Loading...
01st Change Order 04/16/2021 Change Order Request Project: Marathon International Airport Interior Terminal Rehab Change Order#: 1 Address: 9400 Overseas Highway,Marathon,FI,33050 Date Issued: 4/5/2021 Architect Project#: Owner: Monroe County Board of Commisioners GC Project#: Airport 1100 Simonton Street Contract For: Rehab Key West,Florida,33040 Architect: Jacobs Contractor: Design Center Inc 3150 SW 38th Avenue,STE 700 6677 Overseas Hwy Miami,Florida,33146 Marathon,Fl,33050 We Herein request changes in the Contract Sum and Contract Time for proposal Modifications to the Contract Documents described herein(Description Below) I accordance with Change Directives: Material ! Labor, ' to Subcontract Materials Labor,, <Subcontract, , itemriescript)an„1' �tt,�t;� �`d�rr`} -ra�,,.,,,'jlr, � ,;�),}� ' 'llant5 11Olf I''rri' U'njtCiait)"",',., UnitC4 Unit�Cast t:i� C4str�vu,�,Costr,�i,��y Gc9t t 4f Total, Ct ty"a j j ) Credit Adjust CBP Desks for Terrazzo Flooring 7 hr .$80.00 -$560.00 -$560.00 Install CBP Terazzo Flooring 14 sf .$41.20 $0.00 -$576.80 -$576.80 Re-install CBP Desks 7 LS -$80.00 -$560.00 -$560.00 Additional Purchase CBP Smartcell Pads 1 LS $0.00 $3,738.40 $3,738.40 Labor to Install CBP Smartcell Pads 8 hr $45.00 $360,00 $360.00 subtotal ;, 1,>l, hr a ;r ;�4i', S `'.st ri„ tf< r °i t�....�,P ,,t ) ,1"9a ii��7 '„�.,;, $2,401.60 OH&P(15%) $360.24 Bond&Insurance(2%) $48.03 PM Time for review,comment,pricing&coordinating 1 hr $105,00 $105.00 $105.00 $2,914.87 Monal Requested $2,914.87 Additional Days Requested 0 Attachments: Requested by:Design Center Inc Accepted By(Signed): Chris Nolan,E.I./Project Manager 4/5/2021 Accepted By(Print): 04.16.2021 _ ? 4/16/21 4.16.2021 3/16/2021 SmartCells Quotation SmartCells Quotation SATECH Contact o o o S m a r t(3e I'J's, Date: Mar 16, 2021 Brendan Downs SATECH Inc. Expiration Date: May 15, 2021 tel: 3606880496 PO Box 1264, 1769 Bishop Rd Num: 46899 cell: 3606880496 Chehalis, Washington 98532 Delivery Method: Ship bdowns@smartcellsusa.com tel: (360) 748-8711 fax: (360) 748-8822 Bill To Ship To Design Center Inc. Design Center Inc. Chris Nolan Chris Nolan Marathon, FL 33050 Marathon, FL 33050 US US tel: 631-680-4223 tel: 631-680-4223 chris@royal-crest.com chris@royal-crest.com Order Details Product Description _ _ Price Qty I Total _......®.._..�_._ _�...__._�_.�....m _...,_.._...®._._�.....��___ .._..Custom Mat .____,�.n...__... PLTFRM05 Black SmartCells Anti-fatigue Pad, 1/2"thick w/Smooth Top Surface(per sf) $14.83° 138 $2,046.54' PLNTCON Plant Configuration of Custom Platforms(per sq ft) $1.80 138 $248.40 BRUBRAMP05 Black Rubber Connecting Ramp for 1/2"thick Pads(0 to 1/2"over 2.5",per In ft) $5.65* 52 $293.80 ISCRN05 Inside Comer Ramp for 1/2"thick Pad(ea) $10.00 2 $20.00 OSCRN05 Outside Corner Ramp for 1/2"thick Pad(ea) 1 $10.00 6 $60.00 Subtotal $2,668.74 * A discount has a been applied. Your total order price without Totals the discount would have been $4,182.97; you have saved Taxable Product Total $2,668.74 $444.57. on-taxable Items Total $0.00 Names of Files Attached: Design Center Mat.PNG Shipping $869.50 Sales Tax: 7.5 /o $200.16 Total $3,738.40 Comments: ***Mat Fab*** Measurements are INCLUSIVE of Ramp. Signature Name & Title Date https://www.smartcellsusa.com/cc/print_as_quotation_old.php?show_discount=on&show_payment_method=&show_terms=&show_sub_areas=&show... 1/1 Change Order Attachment per Monroe County Code Section 2-58(b) • Change Order was not included in the original contract specifications. Yes ( ) No (X ) If Yes, explanation: • Change Order was included in the original specifications. Yes ( ) No (X ) If Yes, explanation of increase in price: • Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes( ) No(X ) If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order.Yes(X ) No ( ) If no,explanation of why: • Change Order is correcting an error or omission in design document. Yes ( ) No (X ) Should a claim under the applicable professional liability policy be made? Yes( ) No (X ) Explain: This Change order is changing the original intent and scope of work for the Terrazzo Flooring occurring in the CBP office area