Loading...
Item J05 J.5 `, County of Monroe y,4 ' �, "tr, BOARD OF COUNTY COMMISSIONERS Mayor Michelle Coldiron,District 2 �1 nff `ll Mayor Pro Tem David Rice,District 4 -Ile Florida.Keys Craig Cates,District 1 Eddie Martinez,District 3 w � Mike Forster,District 5 County Commission Meeting March 17, 2021 Agenda Item Number: J.5 Agenda Item Summary #7927 BULK ITEM: Yes DEPARTMENT: Airports TIME APPROXIMATE: STAFF CONTACT: Richard Strickland(305) 809-5200 N/A AGENDA ITEM WORDING: Approval to apply to the Federal Aviation Administration (FAA) for Passenger Facility Charge (PFC) Application 420 funding for the Key West International Airport and to accept public comment on the County's application for 30 days upon the posting of the required Public Notice. ITEM BACKGROUND: The Key West International Airport (EYW) intends to file PFC Application No. 20 to impose and use PFCs to fund, in part, the following projects: 1. EYW new Concourse A and Terminal Improvements Program Debt Service 2. EYW Commercial Apron Expansion 3. PFC Administrative Costs Upon a preliminary meeting with the FAA and an Airline consultation meeting, the County will accept public comment as part of the passenger facility charge (PFC) application process under 14 CFR § 158.24. Additional information about this PFC application and the projects (including project description, costs, funding sources, timing and justification)will be posted on the Key West International Airport's website: ww.eyw.com Comments from the public will be accepted for 30 days as described on the website. PREVIOUS RELEVANT BOCC ACTION: None CONTRACT/AGREEMENT CHANGES: N/A STAFF RECOMMENDATION: Approval DOCUMENTATION: PFC Application 420 Packet Pg. 1668 J.5 FINANCIAL IMPACT: Effective Date: Expiration Date: Total Dollar Value of Contract: N/A Total Cost to County: N/A Current Year Portion: Budgeted: Source of Funds: N/A CPI: Indirect Costs: Estimated Ongoing Costs Not Included in above dollar amounts: Revenue Producing: If yes, amount: Grant: County Match: Insurance Required: Additional Details: REVIEWED BY: Beth Leto Completed 03/02/2021 1:22 PM Richard Strickland Completed 03/02/2021 2:58 PM Pedro Mercado Completed 03/02/2021 3:06 PM Purchasing Completed 03/02/2021 3:21 PM Budget and Finance Completed 03/02/2021 3:59 PM Maria Slavik Completed 03/02/2021 4:00 PM Liz Yongue Completed 03/02/2021 4:24 PM Board of County Commissioners Pending 03/17/2021 9:00 AM Packet Pg. 1669 J.5.a Key West International Airport PFC#20 projects for which the County is Seeking Agreement to Impose and Use Authority 1. EYW new Concourse 'A' and Terminal Improvements Program Debt Service Project Start Date: 07/2025 Project End Date: 07/2053 Funding: Approved Alp $0 FDOT Funds $0 Local Funds $0 CL PFC $56,000,000 Total Project Cost $56,000,000 • Project Description: This project is to fund debt service of up to $2,000,000 per year for 28 years to repay the debt that will fund the construction of the new second-level Concourse A of approximately 49,000 square feet;glass enclosed passenger loading bridges;expansion of additional baggage make up areas and devices, airline ramp/office spaces, ramp equipment storage areas and an additional bag claim device; an expanded security checkpoint with area to support up to 4 lanes and added support spaces; a new extended passenger bridge located post security will connect the existing terminal building with the new Concourse; a new pedestrian bridge for public access to airport administration offices;and an expanded rent-a-car facility area '✓ and baggage service offices. Project Justification: Key West International Airport is experiencing tremendous passenger growth. The increased passenger peak hour demand has stressed the terminal passenger processing capabilities for both arrivals and departures to include, ticketing area, security checkpoints, outbound baggage conveyor, departures lounges, baggage claim and aircraft operations. Concourse 'A' addresses the deficiencies while c, providing an improved level of service. CL Project Objective: This project will accommodate the growth through increased capacity,improved operations E and passenger experience. 2. EYW Commercial Apron Expansion Project Start Date: 09/2022 Project End Date: 09/2023 Funding: Approved AIP $12,627,000 FDOT Funds $701,500 Local Funds $0 PFC $701,500 Total Project Cost $14,030,000 Packet Pg. 1670 J.5.a • Project Description: The proposed expansion of the commercial apron as identified in the EYW Master Plan Update will include airfield signage, marking, and lighting and would add approximately 13,200 square yards of concrete pavement. Approximately 2,000 cubic yards of fill material would be placed to allow the new apron pavement to meet the grade of the existing apron and to regrade the surrounding land to match existing grades.The project will include drainage improvements to accommodate the additional expanded pavement. The project will also include the design of the mitigation areas to offset the impacts of the expanded apron area. Project Justification: Key West International Airport is experiencing tremendous passenger growth. Congestion on the commercial apron results from the number of commercial aircraft operations at EYW during peak periods, as well as a trend towards larger aircraft serving EYW. The Airport needs to reduce the congested conditions of the commercial apron by meeting FAA airport design standards for the fleet currently operating at EYW to (1) maintain safe conditions while improving the efficiency of aircraft operations on the apron, (2) alleviate congestion on Taxiway A, and (3) minimize the risk of passengers inadvertently boarding N the wrong aircraft. The expansion of the commercial apron will be needed to achieve these goals.. CL Project Objective: This project will accommodate the growth through increased capacity,improved operations and passenger experience. 3. PFC Administrative Costs 0 Project Start Date. March 2021 Project End Date: March 2022 I Funding: Approved AIP $0 cCD v FDOT Funds $0 Local Funds $0 PFC $48,183 Total Project Cost $48,183 CJ CL Project Description: Includes professional fees for services rendered from the County's consultant in developing PFC Application No. 21-20-C-00-EYW. Project Justification: The justification for this project(PFC Administrative Costs) is the same as the justification for other projects in PFC Application #21-20-C-00-EYW. This project is eligible in accordance with 14 CFR § 158.3, "allowable costs" as explained in that section's preamble. Project Objective: This project will preserve capacity. Packet Pg. 1671