21st Change Order 04/12/2021 ' `v BOARD OF COUNTY COMMISSIONERS County of Monroes , Mayer Michelle Coldiron,District 2 The OI"1 r Mayor Pro Tem David Mice,District 4 Craig Cates,District 1 i f Eddie Martinez,District 3 Mike Forster,District 5 Memorandum DATE: 04/09/2021 TO: BOCC cn=Kevin G.Wilson,P.E.,o=Monroe L(the a Keys, FROM: Kevin G. Wilson P.E. County,Fson-ke in@monroec, i r yr a�`�ry�. �e�f� email=wilson-kevin@monroecounYy- fl.gov,c=Us 2021.04.09 15:42:19-04'00' SUBJECT: Proposed Change Order to be Approved Attached is proposed Change Order#21 for the Monroe County Library & Adult Education Marathon Branch project. This change order increases the final contract sum by $19,178.35. The substantial completion date is unchanged. Monroe County Ordinance 027-1998 and subsequent amendments provide authority for the Administrator to approve change orders within specified limits after providing Board of County Commissioners with at least 24 hours to review them and pose any questions or objections that they may have. It is the Administrator's intent to approve the attached change order under that authority on Monday, April 12, 2021. MONROE CouNTY/ENGINEERING/ lftojEcT MmAGEmENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: #21 Monroe County Library and Adult Education INITIATION DATE:410712021 Center,Marathon Branch CONTRACT DATE:0312112019 TO CONTRACTOR: Pedro-Falcon Contractors, Inc. 31160 Avenue C Big Pine Key,FL 33043 The Contract is changed as follows: The original(Contract Sum)(Guaranteed Maximum Price) ...... 7,016,385.00 Net change by previously authorized Change Orders................................ ................. $ 928,515.29 The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was .............$7,944,90,0.29 The(Contract Sum)(Guaranteed Maximum Price)will be(increased)(decreased)(unchanged)by this Change Order....——....$ 19,178.35 The now(Contract Sum)(Guaranteed Maximum Price)including this Change Order is....,.$ 7,964,078.64 The Contract Time will be(increased)(decreased)(unchanged by... ._.—... ......... ......... 0 Days The date of Substantial Completion as of the date of this Change Order is ................... 4/17/2021 Detailed description of change order and justification: During a scheduled substantial completion walk-through with Project Management, Facilities, and Library staff, it was determined several changes were required. Gutters along the Adult Education Center roof line were not a part of the original plans,however, it was determined that changes to the ADA access ramp resulted in additional gutters now being required to facilitate a dry accessible path. Fascia covers were determined to be required in the Adult Education Center as the shade housings were visible due fo the coiling height1conriguration in the classrooms. Fascia covers would hide the unsightly internal components of the shade system from being visible. Lastly, changes to the exterior signage were made to increase legibility of the letters. Due to this change,more substantial up4lighting was required to allow the building signage to be visible at night. This additional work does not affect the pro ject's substantial completion date. Change order 10,2 796 of opiginyl contract ram,._ Not valid until signed by Owner,Architect 11taiml iJbIel and Cont for ARCHITECT: % ski Ro Sa LLC Date 'Flo CONTRACTOR: Pedro-Falcon Contractors, Inc. ate t Digitally signed by Cary Knight Cary Knigh Date:2021.04.09 15,12:21 DIRECTOR PROJECT MANAGEMENT -04'QQ' Cary Knight,Director Date P cn—Kevin G.Wilson,P.E.,o—Mouroe County,FL (the Florida Keys,on,email—wilson- -fl.gov,-US kevin'monroecounty COUNTY/ASSISTANT ADMINISTRATOR: 2021.0'4.12 1 6-08A5-0400' Roman Gastesi Date Kevin Wilson