Item C21BOARD OF COUNTY COMMISSIONERS
AGENDA ITEM SUMMARY
Meeting Date: May 15, 2013 Division: Public Works/Engineering
Bulk Item: Yes X No _ Department: Engineering
Staff Contact Person/Phone #: Judy Clarke X4329
AGENDA ITEM WORDING: Approval of Amendment 2 to the contract with Metric Engineering,
Inc. for Engineering Design and Permitting Services for the US 1 Bayside Shared Use Path Project to
extend the expiration date of the contract until December 1, 2013. This project is funded by the District
Three Transportation Impact Fees.
ITEM BACKGROUND: The community expressed a desire to construct the shared use path from
approximately MM 106 to MM 99.8 in Key Largo. The project is described in the draft Key Largo
Community Master Plan (2006).
PREVIOUS RELEVANT BOCC ACTION: In August 2010 the BOCC approved using $1,800,000
of District Three Transportation Impact Fees to design and construct a shared use path adjacent to US 1
(bayside) in Key Largo. In October 2011 the BOCC approved a contract with Metric Engineering, Inc.
for Engineering Design and Permitting Services. In June 2012 the BOCC approved Amendment One
adding Engineering Design and Permitting Services for a pedestrian bridge at Marvin Adams
Waterway (MM103) to be added to the scope of services.
CONTRACT/AGREEMENT CHANGES: Extends the date of completion for the project.
STAFF RECOMMENDATIONS: Approval as requested above.
TOTAL COST: $407,843.11 INDIRECT COST: n/a BUDGETED: Yes X No
DIFFERENTIAL OF LOCAL PREFERENCE: not applicable.
COST TO COUNTY: $407,843.11 SOURCE OF FUNDS: Dist. 3 Transportation Impact Fees
REVENUE PRODUCING: Yes No x AMOUNT PER MONTH Year
APPROVED BY: County Attyt OMB/Purchasing _ Risk Management
DOCUMENTATION: Included x Not Required
DISPOSITION: AGENDA ITEM #
revised 7/09
MONROE COUNTY BOARD OF COUNTY COMMISSIONERS
CONTRACT SUMMARY
Contract with: Metric Engineering, Inc.
Contract #
Effective Date:
October 19, 2011
Expiration Date:
December 1, 2013
Contract Purpose/Description:
Extend date of contract until December 1, 2013
Contract Manager: Judith Clarke
4329
Engineering/1
(Name)
(Ext.)
(Department/Stop #)
for BOCC meeting on 05-15-13
Agenda Deadline: 04-30-13
CONTRACT COSTS
Total Dollar Value of Contract: $ 407,843.11 Current Year Portion: $
Budgeted? Yes® No ❑ Account Codes: 1 30 - `LOI q - 5100 (030
Grant: $ - - - -
County Match: $ - - - -
217,014.23
ADDITIONAL COSTS
Estimated Ongoing Costs: $ /yr For:
(Not included in dollar value above) (e . maintenance, utilities, janitorial, salaries, etc.)
CONTRACT REVIEW
Changes Date Out
Date In Needed Reyi e
Division Director ��� �� Yes❑ Nob
Risk Management Yes❑ NoQ�
O.M.B./Purchasing
Yes[:] No[E]
--r - L
County Attorney 41" 7"
Yes❑ No[Z
3
I Comments:
OMB Form Revised 2/27/01 MCP #2
AMENDMENT 2 TO THE CONTRACT FOR ENGINEERING DESIGN AND PERMITTING SERVICES BETWEEN MONROE
COUNTY BOCC AND METRIC ENGINEERING INC. FOR
U.S 1 BAYSIDE SHARED USE PATH PROJECT
THIS AMENDMENT 2 to the CONTRACT is entered into this 15th day of May, 2013 between Monroe
County, whose address is 1100 Simonton Street, Room 2-216 Key West, Florida 33040, hereafter the "COUNTY"
and Metric Engineering Inc., a Corporation of the State of Florida, whose address is 13940 S.W. 136th Street, Suite
200, Miami, Florida 33186, hereafter referred to as "CONSULTANT".
WHEREAS, on the 19th day of October, 2011 the parties executed a contract authorizing the Consultant to
perform Professional Services for the Design and Permitting Services for the U.S. 1 Bayside Shared Use Path
Project for a sum not to exceed $284,943.00; and
WHEREAS, on the 201h day of June, 2012 the parties executed the First Amendment to the Contract with
Metric Engineering, Inc. for Engineering Design and Permitting Services for the U.S. 1 Bayside Shared Use Path to
include design for construction, completion and submission of all required permit applications and support during
the bid and construction phases of the Pedestrian Bridge at Marvin Adams Waterway (MM103) portion of the U.S.
1 Bayside Shared Use Path Project for an additional total not to exceed $122,900.11 with all requirements to be
completed no later than March 15, 2013; and
WHEREAS, site considerations and design decisions necessitate that the completion date of the design
contract be extended; and
WHEREAS, the COUNTY finds the extension of job duration and completion date for this project
reasonable:
NOW THEREFORE, in consideration of the mutual promises contained herein, the COUNTY and
CONSULTANT agree to amend Paragraph 7.1.2 of the contract as follows:
1. All requirements shall be completed no later than December 1, 2013,
in all other respects the Agreement dated October 19, 2011 and Amendment 1 dated June 20, 2012 remains in
full force and effect
In WITNESS WHEREOF each party hereto has caused this contract to be executed by its duly authorized
representative.
BOARD OF COUNTY COMMISSIONERS OF
MONROE COUNTY, FLORIDA
BY:
Mayor/ Chairman
(SEAL)
Metric Engineering Inc.
BY:
T1TL : 5I2, /.�✓i, f &l
Attest: Amy Heavilin, CLERK (SEAL)
Deputy Clerk
p Y
DATE: DATE: j t3�
APPROVED AS TO FOR
CHRISTINE M. LIMBERT-BA ROWS
ASSISTANT COUNTY ATTORNEY
Cate L4
k7 .
Contract for Engineering Design and Permitting Services for U.S. 1 Bayside Shared Use
Path.
