03rd Change Order 01/13/2021 Jacobs Key West International Airport 12/2020 Monroe County Rehabilitate Taxiway A Project No. GAKAP159 CHANGE ORDER PROJECT: CHANGE ORDER NO.: 3 Rehabilitate Taxiway A INITIATED ON: December 15 2020 CONTRACT: GAKAP159 TO(Contractor):General Asphalt 4850 NW 72"d Avenue Miami,Florida 33166 CONTRACT DATE: September 18,2019 You are hereby authorized and directed to make the following change(s)in this Contract: The king tides, after S-27 was installed,were higher than those of the tide prediction charts. During these events the junction can at S-27 was under water. The junction can at S-27 will need to be elevated to avoid future water inundation. Change Order 3 is the modification of the junction can elevation to be higher than these king tide events The original Contract Sum............................... $ 9,691,602.25 Net change by previously approved Change Orders......... $ 4,229.83 The Contract Sum will be unchanged by this Change Order...................... $ 2,156.00 The new Contract Sum including this Change Order will be............................................... $ 9,697,988.08 The Contract Time will be increased by........................................ N/A The Contract Completion date is........................................ January 7,2021 Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time for delays,disruption,inefficiency,acceleration and all other claims. RECOMMENDED: AGREED TO: Jacobs Engineering General Asphalt 12/15/2020 -. Date hry Date AUTHORIZED: Key West International Airport Monroe County 3491 South Roosevelt Blvd. 1100 Simonton Street Key West,FL 33040 Key West,FL 33040 FL 01.13.2021 BFy to By 61 Date ' - - 1/13/21 EXTRA WORK-WORK ORDER F1 mom Date Work Order# 11/19/2020 4-Sign Pad 27 PROJECT IINFORMATION TO> Project Name: KYW Rehabilitate Taxiway A Company Name:Jacobs Project Number:GAKA163 Contact Person:Ms.Lasa Ennis,P.E. Project Location:Key West International Airport Phone:904-224-3135 Item# '; Description Unit quantity Unit Price Total 1 Sign Pad 27 Elevation Change L.S. 1.00 $2,15 701 Sub-Contractor Florida Keys Electric L.S. 1.001 $1,960.00 $1,960.00 Subtotal $1,960.00 Contractor General Asphalt L.S. 1-001 $0.00 $0.00 Total $1,960.00 Mark-up 10.00% $196.00 Grand Total $2,156.00 Page 1 of 1 Proposal October 30,2020 To: General Asphalt Gabriel Martinez Phone:(305)592-3480 4850 NW 72"a Ave. Email:gabriel@generalasphalt.com Miami,FL 33166 Project:Airport Sign Modification/Rework Florida Keys Electric,Ina is pleased to submit our proposal for the electrical work to be done at "Key West International Airport Taxiway A Rehab"Florida Keys Electric,Inc.guarantees that all work performed by our company shall conform to current codes,regulations,and specifications.All work performed by Florida Keys Electric,Ina shall be warranted for one year after date of completion. The following breakdown describes the items and services that Florida Keys Electric,Inc.shall provide as well as any exclusion(s)from our scope of work. FLORIDA KEYS ELECTRIC HAS INCLUDED: • Labor,tools,and material for the removal and reinstallation of sign precast junction can at S-27 to the revised elevation FLORIDA KEYS ELECTRIC HAS NOT INCLUDED: • Utility fees or charges Florida Keys Electric,Inc.proposes to perform the work as stated in this proposal,in accordance with job description,and complete in a workmanlike manner,for the sum of: ProposalPrice..................................................................................................$1,960.00 Respectfully Submitted, Raymond Vazquez President Florida Keys Electric,Ina Confidential Information