Christine Hurley Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes Z No El If Yes, explanation: These owner-requested changes were detennined to be required during construction. • Change Order was included in the original specifications. Yes El No Z If Yes, explanation of increase in price: • Change Order exceeds$50,000 or 5%of contract price(whichever is greater). Yes F1 No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes Z No F] If no, explanation of why: • Change Order is correcting an error or omission in design document, Yes E]No Z Should a claim under the applicable professional liability policy be made? Yes E] No Z Explain: NIA Ln Lo LM q u) P, c: Lin C4 Lq nt I! co ul Ln la 10 0 uj CL cr crLE cr a. LE m 0 2 % cc w -4 m LL Lu Am 0 V u 0 E rj cc r 0 0 w =to % Im m rn o C) 0 v u u LO�[iL [L A I V1 C-1 8 2888289 8 a 8 ui 10- uj CL Ln cr uj r. o 0 LAJ Z� rl 0 m z z 0 39 tp Z8 33 8888888 ui 6 6 g d ul LJ tory uj a o z ju tz Li R q EQ Ik TO LU 61-0 %Olga 4 a a g 19-1 uj "r LU PT z z 0 uj 10 LD z -r 0 0 be C,- 2s z z L6 0 Z PEDRO FALCON CONTRACTORS INC. 31160 Avenue , Beg Pine Key, FL 43 51 (3 7 -2200 -Fax ( ) 7A1 Request for Change Order o3 March 2021 Project: Marathon Ubrary PCO Number.- 038 aeRevised Cover at Ed Center Ter-Tex Construction Approx.50'of Clear Anondized Window Shade Fasciato match Existing ........................................................... 1,458.00 SubtotalSubcontractor........................................ .............................$1,458.00, FFCManagement Fee @ 5%................. ......... ......... ......... ......... ........................... 72.9 Subtotal Subcontractor...........;—..................................................... 1,530- u 1.1%of Tot t.........................................,.......................$16.84 Totale u t e Order Amount.......................................... 1 7. Additional Tima Regidred i 28 Calendar Daysfirom Receipt ofFinal Approved a Order. RespecLftilly 5Amitted, Ken Bygler Project Manager industrial.Commercial-institutional.Residential.Utility Established 1984 Change Request Proposal Project' 201 D34 I Marathon Library Change request number,: 1001 (name and 3490 Overseas Highway Description: Add 50 LF clear anodized fascia at 3-100,3- address) Marathon,FL 33050 101,3-103,3-104 and 3-106 Customer Pedro Falcon Contractors Inc [Notice to Proceed Status: PROPOSAL Submitted date_ Origination date: 03/01121 Received date: Rough order of magnitude: 0.00 [Quotation Submitted date: 03101/21 Due date: Submitted amount 1,45&00 Requested days delay: 0 Notes ADD 50 LINEAR FEET OF ALUMINUM FASCIA COVERS FOR 13 WINDOWS MATERIAL......._..............$680,00 TAX--------------------------•------$4800 FREIGHTIDELIVERY-----$350,00 LABOR--... .........—$190.00 OH&P-- —,— - ---$190.00 TOTAL C/O VALUE$1458,00 Ley2nue Detail Billing Item Description Revenue 12493U 1,458.00 Total Revenue For CR 1001 1,468.00 Approvals Customer Pedro Falcon Contractors Inc Contractor:Ver-Tex Construction,Inc. Authorized Representative: BT By-. Date: Date: Print Date.03/01121 Page 1 of 1 a PEDRO FALCON CONTRACTORS, INC. 31160 Avenue C, Big Piste Key, FL 1 �Q � !- ( ) 7 -2200-Fax( )872-2219 EC 13003416 1 CGC 1607617 is www.pe,drofalcon.com Request for Change Order 23 March 202 Pr Ject:03 arattion Library PC : 03 Description:Additional t Low Roof Bob Hilson and Company Approx. 95'o r and (3)Dovmspout Drop...................................................................................... 8,863.50 Subtotal Subeontractor ................................ .....................................$8,863-50 PFCManagement Fee @ 5%........ ........ ......... ......... .................. ......... ..................