06th Change Order 03/09/2021 Jacobs Key West International Airport 01/2021
Monroe County
Rehabilitate Taxiway A
Project No. GAKAP159
CHANGE ORDER
PROJECT: CHANGE ORDER NO.: 6
Rehabilitate Taxiway A
INITIATED ON: February 18,2021
CONTRACT: GAKAP159
TO(Contractor):General Asphalt
4850 NW 72"d Avenue
Miami,Florida 33166
CONTRACT DATE:September 18,2019
You are hereby authorized and directed to make the following change(s)in this Contract:
General Asphalt is requesting a 41-calendar day time extension to complete the paving and first application of the
permanent pavement markings. On November 191 due to an increase in commercial air traffic the Airport requested
GAC to postpone the construction adiacent to the commercial apron until April 151h The request modified GAC's
critical path to complete the other areas of the project In January,the Airport requested GAC to complete the paving as
soon as feasible instead of re-mobilizing in April. The modification of the construction schedule resulted in loss of
production.This change order is for time only and does not increase contract costs
The original Contract Sum............................... $ 9,691,602.25
Net change by previously approved Change Orders......... $ 177,408.33
The Contract Sum will be unchanged
by this Change Order...................... $ N/A
The new Contract Sum including this Change Order
will be............................................... $ 9,869,010.58
The Contract Time will be increased by........................................ 41 CALENDAR DAYS
The Contract Completion date is................................................... March 25,2021
Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the
Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time
for delays,disruption,inefficiency,acceleration and all other claims.
RECOMMENDED: AGREED TO:
Jacobs Engineering General Asphalt
02/18,/2021
Date yA Date
AUTHORIZED:
Key West International Airport Monroe County
3491 South Roosevelt Blvd. 1100 Simonton Street
Key West,FL 33040 Key West,FL 33040
March 9,2021
'4y - Date By Date
r
A E COUNTY AT7 nNEY
C c
PED O j'
APSE sTf� LINTY AtTfFtIEY
Date �/5/21
4850 NW 72 Avenue
Miami, 33166
General Asphalt Co., Inc. Phone:Florida(305) 92 3480
Fax: (305)477-4675
February 18th, 2021
Lasa Ennis, P.E.
Jacobs
Project Manager-Aviation
200 West Forsyth Street; Suite1520
Jacksonville, FL 32202
Re: EYW Rehabilitate Taxiway A
Time Extension— Rescheduling
Lasa,
General Asphalt Co. Inc, is formally requesting a time extension, due to scheduling restrictions
with the commercial apron connectors. At the request of the Airport connectors 9, 10 & 11
became off limits due to flight schedule and would need to be completed at a later date under
another mobilization.
GAC was officially notified on November 19tn, 2020 "GAC to postpone the A9, Al and Al
closures until April 151 Subsequently the schedule was changed to conform to the request
changing the critical path of the project. All worked stopped in those areas.
The remobilization was retracted,and requested to continue with the work that was previously
off limits. The critical path of work was again required to shift, resources and scheduling
required to accelerate. Closure of the first connector (11) was approved for January 17tn
construction began to open the area as quickly as possible.
During this time the critical path had shifted into coordinating full paving crews previously
schedule for April to be back on the;project. Work was coordinated to take place on the
remaining connectors and allow time for the paving crew to remobilize. The sequence of work
established was to focus around the critical areas in order to pave as soon as the connector
was ready.
The work anticipated for April was estimated at a month and a half for all features of work to be
completed.
The requested time is for 3/25/21 to obtain substantial completion for connectors A9, A10, final
lift of asphalt and 1st application of permanent pavement markings.
Respectfully,
Gabriel Martinez