20th Change Order 03/10/2021 `v BOARD OF COUNTY COMMISSIONERS County of Monroes , Mayer Michelle Coldiron,District 2 The Florida Keys r Mayor tiro Tem David Mice,District 4 Craig Cates,District 1 i f Eddie Martinez,District 3 Mike Forster,District 5 Memorandum DATE: 03/09/2021 TO: BOCC cn=Kevin G.Wilson,P.E.,o=Monroe County,FL(the Florida Keys,ou, FROM: Kevin G. Wilson, P.E. -A L (( k email=wilson- 1 F kevin@monroecounty-fl.gov,c=US 2021.03.09 09:36:37-05'00' SUBJECT: Proposed Change Order to be Approved Attached is proposed Change Order#20 for the Monroe County Library & Adult Education Marathon Branch project. This change order increases the final contract sum by $10,794.90. The substantial completion date is increased to 04/17/2021. Monroe County Ordinance 027-1998 and subsequent amendments provide authority for the Administrator to approve change orders within specified limits after providing Board of County Commissioners with at least 24 hours to review them and pose any questions or objections that they may have. It is the Administrator's intent to approve the attached change order under that authority on Wednesday, March 10, 2021. MONROE COUNTY/ENGINEERING/ PRojEcr MANAGEmENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: #20 Monroe County Library and Adult Education INITIATION DATE:310512021 Center,Marathon Branch CONTRACT DATE:0312112019 TO CONTRACTOR: Pedro-Falcon Contractors,Inc. 31160 Avenue C Big Pine Key,FL 33043 The Contract is changed as follows: The original (Guaranteed Maximum Price) ................... ........ 7,016,385.00 Net change by previously authorized Change Orders .. .....................---.................... $ 917,720.39 The!Contract Sum)(Guaranteed Maximum Price)prior to this Change order was .............$7,934,105.39 The&ntract Sum)(Guaranteed Maximum Price)will be(increased)(decreased)(unchanged)by this Change Order ............$ 10,794.90 The new(Contract Sum)(Guaranteed Maximum Price)including this Change Order is.....1 7,94 ,900. 9 The Contract Time will be(increased)(decreased)(unchanged)by.—,.......... ....... 42 Days The date of Substantial Completion as of the date of this Change Order'S ............ ........ 4/17/2021 Detailed description of change order and justification- Upon installation of the guardraiMhandrail combination,it became evident that the planned railings presented a safety concern. The railings,being nearly solid, contfibuted to almost no sight visibility. This poses safety concerns not only for natural site surveillance by Library staff and Sheritfs Office Deputies, but also for ADA patrons utilizing the designated ADA access ramps.At the request of Library staff, the railings are being replaced with a design that complies with ADA requirements while allowing visibility.Fabrication and installation time is approximately 6 weeks.As handrails are required thr obtaining a Certificate of Occupancy,a time extension for substantial completion is required. Extending substantial completion for the handrails will not impact the next phase of Library setup by Library staff. Increase Substantial Completion by 42 calendar days, from March 6, 2021 to,April 17, 2021. Chan order is 0.15%of ofidinal contract rice. Not valid until signed,py Owner if applicabk and Con act'- ArchitectL ARCHITECT- nk LLC Date CONTRACTOR: 0� edro-Falcon Contractors, Inc. Date Digitally signed by Cary Knight DIRECTOR PROJECT MANAGEMENT Cary Knighu,,,2 021,03,09 0 9:16,0 5-05'00' Cary knight,Director Date cn—Kevin G.Wilson,P.E.,o—Monroe County,FL 'the Florida Keys,ou,e.ail—wilson- kevin@monroecounty-fl.gov,-US COUNIVASSISTANT ADMINISTRATOR: 2021.03.10 15 30 27-0500' Roman Gates. Date Kevin Wilson Christine Hurley Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes E No F] If Yes, explanation: This owner-requested change is to address safety concerns brought up during constrvction by Librarystaff. • Change Order was included in the original specifications. Yes El No Z If Yes, explanation of increase in price: • Change Order exceeds$50,000 or 5%of contract price(whichever is greater). Yes 0 No Z If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes 0 No F1 If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes FJNo E Should a claim under the applicable professional liability policy be made? Yes El No Z Explain: NIA P�EDRO FALCON CONTRACTORS, INC. t31160 Avenue C, Big Pine Key, FL 33043-4516 ( .Fax - 1 - EC 13003416 1 CGC 11 z a Requestfor Change Order 03 March 2021 Project: Marathon library PCO Number: 082 Description: e .or Railings Anschuetz Aluminum Two, Inc. wised.Railings Per Attached Sketch and Proposal............................. ......... ......... .......... ................... ......., ......... ...........,$io,i69.00 Subtotal Subcontractor...................................................................$1o,169.00 PFCManagement Fee s ....... ........... ........ ......... .................. ......... .................$5o8.45 SubtotalSubcontractor............................................. ......................$io,677.45 P&P Bond 1.1%ofTotal Cost..............................................................$117-45 Total Requestfor Change OrderAmount.........................................$1o,794.90 Additional 71me Required is Calendar Daysfrom Receipt offknal Approved Change Order. Respectfiffly Submitted, ]Ken Byer Project Manager Industrial-Commercial.Institutional-Residential Utility E&Iab11sh d 1984 Anschuetz Aluminum Two Inc. Estimate 1649 SW I st Way Suite#2 Date Estimate# Deerfield Beach FL 33441 3/1/2021 21-0147 Name/Address Pedro Falcon Electrical Contractor,Inc, 31160 Avenue C Big Pine Key,FL 33043 P'O. No. Project Marathon Library Item Description Qty Ulm Rate Total CHANGE ORDER 91 Custom Fabricat... To remove existing Guardrail and furnish 98 Linear 98 ea 60.00 5,880.00 feet of 42"tall Horizontal Guard Rail using I"face welded square tube to reject a 4"sphere,2"x 3"rec tube top cap,2"x 2"posts to be installed at existing core drill. Custom Fabricat.., To remove existing Guardrail and furnish 103 103 ea 38.00 3,914.00 Linear feet of 42"tall Grip Rail using To x 3"rec tube top cap,2"x 2"x 1/4"wall posts to be installed at existing core drill. Engineering Signed and Sealed Engineering CAD I ea 375-00 375.00 Permit by others Double Powder coated Sky White Please sign off and remit the deposit of 50%at your earliest convenience.Pricing good for 30 days LTOtal $10,169.00 Signature Kdftall NOHIVHVW _ 5 r � O ... r rvr r r II M_. rIlkNA lee EO s i ✓ i i L 4 s 4 j N S a ....... _��C-- oi�Qi��0ni3c 00000 ate �•�A � „c .....�.�,�• ,.,T9MhT]L`3x2NYXla 353N9N 11d11'P ............... ............. g 4m¢[v' rtarm".r ¢ g x. tt 4V s HUNT) ��^g�y y{}�{ �ry7 tirxwpw syewo�wys G ,� I � s 4 r ' 3 EJ Tj_ El Ft 7 11111H NMI AT x — t 1 l4 : r 6 El 1�0 F 4 w � TnTffr e . � _ Pp { i 1113 �4u I 7 �z �� .. ....... ! @@ t n g . ' ._ .- El000000Eo 0 0 E E oo®000� El �� {� \\ •4 � (� ct � } �. : . \ 2 y 4-4 \\ a � JOL ^■ � � }\ » \\ gr v - [ « [ \ § \\ \\ \ \ \ \ \\Jo \ \ . . . U71 . �. . \ �. �|