$443-18 Subtotalet .....................................................................$9,3o6.68 Bond1.1 of Tot l Cost....................................................................$102-37 Total Requestfor Change OrderAmount........................................$fir, 09.05 Additional 71me Required is unknoum at this . Respeeffiffly Submitted, Ken Bygler Project Manager Industrial.Cominercial-Institutional e Residential.Utility °s#atlrhd 1984 LICENSEM CHANGE ORDER V,, , I `, P Date:march 2Z 2021 COMPANY, INC. RUK;FING &SWEU NEUL Customer's Phone No; 872-2200 Name:bbndhon Library and Adult Education Center The undemgned property owners hereby authonze Bob Hilsan&Company, ,To supply all material and labor 01 NW 14di enue mvesmry for the work s i,e below on l lay at. erseas Hwy, Homestead, FL 33I City: sr ,ttian State:Florida Zile Code:33050 .Box 901643 The undersignedDater hereby authorizes Bob lUsan&Company,Inc.('Contractor")to supply material Homestead, FL 33090 d labor for the work sl=ified below on the 05-246-0209 MANGE 9 305-248-1982 Fax -ERIg - O 305-451-2,9,27 l matching finish 032 aluminum box otter . 0 d one 1 ofdownspout at the South West side,Price includes rrt ,lift equipment rental. Payee for the above scope ofor 0 . 0 t r . com .tr I t L r -HERO&NG Original Cofitr=l' ee. $326,350.00 Add Change Order$1,870.00 .—Labor and Material -ROOF REPMR Add Change Order. S2,192.50—Lift t -NEVV AOOFJNG Total Contract Price- $330,412.50 • FrAV. t )fats -WATERPRO()NNG 44 OF WUNJENANCE SCOPE OF FORK Install matching finish 032 aJurninurn Iron gutter(approx. 95)at the eN-stray section, JnsWl one(1) drop of downspout at the,South side ofthe one--guiry section. install on ladditional LWE1486D AND INSURED drop of downspout at the at the West side of ihm iwo­story section and on (1)additional ch-op ofdownspout of the West side of ffic one-story section. Prim for the Wove scope of work adds$8,863,50 to the conuract price, SERVING Original ontract Price.-S330,412.50 SOUrN FLOARDA, Add Change, Order, v„ Labor and Material Total n atr rice` $359,276.00 Executedin this date day of __.....�... tl and a copy o'which was delivered to d receipt is hereby acknowledged by the Customer, Customer or Agent By f cpted ky t u a/ Omer-sign a«;, , � d Bob Hison&Company,Lnc, BY � (Sales Tgl�'4J"AAHfFO��I]��N3§Y=sN1CTi y � x FX3i YTUC4"lt£]RMUHi 'A 3 � p �W �} all NOI7 p4 yH�D�p�n(�1ry �yy��yy _.»�-,..r .. •.,),- ..,s4,.,...r.�.. , .:.�.„,�, _. .�..-.- .-.-=,r..�-,,...w..,�.-.,.W,r.,...-.. ..-.r-..-._ .-,,r,..-.,,--. .T.r-.,-,.r.... „-rw....--.-...,..-•-^. r,. ..-. _ ,,.. .. . _ ,- -r r S ' I {{ h ' t ! 1 9 r ml ( I i I j 10 3 I m ig WN wl k 6C' 1 I � r� - w i f G k 4� f j�..�. ,a�-. ��flY_1L615T�!""'��•`aA3� -r,nr=ie ��. M ' 7 Ek r r u �u cIIJ (I . Ira L e �,t yre8Lou M r 9� tom«rerw s v tV rrlxrIttlr`n" N - r _.w C .. —� I red 7, �IT�CT�iC�TI� 1111111 T�l TRL I; 7., y 1 t {{ t Hit It 9 � �"�� � � � fi�� ... 99 'tea a ..�.. W s 6 ' Y, t 10 w 1r, M 1 Alj� �H� y ' 1y2y ' 4"i9f. g �i L Ys Y10 I]I].7j I Q ElEl I El ❑1] E,,,.07 "0 0 0]I]E I] _ yeg �s y �gVpy y g yS.f MIND Nouvmm linav oNv Ald"911 NOHIVNVW T-TT-M P p q ................. ........... .............. El 12, Et tl tong ................ InT .......... ------------- - ;r 7— HIN jj �10 Yo pb Ell 11 P mo o i E El El El El El 0 S,L CD HUND No i i v)n a 3 1 AM"1311 NON IVHVWEE soil PaPt l, IT 5 ,YS L U.1 W top q 1L T cis J 01 Elu I II 7i 17 !-tr DUR I L ,-T PLO---I I--- 41,a - "J, PEDRO FALCON CONTRACTORS, INC. 31160 Avenue C,BIg Pine Keys 1 t ( m EC 13003416)'CGC 1607617 Request for Change Order o6 April 2021 Project: Marathon Library ONumber: o4o Description: Exterlor Lighting Revision Revise Flare Exterior lights(see attached)............................................................