Item U11 County of Monroe - BOARD OF COUNTS COMMISSIONERS
Mayor Heather Carruthers District 3
The FloridaKe s Mayor Pro T mMichelleColduoo,District2
Y Craig Cates District l
David Rice.District 4
Sylvia J.Murphy,District 5
County Commission Meeting
November 17, 2020
Agenda Item Summary #7606
firm u-11
BULK ITEM: Yes DEPARTMENT: Project Management
TIME APPROXIMATE: STAFF CONTACT: Kevin Wilson (305) 292-4441
n/a
AGENDA ITEM WORDING: Waiver of purchasing policy and approval of emergency purchase
with Schneider Electric Engineering Services, LLC for the Demand Load Metering Analysis at the
Monroe County Detention Center on Stock Island.
ITEM BACKGROUND: In April 2020 there was an electrical fire at the Monroe County
Detention Center which required the full-time use of the backup geherators until emergency
electrical repairs could be completed. While the existing generators and generator system were in
use, multiple failures occurred which could be due to multiple reasons included incorrect sizing. The
existing generator system is over 20 years old and in need of upgrades and/or replacement. This
purchase with Schneider Electric will provide the County with an in-depth study of the entire
building to determine the appropriate size of generators needed. Staff is requesting the waiver of the
requirement to obtain three quotes for the work, in light of the urgent need for the work as well as
the fact that Schneider Electric is already doing other work on site.
PREVIOUS RELEVANT BOCC ACTION:
4/30/20 — BOCC approved waiver of purchasing policy and ratification of emergency contract with
Nearshore Electric, Inc for the replacement of the entrance busway at MCDC.
4/30/20 — BOCC approved waiver of purchasing policy and ratification of emergency contract with
Schneider Electric USA, Inc. for replacement of the electric switchgear at MCDC.
6/17/20 — BOCC approved a Task Order with T. Y. Lin International for Engineering Design
Services for the generator replacement.
CONTRACT/AGREEMENT CHANGES:n/a
STAFF RECOMMENDATION: Approval of purchase with Schneider Electric.
DOCUMENTATION:
Proposal_Schneider Elec_Demand Load Analysis
Memo_Emergency Analysis with Schneider_signed
FINANCIAL IMPACT:
Effective Date: 11/17/20
Expiration Date: upon completion
Total Dollar Value of Contract: $40,220.00
Total Cost to County: $40,220.00
Current Year Portion: $40,220.00
Budgeted: Yes
Source of Funds: 101-20505
CPI: N/A
Indirect Costs: staff time
Estimated Ongoing Costs Not Included in above dollar amounts:
Revenue Producing: No If yes, amount:
Grant: n/a
County Match: n/a
Insurance Required: Yes
Additional Details: N/A
20505
11/17/20 101-20505 • CORRECTION FACILITIES $40,220.00
REVIEWED BY:
Cary Knight Completed 11/16/2020 2:50 PM
Kevin Wilson Completed 11/16/2020 2:54 PM
Cynthia Hall Completed 11/16/2020 3:05 PM
Purchasing Completed 11/16/2020 3:08 PM
Budget and Finance Completed I1/16/2020 3:16 PM
Maria Slavik Completed 11/16/2020 3:21 PM
Liz Yongue Completed 11/16/2020 3:39 PM
Board of County Commissioners Pending 11/17/2020 9:00 AM
. se .....
....
..st,
_ -r
,-..-- -
Pr
- ,
• .L
" sm i r
AIPP lit 0 -
.
iof 1" Agin . - se. '
rr
Ir less
alf
S .
r ,,, , .
tol ...a-
4 • .
... „. .1
• ..„,
e •
lit
r ;
_ Demand Load4
5 .
i IL
i
Metering pyr
:N 2 .,,,f ,..
• %met. -11.6•••••092116
. • . t 6
7i r
, « .
- .....„
r ' .
"•".•
,.. . ..
i ..
rt,
-ES218084
Quote prepared by: Tomas Remete by Schneider Electric Engineering Services,
LLC
By: Schneider Electric Engineering Services, LLC November 11 2020
Life Is On , Schneider,
L uElectrtc
v Power System Engineering
Proposal for Post Installation Harmonic Analysis
1 .0 Services & Objectives
Schneider Electric Engineering Services, LLC (SEES) proposes a Demand Load Metering per
NEC220.87 at the MONROE COUNTY-JAIL-facility in Key West, FL. The purpose of this analysis is to
determine the maximum demand load of the facility and provide the requested information to confirm the
required Generators size for the facility. The proposed Demand Load Metering responds to the spec
T.Y.LIN INTERNATIONAL from October 2020.
2.0 Sources & System Conditions
SEES will visit the facility during normal working hours to install two (8) Power Analyzers at the following
locations:
1. SWBD Main, 4000A
2. Load side DJJ/MDP1, 600A
3. Load side MCC# 1, 400A
4. Load side DJJ/MDP2, 400A
5. EDP1, 800A
6. EDP2, 1000A
7. EP1, 400A
8. MDP-CH
The Power Analyzers will record data for 30 days and will be set-up under the conditions described in
NEC220.87 Determining Existing Loads.
A Utility shutdown (about 30 min) is required to install the Power analyzers at the Main SWBD. A second
shutdown will be required to remove the data logger after completion of the data collection.
3.0 Deliverable
After all tests have been completed, the Power Analyzers will be removed, and a written report will be
issued outlining the findings.
The maximum Demand Load will be based on the highest phase of the feeder or service. Min, Max, and
Average recordings will be provided per phase, and additional 3 Phase values, such as Power [Watt],
Reactive Power[VAR], Apparent Power [VA], and Power Factor will complete the report.
•
November 11 2020 Page 2
Quote Number: #ES218084 use or disclosure ordata contained on this sheet is subject Schneider
to the restriction on the tine page of this proposal CEIec tr c
s� Power System Engineering
YProposal for Post Installation Harmonic Analysis
4.0 Price
The User Net price for performing the Demand Load Metering per NEC220.87:
Demand Metering: $ 40,220.00 U/N
This price is valid for 30 days.
Note: Prices are out of peak season in Key West. Prices will need to be revisited if the job is scheduled
in peak season (starting about Dec-15).
5.0 Billing
The billing will be based on the following milestones schedule:
Milestone#1:
After installation of the 8 Power Analyzers.
$20,110.00 U/N
Milestone#2:
After completion of the Data Logging and Report issuing.
$20,110.00 U/N
•
6.0 Schedule
Work can begin within 4 weeks after receipt of order. Once work begins, data collection efforts at the
facility are expected to be completed within 30 days. The results of the Demand Load Metering will be
delivered within 2 weeks of data collection completion.
The customer is responsible for facilitating the SEES data collection process, in order to gather the
necessary information for the Demand Load Metering.
November 11 2020 Page 3
Quote Number: #ES218084 Use orasofosure of contained on this sheets subject Schneider
to the resniction on tie tine page of this proposal ei E l e c t r i c
Power System Engineering
Proposal for Post Installation Harmonic Analysis
7.0 Warranty
SEES warrants that the services provided will meet industry standards. The warranty remains in effect
for one year from the completion of the work and is further explained in the SEES "Terms and
Conditions of Supply and Performance."
8.0 Exclusions
If any specific testing services are requested or required, then SEES will provide separate quotations as
applicable and necessary.
Opening of any electrical enclosures while equipment is energized without the customer's permission.
Exposure to any known, expected, or suspicious environmental hazards, chemical agents, or dangerous
operational processes.
This proposal does not include setting/testing overcurrent devices. Please contact SEES for a quote to
set/test the breakers.
9.0 Customer Required Support
In order for SEES to successfully execute the scope of work, certain customer support is required.
Tasks that must be performed by the customer, or designated representatives, are listed below. This
fist may be incomplete. If other items are identified, either before or during the work, SEES will request
these services.
It is the customer's responsibility to coordinate and schedule the power outage with the local utility
company and cover any associated expenses.
Provide an individual authorized to resolve questions and coordinate customer activities, as required.
November 11 2020 Page 4
Quote Number: #ES218084 Use or disclosure of data contained on this sheet is subject Schneider
to the restrrtion on the ale page of this proposal }�
(j Eleetric
Power System Engineering
Proposal for Post Installation Harmonic Analysis
Provide an experienced electrician or electrical supervisor familiar with the power distribution system to
direct and assist SEES personnel in identifying the proper electrical equipment. This individual shall have
a copy of the applicable electrical one line drawings.
Prior to start of work, the customer shall familiarize SEES personnel with their safety practices and
regulations. SEES shall be under no obligation to commence work unless safety practices are acceptable
to SEES. As a safety precaution, prior to the commencement of work, the customer shall provide access
to a nearby telephone with the ability to call outside the facility if cell phone communications are not
possible. If job site is in a rural area, provide telephone numbers for the following services nearest to the
site: Doctor, Hospital, Ambulance, Fire Department, and Police Department.
It is the customer's responsibility to supply, operate and maintain all applicable standard services to this
facility, such as electric power, lighting, water, air, etc. Backup for these systems are not included in this
proposal.
Provide and expedite any badging or required entry and escorts as necessary.
November 11 2020 Page 5
Quote Number: #ES218084 use or disclosure of data contained on this sheet is subject Schaneider
to the restriction on the tine parte or this proposer ej E I e c t r l c
Power System Engineering
Proposal for Post Installation Harmonic Analysis
11 .0 Terms & Conditions
The work described in this proposal will be performed in accordance with Schneider Electric
Engineering Services, LLC Terms and Conditions of Supply and Performance, which are attached to
this proposal. Unless agreed to in writing, no other terms and conditions shall apply and any preprinted
terms and conditions on the customer's purchase order are specifically rejected.
All work is to be performed during normal straight time working hours when possible, Monday through
Friday, exclusive of holidays observed by Schneider Electric Engineering Services, LLC. Price includes
any required after-hour assessments and testing during Monday through Friday. If the customer
requires work to be performed on a weekend or holiday, the price will be adjusted to reflect the
applicable differentials in the appropriate published hourly or daily rates in effect at the time such work
is performed.
All pricing is based on the customer providing accurate power system data. Schneider Electric
Engineering Services, LLC is not responsible for assessment inaccuracies that are due to incorrect
power system information provided by the customer. Changes due to incorrect information will require
additional pricing.
Schneider Electric Engineering Services, LLC must be granted ready access to the equipment under
investigation. During the onsite testing, Schneider Electric Engineering Services, LLC will need access
to the facility's electrical panels, and the assistance of an electrician or facilities technician familiar with
the electrical loads and the routing of conductors in the facility. Schneider Electric Engineering
Services, LLC reserves the right to discontinue any work deemed by Schneider Electric Engineering
Services, LLC to be unsafe.
DISCLAIMER:'The Purchaser acknowledges that the products or pant thereof are produced in, or
otherwise sourced from, or will be installed in areas already affected by, or that may be affected in the
future by, the prevailing COVID-19 epidemics/pandemic and that the situation may trigger stoppage,
hindrance or delays in SE's (or its subcontractors) capacity to produce, deliver, install or service the
products, irrespective of whether such stoppage, hindrance or delays are due to measures imposed by
authorities or deliberately implemented by SE (or its subcontractors) as preventive or curative measures
to avoid harmful contamination exposure of SE's (or its subcontractors') employees. The Purchaser
therefore recognizes that such circumstances shall be considered as a cause for excusable delay not
exposing SE to contractual sanctions including without limitation, delay penalties, liquidated or other
damages or termination for default.
November 11 2020 Page 6
Quote Number: #E5218084 Use or disclosure of dara contained on this sheets subject Schneider
to the restriction on the Ude page orT is proposal �j
&Electric
Life Is On Schneider
Electric
County of Monroe BOARD OF COEY71 COSibrrSSIONERS
M II it ( .out ❑ ibi:
The Florida Keys jid; ;� Craig , veya u r n�,iu<<2
fLI Cate..o Ltd
r> id U i2i !
MEMORANDUM
DATE: November 16, 2020
TO: BOCC, Administrator
THRU: Kevin Wilson -�-//
FROM: Dan Bensley
SUBJECT: Waiver of Purchasing Policy to contract for Load study of the Stock Island
Jail
Action Requested: BOCC approval
Background:
There have been multiple back up generator failures in the past year. Staff has contracted
with a consultant to design the installation of new back up generators. In order to properly
size the generators a load study is required.
All electrical supply for the entire site passes through one meter although there are two
generators and several separate systems. The consultant can perform a load study that will
ensure the replacement generators are properly sized for $40,220, Normally, purchasing
policy requires multiple quotations for such a purchase. Staff requests a BOCC waiver of
that policy to allow the consultant to add this load study to their existing work to ensure that
the new generators are properly sized.