THIS Contract (The AGREEMENT) made and entered into this 19th day of October, 2011 by
and between Monroe County, a political subdivision of the State of Florida, whose address is
1100 Simonton Street, Key West Florida, 33040, its successors and assigns hereinafter referred
to as the "COUNTY," through the Monroe County Board of County Commissioners (BOCC),
the Owner
=1
Metric Engineering, Inc., a corporation of the State of Florida, whose address is 13940 S.W.
136th Street, Suite 200, Miami, Florida 33186, its successors and assigns, hereinafter referred
to as "CONSULTANT",
WITNESSETH:
NOW, THEREFORE, in consideration of mutual promises, covenants and agreements stated
herein, and for other good and valuable consideration, the sufficiency of which is hereby
acknowledged, COUNTY and CONSULTANT agree as follows:
FORM OF AGREEMENT
ARTICLE I
REPRESENTATIONS AND WARRANTIES
By executing this Agreement, the CONSULTANT makes the following express representations
and warranties to the COUNTY:
1.1.1 The CONSULTANT shall maintain all necessary licenses, permits or other authorizations
necessary to act as CONSULTANT for the Project until the CONSULTANT'S duties
hereunder have been satisfied;
1.1.2 The CONSULTANT has become familiar with the Project site and the local conditions
under which the Project is to be designed, constructed, and operated;
1.1.3 The CONSULTANT shall prepare all documents required by this Agreement including,
but not limited to, all contract plans and specifications, in such a manner that they shall
be in conformity and comply with all applicable law, codes and regulations. The
CONSULTANT shall prepared as a part of this Contract all documents that will be
adequate and sufficient to accomplish the purposes of the Project, therefore, eliminating
any additional construction cost due to missing or incorrect design elements in the
contract documents;
1.1.4 The CONSULTANT assumes full responsibility to the extent allowed by law with
regards to his performance and those directly under his employ.
1.1.5 The CONSULTANT'S services shall be performed as expeditiously as is consistent with
professional skill and care and the orderly progress of the Project. In providing all
services pursuant to this agreement, the CONSULTANT shall abide by all statutes,
ordinances, rules and regulations pertaining to, or regulating such services, including
those now in effect and hereinafter adopted. Any violation of said statutes, ordinances,
rules and regulations shall constitute a material breach of this agreement and shall entitle
the COUNTY to terminate this agreement immediately upon delivery of written notice of
termination to the CONSULTANT.
1.1.6 At all times and for purposes under this agreement the CONSULTANT is an independent
contractor and not an employee of the Board of County Commissioners for Monroe
County. No statement contained in this agreement shall be construed so as to find the
CONSULTANT or any other of his/her employees, contractors, servants, or agents to be
employees of the Board of County Commissioners for Monroe County.
1.1.7 The CONSULTANT shall not discriminate against any person based on race, creed,
color, national origin, sex, age or any other characteristic or aspect which is not related,
in its recruiting, hiring, promoting, terminating, or other area affecting employment under
this agreement or with the provision of services or goods under this agreement.
ARTICLE II
SCOPE OF BASIC SERVICES
2.1.1 The CONSULTANT will perform for the COUNTY services as described in
Attachment A, Scope of Basic Services.
2.2 CORRECTIONS OF ERRORS, OMMISSIONS, DEFICIENCIES
2.2.1 The CONSULTANT shall, without additional compensation, promptly correct errors,
omissions, deficiencies, or conflicts in the work product of the CONSULTANT or its
subconsultants, or both.
2.3 NOTICE REQUIREMENTS
2.3.1 All written correspondence to the COUNTY shall be dated and signed by an authorized
representative of the CONSULTANT. Any notice required or permitted under this
agreement shall be in writing and hand delivered or mailed, postage prepaid, to the
COUNTY by certified mail, return receipt requested, to the following:
Ms. Judith Clarke, P.E.
Monroe County Engineering Services Department
1100 Simonton Street
Key West, FL 33040
And:
Mr. Roman Gastesi, Jr.
County Administrator
1100 Simonton Street
Key West, FL 33040
For the Consultant:
Mr. Frank Panellas, PE
Metric Engineering, Inc.
13940 SW 136 St., Suite 200
Miami, FL 33186
ARTICLE III
ADDITIONAL SERVICES
3.1 The services described in this Article III are not included in Basic Services. They shall
be paid for by the COUNTY as provided in this agreement as an addition to the compensation
paid for the Basic Services but only if approved by the COUNTY before commencement, and as
follows:
A. Providing services of CONSULTANT for other than the previously listed consulting
scope of Project provided as a part of Basic Services.
B. Providing any other services not otherwise included in this Agreement or not
customarily furnished in accordance with generally accepted consulting practice.
C. Providing representation before public bodies in connection with the Project, upon
approval by the COUNTY.
3.2 If Additional Services are required, such as those listed above, the COUNTY shall
issue a letter requesting and describing the requested services to the CONSULTANT. The
CONSULTANT shall respond with fee proposal to perform the requested services. Only after
receiving an amendment to the Agreement and a notice to proceed from the COUNTY, shall the
CONSULTANT proceed with the Additional Services.
ARTICLE IV
COUNTY'S RESPONSIBILITIES
4.1 The COUNTY shall provide full information regarding requirements for the project
including physical location of work, county maintained roads and maps.
4.2 The COUNTY shall. designate Monroe County Engineering Services Department to act
on the COUNTY'S behalf with respects to the Project. The COUNTY or Monroe County
Engineering Services Department shall render decisions in a timely manner pertaining to
documents submitted by the CONSULTANT in order to avoid unreasonable delay in the orderly
and sequential progress of the CONSULTANT'S services.
4.3 Prompt written notice shall be given by the COUNTY and its representative to the
CONSULTANT if they become aware of any fault or defect in the Project or nonconformance
with the Agreement Documents. Written notice shall be deemed to have been duly served if sent
pursuant to paragraph 2.3.
4.4 The COUNTY shall furnish the required information and services and shall render
approvals and decisions as expeditiously as necessary for the orderly progress of the Consultants
services and work of the contractors.
4.5 The COUNTY'S review of any documents prepared by the CONSULTANT or its
subconsultants shall be solely for the purpose of determining whether such documents are
generally consistent with the COUNTY'S criteria, as, and if, modified. No review of such
documents shall relieve the CONSULTANT of responsibility for the accuracy, adequacy, fitness,
suitability or coordination of its work product.
