING AND ANALYSIS
Post-Construction Acoustical Testing of Building A, Part 1 Condominium Units
The NIP Program Manager previously performed pre-construction acoustical testing on
approximately 10% of all KWBTS condominiums in 3 Buildings (A, B, C) to measure the noise
level reduction (NLR) in representative rooms.
Upon completion of the NIP KWBTS Building A, Part 1 Construction, the NIP Program
Manager will conduct post-modification acoustical tests in seven (7) condominium units in
Building A, Part 1 (units where pre-modification acoustical testing was accomplished). The
NIP Program Manager will perform post-construction acoustical testing on the units to
measure the noise level reduction (NLR) in representative rooms. The post-modification
acoustical measurements will be used to verify the noise level reduction achieved by the
acoustical modifications. Pre-modification data will be compared with post-modification
measurements to document the achieved increase in noise reduction, and as a check on
quality control. This data will assist the NIP Program Manager in assuring that the acoustic
modification treatments provide a minimum 5-decibel reduction. The noise level reduction
(NLR) measurements essentially consist of placing a loudspeaker outside each
condominium unit that will be measured. The electrical signal of an artificial noise source is
fed through the amplification/loudspeaker system and is filtered to simulate aircraft noise.
The technician will measure the average interior sound level within the room and the sound
level directly outside each exterior element (i.e., doors, windows, and walls). An overall NLR
will be mathematically computed based on the measured test data and the acoustical
conditions of each room. All tests will be conducted in accordance with ASTM Designation
E966 "Standard Guide for Field Measurement of Airborne Sound Insulation of Building
Fagades and Fagade Elements. This task also requires the communication and scheduling of
all acoustical testing appointments with all associated KWBTS Building A, Part 1 property
owners.
On behalf of the Monroe County Director of Airports, DML&A will attend post-construction
noise testing, and review the results of the analysis.
2020-21 SOW, NCP Coordinator Page 13 of 13
TASK 11 CONSTRUCTION CLOSEOUT
The NIP Program Manager will provide KWBTS Building A, Part 1 construction close-out
tasks to include:
Final Assessment of Building A, Part 1 Construction Process
The THC Construction Manager will prepare a full technical assessment of performance and
achievements, including the adequacy of technical specifications, required specification
revisions, construction process evaluation of sequencing and methodology, evaluation of
the predicted versus the actual costs for modifications, change orders, contract schedule
compliance and full cost accounting including bid cost and Unit Price request evaluation.
On behalf of the Monroe County Director of Airports, DML&A will participate in the
assessment of the construction process.
Key West International Airport
Noise Compatibility Program
2020-21 Scope of Work
Airport Noise Program Coordinator
Deborah Lagos $170
TASK 1-PROJECT MANAGEMENT
Host Coordination/Progress Conference Calls 24 $4,080
Attend KWIA Ad-Hoc Committee Meetings 0 $0
Conduct KWBTS NIP Meetings 90 $15,300
Brief Director of Airports 18 $3,060
Daily Communication with Property Owners and Others 8 $1,360
Develop Scopes of Work 12 $2,040
Assist with Grant Application Process 16 $2,720
Revise Information for JACIP 6 $1,020
Provide Information to the Public 12 $2,040
Maintain Database of Potentially-Eligible Properties 12 $2,040
Prepare Project Invoicing 12 $2,040
Close Out Project 8 $1,360
SUBTOTAL-TASK1 218 $37,060
TASK 2-REVIEW PROPOSED ACOUSTICAL MODIFICATIONS WITH PROPERTY OWNERS
Attend Review Meetings and Assist with Legal Documents 40 $6,800
SUBTOTAL-TASK2 40 $6,800
TASK 3-PREPARE LEGAL DOCUMENTS
Review Legal Documents 8 $1,360
SUBTOTAL-TASK3 8 $1,360
TASK 4-UPDATE BID DOCUMENTS--KWBTS BUILDING A
Conduct NIP Orientation Sessions for all 21 Building A Property Owners 32 $5,440
Update Bidding Documents(Project Manual Volume 1 of 3) 12 $2,040
Update Technical Specifications(Project Manual Volume 2 of 3) 8 $1,360
Update Asbestos Specifications(Project Manual Volume 3 of 3) 4 $680
Revise Construction Drawings(Volume 1 of 1) 4 $680
SUBTOTAL-TASK 4 60 $10,200
TASK 5-BID PROCESS-KWBTS BUILDING A
Prepare Bid Advertisement 1 $170
Contractor Request for Information 1 $170
Conduct Pre-Bid Meeting 14 $2,380
Attend Bid Opening 0 $0
Review Bids and Prepare Award Recommendation 8 $1,360
Coordinate Contract Award 6 $1,020
SUBTOTAL-TASKS 30 $5,100
TASK 6-ANALYSIS&MODELING OF PRE-CONSTRUCTION ACOUSTICAL TESTING DATA
Review Technical Memorandum 2 $340
SUBTOTAL-TASK6 2 $340
TASK 7-PROPERTY OWNER PRE-CONSTRUCTION TASKS
Conduct NIP Construction Orientation Sessions 24 $4,080
Prepare Designated Storage Space Sketches 0 $0
Conduct Storage Space Site Visits 0 $0
SUBTOTAL-TASK 7 24 $4,080
TASK 8-CONTRACTOR PRE-CONSTRUCTION TASKS
Review Contractor Criminal Background Reports 0 $0
Review Contractor Drug Testing Reports 0 $0
Develop and Issue ID Badging 0 $0
Review Contractor Submittals 0 $0
Conduct Final Measurement Walk-Through Inspections 12 $2,040
Conduct Pre-Construction Conference 4 $680
Perform Review of Contractor Final Construction Schedule 1 $170
Conduct Product Inspections 0 $0
Conduct Lift Inspections 0 $0
Review Contractor Deficiency Point System 0 $0
City of Key West Permitting Process 1 $170
SUBTOTAL-TASKS 18 $3,060
TASK 9-DAILY CONSTRUCTION MANAGEMENT TASKS
Perform Daily Site Visits 0 $0
Conduct Weekly Progress Meetings with Contractor 20 $3,400
Provide Proper Property Owner Communication 0 $0
Coordinate with NIP Design Team to Develop Solutions to Unforeseen Conditions 6 $1,020
Coordination and Safety Escorting Non-Participating Property Owners in Building B 0 $0
Monitor Adherence to Construction Safety&Phasing Plan 0 $0
Maintain Construction Files 0 $0
Contractor Payment Review and Processing 8 $1,360
Conduct Substantial Completion Inspections 0 $0
Conduct Final Completion Inspections 8 $1,360
Administration of Construction Documents 8 $1,360
SUBTOTAL-TASK 9 50 $8,500
TASK 10-POST-CONSTRUCTION NOISE TESTING AND ANALYSIS
Post-Modification Noise Testing of Building B Condominium Units 16 $2,720
SUBTOTAL-TASK10 16 $2,720
TASK 11-CONSTRUCTION CLOSEOUT TASKS
Final Assessment of Construction Process 3 $510
SUBTOTAL-TASK11 3 $510
TOTALS 469 $79,730