1st Change Order 08/20/2020 MONROE COUNTY DEPARTMENT OF AIRPORTS CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 001 Baggage Conveyor System Upgrade Key West International Airport INITIATION DATE: 8/20/2020 TO CONTRACTOR: G&S Mechanical USA CONTRACT DATE:7/17/2019 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price)...........................$1,412,686 Net change by previously authorized Change Orders.................................. The (Contract Sum)(Guaranteed Maximum Price) prior to this Change order was..$1,412,686 The(Contract Sum)(Guaranteed Maximum Price)will be(increased) (decreased) (unchanged) by this Change Order.......n1a The new(Contract Sum) (Guaranteed Maximum Price) including this Change Order is$1,412,686 The Contract Time will be(increased) (decreased) (unchanged) by...increased by .....76 days The date of Substantial Completion as of the date of this Change Order is...08109/2020............. Detailed description of change order and justification: Reguest to add 75 days to contract, to provide time needed to complete contract. resulting from delays caused by obtaining TSA accegtance to conceptual design and covid-19 related supply chain disruptions. In addition, this time is requested to allow G&S tiMe to c9mplete, submit final turn over,manuals andissue remaining DaV aDDlications for this deliverable and previous Day aDDlication retention. This change Order is 0%of the original contract price. ........ Not vali until i r r iec I lic lend Contractor ARCHITECT: Date CONTRACTOR: 09/23/2020 " t p4l Dae 10/2/20 DIRECTOR OF AIRPORTS: Date Ad"Ak—W ftMAWW1&r"AdWf*�—V Roman Gastes• A'g'qw'Sus ASST./COUNTY ADMINISTRATOR: IOrNROE !�MNKY A "0 ,ZAOV' FOW P ASST, NTWY ATMRNEY Date_—JQL1aL_ Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ❑ No ❑ This question is not applicable. The scope of work and supply is not changing. This change order is seeking a time extension only, to allow for final deliverables to be completed and final pay application to be accepted. • Change Order was included in the original specifications. Yes ❑ No ❑ This question is not applicable. The scope of work and supply is not changing. This change order is seeking a time extension only, to allow for final deliverables to be completed and final pay application to be accepted. • Change Order exceeds$25,000 or 5% of contract price(whichever is greater). Yes ❑ No No change to contract price. • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: