2nd Change Order 02/11/2014 MEMORANDUM DATE: February 11,2014 TO: Vitia Fernandez,Deputy Clerk FROM: Beth Leto,Public Works RE: CO#2—Siemen's Industry,Inc. Enclosed please find the fully-executed original of Change Order #2, extending contract completion date by one hundred twenty (120) days to June 11, 2014, as executed by Debbie Frederick, Deputy County Administrator, in accordance with Ordinance 026-1998. Should you have any questions, please feel free to contact me at x4560. cc: Bob Stone Ann Riger Tina Kunst MEMORANDUM TO: Board of County Commissioners From: Debbie Frederick Deputy County Administrator Date: February 7, 2014 RE: Change Order Attached is a proposed change order for Siemens Industry,Inc. (Change Order*2 is for a no-cost time extension of no days. The new substantial completion date is June 11, 2014.) According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placedpl on the BOCC agenda. The Administrator intends to ap ro this cha a order on➢dend�ay, February up, 2o14. ie Frederick County Administrator DF:cac MEMORANDUM DATE: FEBRUARY 4, 2014 TO: DENT PIERCE, PUBLIC WORKS DIVISION DIRECTOR n FROM: BOB STONE, MIDDLE KEY OPERATIONS DIRECTOWtV/ RE: FIRE DETECTION AND ALARM SYSTEM REPLACEMENT- MONROE COUNTY DETENTION CENTER - STOCK ISLAND Attached for approval is Change Order No. 2, executed by the Contractor and myself for the project referenced above. This is a no cost change order and only extends the substantial completion date by one hundred and twenty days. At this time, the substantial completion date is February 11, 2014. Due to the complexity of the existing fire alarm system and its interconnectivity with other life safety systems, it has taken the Contractor an extended period to develop and install a method to parallel both the new and old system. This is being done to comply with their agreement in not disrupting or jeopardizing Detention Center operations. Therefore, the requested one hundred and twenty day time extension is recommended. If approved, the new substantial completion date would be June 11, 2014. Please let me know if there are any questions or more information is desired. • MONROE COUNTY PUBLIC WORKS Change Order PROJECT: CHANGE ORDER NUMBER: 002 Monroe County,FL— Fire Detection and Alarm System Replacement DATE: February 3,2014 Monroe County Detention Center CONTRACTOR: PROJECT NUMBER: PWD-none-25-2012 Siemens Industry, Inc. CONTRACT DATE: April 17,2013 3021 North Commerce Parkway NOTICE TO PROCEED: June 7,2013 Miramar,Florida 33025 CONTRACT FOR: General Construction THE CONTRACT IS CHANGED AS FOLLOWS: Due to the complexity and time impact in transferring system functions to the new system with minimized impact to the facility, the contract time is hereby extended by(120)one hundred and twenty days. Please note that the contract amount has not changed. The original Contract Sum was $270,580.00 The net change by previously authorized Change Orders $0 The Contract Sum prior to this Change Order was $270580.00 The Contract Sum will be changed by this Change Order in the amount of $0 The new Contract Sum including this Change Order will be $270,580.00 The Contract Time will be increased by(120)one hundred and twenty days. The date of Substantial Completion as of the date of this Change Order therefore,is June 11,2014. NOT VALID UNTIL SIGNED BY THE CONTRACTOR AND THE OWNER Robert A. Stone. MCPW Siemens Industry, Inc. Monroe County,FL Owner's Representative Contractor Owner 10600 Aviation Blvd., Marathon, FL 3021 N.Commerce Parkway 1100 Simonton Street Marathon,FL 33050 Miramar, FL 33025 Key West, FL 33040 Address Address Address / '� BY (Signature) Y ignatureJ (( '(Signature) /r; — i ( /1 DATE / DATE D (77lll//`-J' SIEMENS January, 27, 2014 Robert A. Stone Director. Middle Keys Operation Monroe County Public Works 10600 Aviation Blvd Marathon, Fl. 33050 SUBJECT: Request for Time Extension PROJECT: Monroe County Detention Center Dear Mr. Stone: ISSUE: The installation of the work schedule is being delayed due to the complexity of the old addressable system. A few changes needed to be done to minimize the down time of the existing SLC circuits and the dorm door releases. BACKGROUND: The value engineering and removing the old transponders is causing an issue with the existing wiring Siemens will add the transponders back into the system. Some of the relay boards for the door release and smoke control are on back order from our factory. SITUATION: The substantial completion date is February I I, 2014. REQUEST: We are requesting an additional 120 days to complete the installation. This would put the new substantial completion date 6/11/2014. If you have any questions, contact me as soon as possible. My telephone numbers are 954-364-6770, and my cell phone number is 954-806-8732. Very truly yours, Edward Pleffner Operations Manager Sawa 7. Pleasez cc: Project file Project Team