4.6 The COUNTY shall provide copies of necessary documents required to complete the
work.
4.7 Any information that may be of assistance to the CONSULTANT that the COUNTY
has immediate access to will be provided as requested.
ARTICLE V
INDEMNIFICATION AND HOLD HARMLESS
5.1.1 The CONSULTANT covenants and agrees to indemnify and hold harmless
COUNTY/Monroe County and Monroe County Board of County Commissioners from
any and all claims for bodily injury, including death, personal injury, and property
damage, including property owned by Monroe County, and any other losses, damages,
and expenses, including attorney's fees, court costs and expenses, which arise out of, in
connection with, or by reason of services provided by the CONSULTANT or
Subcontractor(s) in any tier, occasioned by the negligence, errors, or other wrongful act
or omission of the CONSULTANT in any tier, their employees, or agents.
5.1.2 The first ten dollars ($10.00) of remuneration paid to the CONSULTANT is for the
indemnification provided for above. The extent of liability is in no way limited to,
reduced, or lessened by the insurance requirements contained elsewhere within this
agreement. Should any claims be asserted against the COUNTY by virtue of any
deficiency or ambiguity in the plans and specifications provided by the CONSULTANT,
the CONSULTANT agrees and warrants that he shall hold the COUNTY harmless and
shall indemnify him from all losses occurring thereby and shall further defend any claim
or action on the COUNTY'S behalf.
5.1.3 In the event the completion of the project (to include the work of others) is delayed or
suspended as a result of the CONSULTANT'S failure to purchase or maintain the
required insurance, the CONSULTANT shall indemnify COUNTY from any and all
increased expenses resulting from such delays. Should any claims be asserted against
COUNTY by virtue of any deficiencies or ambiguity in the plans and specifications
provide by the CONSULTANT the CONSULTANT agrees and warrants that
CONSULTANT hold the COUNTY harmless and shall indemnify it from all losses
occurring thereby and shall further defend any claims or action on the COUNTY' S
behalf.
5.1.4 The extent of liability is in no way limited to, reduced or lessened by the insurance
requirements contained elsewhere within the Agreement.
5.1.5 This indemnification shall survive the expiration or early termination of the Agreement.
ARTICI N. Vi
PERSONNEL
6.1 PERSONNEL
The CONSULTANT shall assign only qualified personnel to perform any service concerning the
project. At the time of execution of this Agreement, the parties anticipate that the following
named individuals will perform those functions as indicated:
NAME
Frank Panellas, PE
Manuel Sauleda, PE
Charles Alfaro, PE
Fernando Larios
Manuel Inastrilla
Raj Krishnasamy, PE
Manuel Vera, Jr., PSM
FUNCTION
Project Manager
Chief Engineer
Project Engineer
Designer
Designer
Geotechnical Services
Surveying
So long as the individuals named above remain actively employed or retained by the
CONSULTANT, they shall perform the functions indicated next to their names. If they are
replaced the CONSULTANT shall notify the COUNTY of the change immediately.
ARTICLE VII
PAYMENTS
7.1 PAYMENT SUM
7.1.1 The COUNTY shall pay the CONSULTANT in current funds for the CONSULTANT'S
performance of this Agreement the Total Not to Exceed Lump Sum Amount of Two
Hundred Eighty -Four Thousand Nine Hundred Forty -Three and no cents
($284,943.00).
7.2 PAYMENTS
7.2.1 For its assumption and performances of the duties, obligations and responsibilities set
forth herein, the CONSULTANT shall be paid monthly.
(A) If the CONSULTANT'S duties, obligations and responsibilities are materially
changed by amendment to this agreement after execution of this Agreement,
compensation due to the CONSULTANT shall be equitably adjusted, either
upward or downward;
(B) As a condition precedent for any payment due under this Agreement, the
CONSULTANT shall submit monthly, unless otherwise agreed in writing by the
COUNTY, an invoice to the COUNTY requesting payment for services properly
rendered and reimbursable expenses due hereunder. The CONSULTANT'S
invoice shall describe with reasonable particularity the service rendered. The
CONSULTANT'S invoice shall be accompanied by such documentation or data
in support of expenses for which payment is sought that the COUNTY may
require.
(C) For the performance of the optional additional services and contingent additional
services described in Article III of this contract, provided same are first
authorized in writing by the COUNTY, the CONSULTANT shall be paid hourly
at the rates as negotiated.
7.3 REIMBURSABLE EXPENSES
7.3.1 Reimbursable expenses include expenses incurred by the CONSULTANT in the interest
of the Project:
a. Expenses of transportation submitted by CONSULTANT, in writing, and living
expenses in connection with travel authorized by the COUNTY, in writing, but only
to the extent and in the amounts authorized by Section 112.061, Florida Statutes;
b. Cost of reproducing maps or drawings or other materials used in performing the
scope of services;
c. Postage and handling of reports;
7A BUDGET
7.4.1 The CONSULANT may not be entitled to receive, and the COUNTY is not
obligated to pay, any fees or expenses in excess of the amount budgeted for this Agreement in
each fiscal year (October 1- September 30) by COUNTY'S Board of County Commissioners.
The budgeted amount may only be modified by an affirmative act of the COUNTY'S Board of
County Commissioners.
ARTICLE VIII
INSURANCE
8.1.1 The CONSULTANT shall obtain insurance as specified and maintain the required
insurance at all times that this Agreement is in effect. In the event the completion of the
project (to include the work of others) is delayed or suspended as a result of the
CONSULTANT'S failure to purchase or maintain the required insurance, the
CONSULTANT shall indemnify the COUNTY from any and all increased expenses
resulting from such delay.
8.1.2 The coverage provided herein shall be provided by an insurer with an A.M. Best
Rating of VI or better, that is licensed to do business in the State of Florida and that has
an agent for service of process within the State of Florida. The insurance certificate shall
contain an endorsement providing sixty (60) days notice to the COUNTY prior to any
cancellation of said coverage. Said coverage shall be written by an insurer acceptable to
the COUNTY and shall be in a form acceptable to the COUNTY.
8.1.3 CONSULTANT shall obtain and maintain the following policies:
A. Workers' Compensation insurance as required by the State of Florida, sufficient to
respond to Chapter 440 Florida Statutes.
