03rd Change Order 01/13/2021 Jacobs Key West International Airport 12/2020
Monroe County
Rehabilitate Taxiway A
Project No. GAKAP159
CHANGE ORDER
PROJECT: CHANGE ORDER NO.: 3
Rehabilitate Taxiway A
INITIATED ON: December 15 2020
CONTRACT: GAKAP159
TO(Contractor):General Asphalt
4850 NW 72"d Avenue
Miami,Florida 33166
CONTRACT DATE: September 18,2019
You are hereby authorized and directed to make the following change(s)in this Contract:
The king tides, after S-27 was installed,were higher than those of the tide prediction charts. During these events the
junction can at S-27 was under water. The junction can at S-27 will need to be elevated to avoid future water
inundation. Change Order 3 is the modification of the junction can elevation to be higher than these king tide events
The original Contract Sum............................... $ 9,691,602.25
Net change by previously approved Change Orders......... $ 4,229.83
The Contract Sum will be unchanged
by this Change Order...................... $ 2,156.00
The new Contract Sum including this Change Order
will be............................................... $ 9,697,988.08
The Contract Time will be increased by........................................ N/A
The Contract Completion date is........................................ January 7,2021
Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the
Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time
for delays,disruption,inefficiency,acceleration and all other claims.
RECOMMENDED: AGREED TO:
Jacobs Engineering General Asphalt
12/15/2020
-.
Date hry Date
AUTHORIZED:
Key West International Airport Monroe County
3491 South Roosevelt Blvd. 1100 Simonton Street
Key West,FL 33040 Key West,FL 33040
FL
01.13.2021
BFy to By 61 Date
' - - 1/13/21
EXTRA WORK-WORK ORDER
F1 mom
Date Work Order#
11/19/2020 4-Sign Pad 27
PROJECT IINFORMATION TO>
Project Name: KYW Rehabilitate Taxiway A Company Name:Jacobs
Project Number:GAKA163 Contact Person:Ms.Lasa Ennis,P.E.
Project Location:Key West International Airport Phone:904-224-3135
Item# '; Description Unit quantity Unit Price Total
1 Sign Pad 27 Elevation Change L.S. 1.00 $2,15 701
Sub-Contractor
Florida Keys Electric L.S. 1.001 $1,960.00 $1,960.00
Subtotal $1,960.00
Contractor
General Asphalt L.S. 1-001 $0.00 $0.00
Total $1,960.00
Mark-up 10.00% $196.00
Grand Total $2,156.00
Page 1 of 1
Proposal
October 30,2020
To: General Asphalt
Gabriel Martinez Phone:(305)592-3480
4850 NW 72"a Ave. Email:gabriel@generalasphalt.com
Miami,FL 33166
Project:Airport Sign Modification/Rework
Florida Keys Electric,Ina is pleased to submit our proposal for the electrical work to be done at "Key West
International Airport Taxiway A Rehab"Florida Keys Electric,Inc.guarantees that all work performed by our
company shall conform to current codes,regulations,and specifications.All work performed by Florida Keys
Electric,Ina shall be warranted for one year after date of completion. The following breakdown describes the
items and services that Florida Keys Electric,Inc.shall provide as well as any exclusion(s)from our scope of
work.
FLORIDA KEYS ELECTRIC HAS INCLUDED:
• Labor,tools,and material for the removal and reinstallation of sign precast junction can at S-27 to the
revised elevation
FLORIDA KEYS ELECTRIC HAS NOT INCLUDED:
• Utility fees or charges
Florida Keys Electric,Inc.proposes to perform the work as stated in this proposal,in accordance with job
description,and complete in a workmanlike manner,for the sum of:
ProposalPrice..................................................................................................$1,960.00
Respectfully Submitted,
Raymond Vazquez
President
Florida Keys Electric,Ina Confidential Information