Item F2
TIME APPROXIMATE PLEASE
BOARD OF COUNTY COMMISSIONERS
AGENDA ITEM SUMMARY
Meeting Date:
July 18. 19, 2001
Division: Public Works
Bulk Item: Yes _No ~
Department:
Enaineerina
AGENDA ITEM WORDING: Update from Bert Bender & Associates Architects, P.A. on the status of the
Gato Building Renovation Project.
ITEM BACKGROUND: Bender & Associates Architects, P.A. is providing the architectural services, and D. L.
Porter Construction is the contractor, for the renovation of the Gato Building.
PREVIOUS REVELANT BOCC ACTION: On March 13, 1997, BOCC approved a contract with Bender &
Associates Architects, P.A. for the services at the Old Navy Commissary Building (Gato Building). On November
12, 1998, the Board granted approval and authorized execution of a contract with Cross Environmental Services,
Inc. for the Selective Demolition & Abatement program (PHASE I). On July 21, 1999, the Board granted
approval and authorized execution of a contract with Lodge Construction for the renovation. On February 22,
2000, Lodge Construction was terminated. On April 19, 2000, the "Board granted approval to enter into contract
with D.L. Porter Construction to complete the Gato Building Renovation.
CONTRACT I AGREEMENT CHANGES: No changes to contract.
STAFF RECOMMENDATIONS: No action required.
TOTAL COST N/ A
BUDGETED: Yes N/A
No
COST TO COUNTY: N/A
REVENUE PRODUCING: Yes No X AMOUNT PER MONTH_ Year
APPRO~ED ~ ~ OMS/Purchasing _ ~k ~a~7"ent_
Item prepare~ ~~
Stephanie L. Coffer, Construction Manager David S. Koppel, P.E., County Engineer
~,~~
DIVISION DIRECTOR APPROVAL:
~ I ~iJ' Ivl
Dent Pierce, Division Director
DOCUMENTATION: Included
To Follow_
Not Required X
AGENDA ITEM # /..,~
DISPosmON:
Revised 2/27/01