B. Employers Liability Insurance with limits of $1,000,000 per Accident, $1,000,000
Disease, policy limits, $1,000,000 Disease each employee.
C. Comprehensive business automobile and vehicle liability insurance covering claims
for injuries to members of the public and/or damages to property of others arising
from use of motor vehicles, including onsite and offsite operations, and owned, hired
or non -owned vehicles, with One Million Dollars ($1,000,000.00) combined single
limit and One Million Dollars ($1,000,000.00) annual aggregate.
D. Commercial general liability, including Personal Injury Liability insurance covering
claims for injuries to members of the public or damage to property of others arising
out of any covered act or omission of the CONSULTANT or any of its employees,
agents or subcontractors or subconsultants, including Premises and/or Operations,
Products and Completed Operations, Independent Contractors; Broad Form Property
Damage and a Contractual Liability Endorsement with One Million Dollars
($1,000,000) per occurrence and annual aggregate.
An Occurrence Form policy is preferred. If coverage is changed to or provided on a
Claims Made policy, its provisions should include coverage for claims filed on or
after the effective date of this Agreement. In addition, the period for which they may
be reported must extend for a minimum of 48 months following the termination or
expiration of this Agreement.
E. Professional liability insurance of One Million Dollars ($1,000,000.00) per claim and
Two Million Dollars ($2,000,000.00) annual aggregate. If the policy is a "claims
made" policy, CONSULTANT shall maintain coverage or purchase a "tail" to cover
claims made after completion of the project to cover the statutory time limits in
Chapter 95 of the Florida Statutes.
F. COUNTY shall be named as an additional insured with respect to CONSULTANTS
liabilities hereunder in insurance coverage identified in Paragraphs C and D.
G. CONSULTANT shall require its subconsultants to be adequately insured at least to
the limits prescribed above, and to any increased limits of CONSULTANT if so
required by COUNTY during the term of this Agreement. COUNTY will not pay for
increased limits of insurance for subconsultants.
H. CONSULTANT shall provide to the COUNTY certificates of insurance or a copy of
all insurance policies including those naming the COUNTY as an additional insured
by including any subsection hereunder. The COUNTY reserves the right to require a
certified copy of such policies upon request.
I. If the CONSULTANT participates in a self-insurance fund, a Certificate of Insurance
will be required. In addition, the CONSULTANT may be required to submit updated
financial statements from the fund upon request from the COUNTY.
8.2 APPLICABLE LAW
This contract is governed by the laws of the State of Florida. Venue for any litigation arising
under this contract must be in Monroe County, Florida.
ARTICLE IX
MISCELLANEOUS
9.1 SECTION HEADINGS
Section headings have been inserted in this Agreement as a matter of convenience of reference
only, and that it is agreed that such section headings are not a part of this Agreement and will not
be used in the interpretation of any provisions of this Agreement.
9.2 OWNERSHIP OF THE PROJECT DOCUMENTS
The documents prepared by the CONSULTANT for this Project belong to the COUNTY and
may be reproduced and copied without acknowledgement or permission of the CONSULTANT.
CONSULTANT shall have no liability arising out of or relating to any use, reuse or modification
of the documents that occurs without the CONSULTANT's consent and professional
involvement outside of this project.
9.3 SUCCESSORS AND ASSIGNS
The CONSULTANT shall not assign or subcontract its obligations under this Agreement except
in writing and with the prior written approval of the Board of County Commissioners for Monroe
County and the CONSULTANT, which approval shall be subject to such conditions and
provisions as the Board may deem necessary. This paragraph shall be incorporated by reference
into any assignment or subcontract and any assignee or subcontractor shall comply with all of the
provisions of this Agreement. Subject to the provisions of the immediately preceding sentence,
each party hereto binds itself, its successors, assignees and legal representatives to the other and
to the successors, assigns and legal representatives of such other party. The CONSULTANT
shall not assign its right hereunder, except its right to payment, nor shall it delegate any of its
duties hereunder without the written consent of the COUNTY.
9.4 NO THIRD PARTY BENEFICIARIES
Nothing contained herein shall create any relationship, contractual or otherwise, with or any
rights in favor of, any third party.
9.5 TERMINATION
A. In the event the CONSULTANT shall be found to be negligent in any aspect of
service, the COUNTY shall have the right to terminate this Agreement after five days written
notification to the CONSULTANT.
B. The COUNTY may terminate this Agreement without cause by giving the other party sixty
(60) days written notice of its intention to do so.
9.6 CONTRACT DOCUMENTS
The contract documents consist of the Request for Qualifications (RFQ), any addenda, the Form
of Agreement (Articles I-XV), the CONSULTANTS response to the RFQ, the documents
referred to in the Form of Agreement as a part of this Agreement, and the attachments and
modifications made after execution. by written amendment. In the event any conflict between any
of those Agreement documents, the one imposing the greater burden on the CONSULTANT will
control.
9.7 PUBLIC ENTITIES CRIMES
A person or affiliate who has been place on the convicted vendor list following a conviction for
public entity crime may not submit a bid on contracts to provide any goods or services to a
public entity, may not submit a bid on a contract with a public entity for the construction or
repair of a public building or public work, may not submit bids on leases of real property to
public entity, may not be awarded or perform work as a contractor, supplier, subcontractor, or
consultant under a contract with any public entity, and may not transact business with any public
entity in excess of the threshold amount provided in Section 287.017 of the Florida Statutes, for
CATEGORY TWO for a period of 36 months from the date of being placed on the convicted
vendor list.
By signing this Agreement, CONSULTANT represents that the execution of this Agreement will
not violate the Public Entity Crimes Act (Section 287.133, Florida Statutes), Violation of this
section shall result in termination of this Agreement and recovery of all moneys paid hereto, and
may result in debarment from COUNTY' S competitive procurement activities.
In addition to the foregoing, CONSULTANT further represents that there has been no
determination, based on an audit that it or any subconsultant has committed an act defined by
Section 287.133, as "public entity crime", and that it has not been formally charged with
committing an act defined as a "public entity crime" regardless of the amount of money involved
or whether CONSULTANT has been placed on the convicted vendor list.
CONSULTANT will promptly notify the COUNTY if it or any subcontractor or
subconsultant is formally charged with an act defined as a "public entity crime" or has
been placed on the convicted vendor list.