$7,126-oo PFCOverhead Cry 5%.................................................................................................$356.30 PFCProfit @ 5 .......................................................................................................$356.30 yle Tax.......y[.■y...�'.......... ... ............ .,... ......... ......... ......... .................. ......... ....._........I.. 3.51 SubtotalPFC C...............ii................ .........................a4Ie.YF.....,.........,. ....e.,w......... 80 .1 . P&P Bond1.1%of Total Cost................................................................... 9- , Total Requestfor Change OrderAnwunt......................................... , ,2.1.,E Materials lead times(8 to 12 weeks estintated)will exceed contract date.completion 7his item shall be consideredd not qffect substantial completion by authorization. Qfthis change order request. Respectfully Sub. fitted, n Ry lier Project Manager Industrial Commercial.institutionalResidential.Utility Established 1984 Date: Apr 1, 2021 Quote: MIA19-133640-15 Quote Page 111 Power& Lighting Systems, Inc. 3832 Shipping Avenue Miami FL 33146 Phone: (305)444-8520 Fax: (305)445-1948 Project Marathon Library and Adult Education From:r Jessica Ho=0 S Quote Ph: (305) 1 8520x122 Center-extra,flid and mtg plate Email:jhoyos@p4s.com Location Marathon! FL Quote MIA19-133640-15 To: Craig Cowan For ESI Old Date Aug 27, 2019 13395 NW 107 AVE Expires Sep 26, 2019 Hialeah Gardens FL 33018 Architect: Synalovs1d Rornanik Saye Phone, (305) 702-6001 Engineer: Delta G Engineers Fax: (305) 590-5709 EMail. cralg@electricalsuppliesinc.com QTY Type MFG Part Price Uo ExtPrice 1 H ABL IC04WC 40/15 AR LSS 400 MVOLT EZB JBX DN DNA $340.00 $340.00 1 H-PLATE ABL NO QUOTE Notes: plus freight quote good for 30 days. no info on adapter plate,so no quote Power&Lighting systems,inc.-Miarni Jessica l-loyos Page Ill a)Z 0 < c 0 E too 0 e e aR 0 m CD X U— z 0 CD OL N c 0 cL.G w :3 C-4 X w - 3 2 Ou-V-j 04 0 w C% < Ecm c 0 zcq OX: A 6 z alL I? LL z 0 ui (D UJ 2 CV5 WW CL I? (D E D cy Total Matmial Cosis Tool Mmehours 3,6637 -MAIA-0-51 WHA WX )A,-Nl:[p N( uNrr MALT.UNn LRS 1111 I A X4 —4 1 713.30 S 2"20 2 1 nI T", 'wJ"0-VIVI CH 3 37A 75. 4 OA 3 1 S 44.80 3 WAD- 0 OLOO 4 LUM go UP Fee s 255.00 9 255.00 I I I M 1 9 340JM 5 340,00 100 6 Fbdnft It Eadmowl PmW I Fv 11 t 50m 3 -SO.00 0,00 DATE REGAPULATION PEDRO FALCON SHEET ELECT.CONTIRS.NC FOR AlEff LO,011 DESCRIFTION mut dil _Labor Hours I&bor%ofconC LIGHTING s 3fi63-40 26.00 Branch Power s 0.00 Switch Gear s - 0,00 GENERATOR s 000 FireAtarm si - a Security sygtems $ 000 comm,mata 0 CCTV a Ligbit.ming Protection s a-DID Pulkic Addre&s s 0X0 Cathodic Protection 0.00 Misc. S 0110 TOTAL MATERIAL&MANHOURS S 3,663.40 26.00 100.6,0 MISCELLANEOUS MATERIAL 5 250,00 SUBTOTAL MATERIAL S 3,913AD TAX ON MATERIAL(7-112-1.) S TOTAL MATERIAL COST S 3,913A0 FOREMAN HOURS @ S RATE 45.00 3.9 S 175,50 JOURNEYMAN HOURS @ S RATE 26-00 S 910.00 LABOR HOURS @&RATE 5 -NAO s - TRAVEL I NON PRODUCTIVE I OVERTIME s - DIRECT LABOR-TOTAL COST s 1,05-50 PAYROLL TAXES&INS.-RATE s 412A9 PERMIT AND INSPECTION FEE I. $ - EQUIPMENT s 1,500.00 FUEL(GALLONS @ RATE) 5 30-0 S 15.00 TELEPHONE s - FREIGHT EXPRESS AND CARTAGE s SPECIAL EQUIPMENT s DRAWINGS SANITARY EXPENSKLOD,GING.MEALS s PROJECT TRAVEL(#OF TRIPS @ RATE) TOOLS("A OF LABOR) TOTAL JOB EXPENSE 5 2,127.49 TOTAL PRIME COST(MATERIAL EXP.) s 7,126,39 OVERHEAD% f s 5 7,126,39 SLJB-COtm&CT0R GUOTES LIG FNC—.—PROTECnON U0—MNfU14lL:A HUNS CATHODIC PROTECTION SUB-CONTRACTOR TOTAL Tax 3 SUB-CONTRACTOR GRAND TOTAL Sub Cent rocto r Mark up a 41t4 c 000 0.00 TOTAL NET COST s 7,126.39 ]PROFIT% $ SUBTOTAL s 7,126.39 BOND SELLING PRICE