9.8 MAINTENANCE OF RECORDS
CONSULTANT shall maintain all books, records, and documents directly pertinent to
performance under this Agreement in accordance with generally accepted accounting principles
consistently applied. Records shall be retained for a period of five years from the termination of
this Agreement. Each party to this Agreement or their authorized representatives shall have
reasonable and timely access to such records of each other party to this Agreement for public
records purposes during the term of the Agreement and for four years following the termination
of this Agreement. If an auditor employed by the County or Clerk determines that monies paid
to CONSULTANT pursuant to this Agreement were spent for purposes not authorized by this
Agreement, the CONSULTANT shall repay the monies together with interest calculated
pursuant to Sec. 55.03, FS, running from the date the monies were paid to County.
9.9 GOVERNING LAW, VENUE, INTERPERTATION, COST AND FEES
This Agreement shall be governed by and construed in accordance with the laws of the
State of Florida applicable to contracts made and to be performed entirely in the State. In the
event that any cause of action or administrative proceeding is instituted for the enforcement or
interpretation of this Agreement, COUNTY and CONSULTANT agree that venue will lie in the
16TH Judicial Circuit, Monroe County, Florida, in the appropriate court or before the appropriate
administrative body in Monroe County, Florida. This Agreement shall not be subject to
arbitration. The County and CONSULTANT agree that, in the event of conflicting
interpretations of the terms or a term of this Agreement by or between any of them the issue shall
be submitted to mediation prior to the institution of any other administrative or legal proceeding.
9.10 SEVERABILITY
If any term, covenant, condition or provision of this Agreement (or the application thereof to any
circumstance or person) shall be declared invalid or unenforceable to any extent by a court of
competent jurisdiction, the remaining terms, covenants, conditions and provisions of this
Agreement, shall not be affected thereby; and each remaining term, covenant, condition and
provision of this Agreement shall be valid and shall be enforceable to the fullest extent permitted
by law unless the enforcement of the remaining terms, covenants, conditions and provisions of
this Agreement would prevent the accomplishment of the original intent of this Agreement. The
County and CONSULTANT agree to reform the Agreement to replace any stricken provision
with a valid provision that comes as close as possible to the intent of the stricken provision.
9.11 ATTORNEY'S FEES AND COSTS
The COUNTY and CONSULTANT agree that in the event any cause of action or administrative
proceeding is initiated or defended by any party relative to the enforcement or interpretation of
this Agreement, the prevailing party shall be entitled to reasonable attorney's fees and court costs
expenses, as an award against the non -prevailing party, and shall include attorney's fees and
courts costs expenses in appellate proceedings, as an award against the non -prevailing party.
Mediation proceedings initiated and conducted pursuant to this Agreement shall be in accordance
with. the Florida Rules of Civil Procedure and usual and customary procedures required by the
circuit court of Monroe County.
9.12 BINDING EFFECT
The terms, covenants, conditions, and provisions of this Agreement shall bind and inure to the
benefit of the COUNTY and CONSULTANT and their respective legal representatives,
successors, and assigns.
9.13 AUTHORITY
Each party represents and warrants to the other that the execution, delivery and performance of
this Agreement have been duly authorized by all necessary COUNTY and corporate action, as
required by law.
9.14 CLAIMS FOR FEDERAL OR STATE AID
CONSULTANT and COUNTY agree that each shall be, and is, empowered to apply for, seek,
and obtain federal and state funds to further the purpose of this Agreement; provided that all
applications, requests, grant proposals, and funding solicitations shall be approved by each party
prior to submission.
9.15 ADJUDICATION OF DISPUTES OR DISAGREEMENTS
COUNTY and CONSULTANT agree that all disputes and disagreements shall be attempted to
be resolved by meet and confer sessions between representatives of each of the parties. If no
resolution can be agreed upon within 30 days after the first meet and confer session, the issue or
issues shall be discussed at a public meeting of the Board of County Commissioners. If the issue
or issues are still not resolved to the satisfaction of the parties, then any party shall have the right
to seek such relief or remedy as may be provided by this Agreement or by Florida law. This
provision does not negate or waive the provisions of paragraph 9.5 concerning termination or
cancellation.
9.16 COOPERATION
In the event any administrative or legal proceeding is instituted against either party relating to the
formation, execution, performance, or breach of this Agreement, COUNTY and CONSULTANT
agree to participate, to the extent required by the other party, in all proceedings, hearings,
processes, meetings, and other activities related to the substance of this Agreement or provision
of the services under this Agreement. COUNTY and CONSULTANT specifically agree that no
party to this Agreement shall be required to enter into any arbitration proceedings related to this
Agreement.
9.17 NON DISCRIMINATION
CONSULTANT and COUNTY agree that there will be no discrimination against any person,
and it is expressly understood that upon a determination by a court of competent jurisdiction that
discrimination has occurred, this Agreement automatically terminates without any further action
on the part of any party, effective the date of the court order. CONSULTANT and COUNTY
agree to comply with all Federal and Florida statutes, and all local ordinances, as applicable,
relating to nondiscrimination. These include but are not limited to: 1) Title VI of the Civil
Rights Act of 1964 (PL 88-352) which prohibits discrimination on the basis of race, color or
national origin; 2) Title IX of the Education Amendment of 1972, as amended (20 USC ss. 1681-
1683, and 1685-1686), which prohibits discrimination on the basis of sex; 3) Section 504 of the
Rehabilitation Act of 1973, as amended (20 USC s. 794), which prohibits discrimination on the
basis of handicaps; 4) The Age Discrimination Act of 1975, as amended (42 USC ss. 6101-6107)
which prohibits discrimination on the basis of age; 5) The Drug Abuse Office and Treatment Act
of 1972 (PL 92-255), as amended, relating to nondiscrimination on the basis of drug abuse; 6)
The Comprehensive Alcohol Abuse and Alcoholism Prevention, Treatment and Rehabilitation
Act of 1970 (PL 91-616), as amended, relating to nondiscrimination on the basis of alcohol
abuse or alcoholism; 7) The Public Health Service Act of 1912, ss. 523 and 527 (42 USC ss.
690dd-3 and 290ee-3), as amended, relating to confidentiality of alcohol and drug abuse patent
records; 8) Title VIII of the Civil Rights Act of 1968 (42 USC s. et seq.), as amended, relating to
nondiscrimination in the sale, rental or financing of housing; 9) The Americans with Disabilities
Act of 1990 (42 USC s. 1201 Note), as maybe amended from time to time, relating to
nondiscrimination on the basis of disability; 10) Any other nondiscrimination provisions in any
Federal or state statutes which may apply to the parties to, or the subject matter of, this
Agreement.
9.18 COVENANT OF NO INTEREST
CONSULTANT and COUNTY covenant that neither presently has any interest, and shall not
acquire any interest, which would conflict in any manner or degree with its performance under
this Agreement, and that only interest of each is to perform and receive benefits as recited in this
Agreement.
9.19 CODE OF ETHICS
COUNTY agrees that officers and employees of the COUNTY recognize and will be required to
comply with the standards of conduct for public officers and employees as delineated in Section
112.313, Florida Statutes, regarding, but not limited to, solicitation or acceptance of gifts; doing
business with one's agency; unauthorized compensation; misuse of public position, conflicting
employment or contractual relationship; and disclosure or use of certain information.
9.20 NO SOLICITATION/PAYMENT
The CONSULTANT and COUNTY warrant that, in respect to itself, it has neither employed nor
retained any company or person, other than a bona fide employee working solely for it, to solicit
or secure this Agreement and that it has not paid or agreed to pay any -person, company,
corporation, individual, or firm, other than a bona fide employee working solely for it, any fee,
commission, percentage, gift, or other consideration contingent upon or resulting from the award
or making of this Agreement. For the breach or violation of the provision, the CONSULTANT
agrees that the COUNTY shall have the right to terminate this Agreement without liability and,
at its discretion, to offset from monies owed, or otherwise recover, the full amount of such fee,
commission, percentage, gift, or consideration.
9.21 PUBLIC ACCESS
The CONSULTANT and COUNTY shall allow and permit reasonable access to, and inspection
of, all documents, papers, letters or other materials in its possession or under its control subject
to the provisions of Chapter 119, Florida Statutes, and made or received by the CONSULTANT
and COUNTY in conjunction with this Agreement; and the COUNTY shall have the right to
unilaterally cancel this Agreement upon violation of this provision by CONSULTANT.
9.22 NON -WAIVER OF IMMUNITY
Notwithstanding the provisions of Sec. 768.28, Florida Statutes, the participation of the
CONSULTANT and the COUNTY in this Agreement and the acquisition of any commercial
liability insurance coverage, self-insurance coverage, or local government liability insurance
pool coverage shall not be deemed a waiver of immunity to the extent of liability coverage, nor
shall any contract entered into by the COUNTY be required to contain any provision for waiver.
9.23 PRIVILEGES AND IMMUNITY
All of the privileges and immunities from liability, exemptions from laws, ordinances, and rules
and pensions and relief, disability, workers' compensation, and other benefits which apply to the
activity of officers, agents, or employees of any public agents or employees of the COUNTY,
when performing their respective functions under this Agreement within the territorial limits of
the COUNTY shall apply to the same degree and extent to the performance of such functions and
duties of such officers, agents, volunteers, or employees outside the territorial limits of the
COUNTY.
9.24 LEGAL OBLIGATIONS AND RESPONSIBILITIES
Non -Delegation of Constitutional or Statutory Duties. This Agreement is not intended to, nor
shall it be construed as, relieving any participating entity from any obligation or responsibility
imposed upon the entity by law except to the extent of actual and timely performance thereof by
any participating entity, in which case the performance may be offered in satisfaction of the
obligation or responsibility. Further, this Agreement is not intended to, nor shall it be construed
as, authorizing the delegation of the constitutional or statutory duties of the COUNTY, except to
the extent permitted by the Florida constitution, state statute, and case law.
9.25 NON -RELIANCE BY NON-PARTIES
No person or entity shall be entitled to rely upon the terms, or any of them, of this Agreement to
enforce or attempt to enforce any third -party claim or entitlement to or benefit of any service or
program contemplated hereunder, and the CONSULTANT and the COUNTY agree that neither
the CONSULTANT nor the COUNTY or any agent, officer, or employee of either shall have the
authority to inform, counsel, or otherwise indicate that any particular individual or group of
individuals, entity or entities, have entitlements or benefits under this Agreement separate and
apart, inferior to, or superior to the community in general or for the purposes contemplated in
this Agreement.
9.26 ATTESTATIONS AND TRUTH IN NEGOTATION
CONSULTANT agrees to execute such documents as the COUNTY may reasonably require
including a Public Entity Crime Statement, an Ethics Statement, and a Drug -Free Workplace
Statement. Signature of this Agreement by CONSULTANT shall act as the execution of a truth
in negotiation certificate stating that wage rates and other factual unit costs supporting the
compensation pursuant to the Agreement are accurate, complete, and current at the time of
contracting. The original contract price and any additions thereto shall be adjusted to exclude
significant sums by which the agency determines the contract price was increased due to
inaccurate, incomplete, or concurrent wage rates and other factual unit costs. All such
adjustments must be made within one year following the end of the Agreement.
9.27 NO PERSONAL LIABILITY
No covenant or agreement contained herein shall be deemed to be a covenant or agreement of
any member, officer, agent or employee of Monroe County in his or her individual capacity, and
no member, officer, agent or employee of Monroe County shall be liable personally on this
Agreement or be subject to any personal liability or accountability by reason of the execution of
this Agreement.
9.28 EXECUTION IN COUNTERPARTS
This Agreement may be executed in any number of counterparts, each of which shall be regarded
as an original, all of which taken together shall constitute one and the same instrument and any
of the parties hereto may execute this Agreement by singing any such counterpart.
AS"
By. \,_ %
Deputy Clerk
WHEREOF, each party caused this Agreement to be executed by its duly
sentative on the day and year first above written.
BOARD OF COUNTY COMMISSIONERS
L. KOLHAGE, Clerk OF MONROE CO NTY, FLORIDA
By:
Mayor/Chairman
Date: 444clt' /9, 20 11
(Seal)
Attest: MAa'I LEy
QrLt?G 924
WITNESS
METRIC ENGINEERING, INC:
By:
Title: k( I eJ I S-By:
WITNESS
MONROE COUNTY ATTC;
_APPROVED AS TO FORLR: ,
CHR18 WE M. LIMBBRT-BARROViS
ASSISTANT COUNTY ATTORNEY
Date 1/)� _
ATTACHMENT A
SCOPE OF BASIC SERVICES
Attachment A
Scope of Basic Services
The scope of services for the US 1 Shared Use Bayside Trail will include completion of design
for construction, completion and submission of all required permit applications and support
during the bid and construction phases of the project, as described below:
The Design for Construction shall include, but shall not necessarily be limited to, plans and
specifications which describe all systems, elements, details, components, materials, equipment,
and other information necessary for construction. The Design for Construction shall be accurate,
coordinated and in all respects adequate for construction and shall be in conformity, and comply,
with all applicable law, codes, permits, and regulations. Products, equipment and materials
specified for use shall be readily available unless written authorization to the contrary is given by
the County. The design plans must satisfactorily address drainage impacts to swales and
ditches, drop off treatments in areas of slope condition, potential encroachments and impacts to
wetlands and identify logical termini.
1.0 DESIGN DEVELOPMENT
The Consultant will develop the design of the shared use path for approval by the County. The
Consultant will obtain FDOT proposed US 1 southbound resurfacing plans and determine
available right of way from mile marker 106 to approximately mile marker 99.5. Where feasible
the desired path width is twelve feet. Design Development will include attending one community
workshop to obtain input from local residents to incorporate into the design where feasible.
2.0 CONSTRUCTION DOCUMENTS PHASE
2.1 The Consultant shall prepare, for approval by the County, Construction Documents
consisting of Drawings and Specifications setting forth in detail the requirements for the
construction of the project. Construction documents shall conform to Florida Department of
Transportation standards, and all Federal, State and local laws and guidelines, including but not
limited to the standards contained in the following:
Florida Department of Transportation Roadway Plans Preparation Manuals
http://www.dot.state.fl..us/rddesign/P.PMMantial/PPM .
sh tm
2. Florida Department of Transportation Design Standards
http://www.dot.state.fl.us/rddesignfDesignStandards/Stan.dards. shtm
3. Florida Department of Transportation Surveying Procedure
http://www2.dot.state.fl.us/proceduraldocuments/procedures/bin/550030101.pdf
4. Florida Department of Transportation Drainage Manual
http://www.dot.state.fl.us/rddesi.g.n/dr/files/2008 DrainageM:anual.pdf
5. Florida Department of Transportation Soils and Foundations Handbook
htt.D://www.dot.state.fl.u.s/stiuctures/ManLials/SFH.t)df
6. Florida Department of Transportation Structures Manual
littp://www.dot.state.fl.us/structures/manl.ib.sh.tni
7. Florida Department of Transportation Structures Manual including Temporary
Design Bulletins
http://www.dot.state.fl.us/struct-ires/maul ib.shtm
MUTCD
http://mutcd.fliwa.dot. ggov/
American Disabilities Act
http://www2.dot.state.fl.us/p.roceduraldocuments/procedures/bin/62502001,5.pd '
10. Florida Department of Transportation Flexible Pavement Design Manual
http://www.dot.state.fl.us/paavementmanagement/PUBLICATIONS.shtm
11. Florida Department of Transportation Rigid Pavement Design Manual
http://www.dot.state.fl.us/paverentmanagement/pcs/RigidPavementManualJanu
,-,i,IIT �ac
12. Federal Highway Administration Checklist and Guidelines for Review of
Geotechnical Reports and Preliminary Plans and Specifications
http://www.fbwa.dot.gov/en rii eeri.ng/geoteeb/DLibs/reviewgui.de/cbeck.list.cfin
13. Florida Department of Transportation Manual of Uniform Minimum Standards
for Design, Construction and Maintenance for Streets and Highways
httP://www.dot. st.ate.fl.us/rddesi t;n/FloridaGreenbook/2007/2007FloridaGreenboo
14. Florida Statutes
http://www.lea. state.fl.us/Statutes/i.ndex.cfin?.mode=V.Iew%,20Statutes&Submen.0
=1&Tab=statutes&CFID=14677574&CFTOKI N=80981948
Where conditions require deviating from FDOT standards the Consultant will apply for and
obtain all required variances prior to proceeding.
2.2. The Consultant shall provide Drawings and applicable Technical Special Provisions for
the County's review.
2.3 Upon completion of the Construction Documents Phase, the Consultant shall provide
Construction Documents for the County's approval. Upon approval by the County the Consultant
shall provide the County up to 5 sets of Construction Documents that have been signed and
sealed by the Engineer. The Consultant shall also provide an electronic version of the
construction documents. The Consultant shall provide an estimate of anticipated construction
cost in accordance with the construction development phase.
2.4 The Consultant shall assist the County in the preparation of the necessary bidding
information for the production of bidding forms, the Conditions of the Contracts, and the forms
of Agreements between the County and the Contractors by providing supporting_ information as
to the projects scope, bid items, estimated quantities and construction duration. The County shall
prepare all Bidding Forms, Conditions of the Contract, and Forms of Agreement.
2.5 The Consultant's construction documents (plans, specifications, etc) will conform to all
codes and regulations of the federal government, county, state, municipalities, agencies and state
departments, in effect at the date of this Agreement, and shall be of such completion as to be
acceptable for review and ruling by said agencies when permits are applied for. The Consultant
shall use due care in determining permit requirements and shall meet with regulatory agencies as
necessary to coordinate specific permit requirements. The Consultant shall document all
meetings and conversations with said regulatory agencies. If permits are denied for
incompleteness or for lack of following said codes or regulations, or permit requirements, then
the Consultant will conform the construction documents in such manner to receive permits upon
such plans. Work required by the Consultant to conform documents to federal, state, city, county,
or agency specifications to allow them to be approved shall be completed at no charge or cost to
the County, unless said requirements are changed during the course of the project.
2.6 The Consultant shall file (through the County) all documents required for the approval of
governmental authorities having jurisdiction over the project. The Consultant shall file (through
the County) the necessary documents to obtain Florida Department of Transportation (FDOT)
Right of Way permit, environmental resources permits, and all other permits required for
construction. The County shall be responsible for the timely submittal of all permit application
fees.
2.7 At intervals mutually agreeable to the County and Consultant, the Consultant shall
provide drawings and other documents which depict the current status of design for the County's
and, if required FDOT's review and information. At a minimum the Consultant shall provide
drawings for review at the 30% milestone (for public meeting), 60%, 90% milestones and 100%
milestone. The Consultant shall provide an estimate of anticipated construction costs.
2.8 As needed by the County, the Consultant will provide clarification and answers to
questions from prospective bidders during the construction bid process. Answers will be
provided in a timely manner in order to facilitate bidding.
3.0 CONSTRUCTION DOCUMENTS PHASE REQUIREMENTS
To satisfactorily perform the Construction Documents phase requirement, the Consultant must
complete the tasks set forth in items 3.1 through 3.5.
3.1 Survey — Obtain services of licensed surveyor for preparation of construction plans.
3.2 Construction Plans — This consists of, at a minimum, Key Sheet, Summary of Pay Items
and Quantities, Drainage Map, Project Layout, Plan and Profile sheets including locations of
existing utilities, Typical Sections, Detail sheets, General Notes, Stormwater Management Plan,
Traffic Control Plan. Construction plans shall be in accordance with FDOT Plans Preparation
Manual.
3.3 Specifications — For general specifications, FDOT Specifications will be incorporated.
Comprehensive, abbreviated methods, materials and systems descriptions in tune with the
drawings will be developed as necessary with Technical Special Provisions.
3.4 Schedules — Prepare an estimate of the Construction Time.
3.5 Estimate of Construction Cost — Estimate of anticipated cost in accordance with the
Construction Documents.
4.0 CONSTRUCTION PHASE
4.1 The Consultant shall review and approve or take other appropriate action upon
Contractor's Shop Drawings submittals for prefabricated elements to be placed permanently in
the structure but only for the limited purpose of checking for conformance with information
given and the design concept expressed in the Contract Documents. The Consultant's action shall
be taken with such reasonable promptness as to cause no delay in the Contractor's Work or in
construction by the County's own forces, while allowing sufficient time in the Consultant's
professional judgment to permit adequate review. In general, said review and action shall be
completed in 10 working days from receipt of a shop drawing submittal, excluding resubmittals.
Review of such submittals is not conducted for the purpose of determining the accuracy and
completeness of other details such as dimensions and quantities or for substantiating instructions
for installation or performance of equipment or systems designed by the Contractors, all of
which remain the responsibility of the Contractors to the extent required by the Contract
Documents. The Consultant's review shall not constitute approval of safety precautions or,
unless otherwise specifically stated by the Consultant, of construction means, methods,
techniques, sequences, or procedures. The Consultant will provide answers to Requests for
Information (RFI's) from the Contractor, as needed during construction.
4.2 The Consultant shall, without additional compensation, promptly correct any errors,
omissions, deficiencies, or conflicts in the work product of the Consultant or its consultants or
both.
4.3 The Consultant must reimburse the County for any added costs paid by the County during
construction that were incurred as the result of any error, omission, deficiency, or conflict in the
work product of the Consultant, its consultants, or both. This added expense is defined as the
difference in cost from that which the County would have paid if the work was included in the
bid, and the actual cost presented by the Contractor. The Consultant shall not be held responsible
for additional deficiencies found due to a delay in the construction of the project or for those
hidden deficiencies that could not reasonably be determined through a review of FDOT Bridge
Inspection Reports or physical inspection of a bridge by the Consultant.
5.0 CONSTRUCTION COST
Contemporaneously with the submission of the Design, the Consultant shall submit to the
County in writing its final estimate of the contractor's anticipated bid price for constructing the
Project. Once submitted, the final anticipated price estimate shall be adjusted by the Consultant
to reflect any increase or decrease in anticipated price resulting from a change in Design.
5.1 The Construction Cost shall be the total estimated bid cost to the County of all
elements of the Project designed or specified by the Consultant.
5.2 The Construction Cost shall include the cost at current market rates of labor and
materials and Equipment designed, specified, selected or specially provided for by the
Consultant, plus a reasonable allowance for Contractor's overhead and profit.
5.3 Construction cost does not include the compensation of the Consultant and the
Consultant's consultants, the costs of land, rights -of -way, financing or other costs which are the
responsibility of the County.
5.4 The Consultant agrees that, should the bid for construction of the project exceed its
estimate by ten percent (10%) or more, it will redesign, redraw or rebid, at no additional cost or
expense to the County, until the bids are within the stated limits unless such variations result
from reasons outside of the CONSULTANT'S reasonable control.
ATTACHMENT B
CONSULTANTS COST PROPOSAL
METRIC
ENGINEERING
Proposed Scope of Services for
Engineering Design and Permitting Services for the
US-1 Bayside Shared Use Path
Monroe County
The project "Engineering Design and Permitting Services for the US-1 Bayside Shared Use Path" consists of
developing design and construction documents for the addition of a shared use path adjacent to the north side of
US-1 from approximately mile markers 106 to approximately mile marker 99.5. The sections below describe in
further details the scope of services to be accomplished as part of this project. The effort and fee estimate associated
with the landscape architecture services has been included in this scope of services for review. The attached fee
estimate following the scope of services includes the associated effort for Tasks 3 to Tasks 8. Similarly, there are
detailed fee estimates attached for the geotechnical work to be performed by Tierra South Florida as well as the
surveying services to be performed by MG Vera & Associates.
Proiect General Tasks (Task 3.0):
The scope of this task includes preparation of all required exhibits and attendance to one public information meeting
to be held for this project. This task also includes the completion of the project's specifications package as well as
the maintenance of the contract for the duration of the project. In addition, scope includes attendance of the project
manager to critical meetings.
Roadwav Analvsis (Task 4.0):
Scope includes the design of the shared used path following FDOT requirements. As part of these services we will
prepare a proposed typical section package to be submitted to FDOT for approval. The design phase will include
the creation of the proposed shared used path alignment, proposed profile and proposed cross sections every 100
feet as required by FDOT. In addition, this task will also include the preparation and submittal to FDOT of a design
variation for all locations where the proposed shared use path will not be able to maintain a minimum width of 12
feet or a horizontal clearance of 4 feet to obstacles.
i-f ETPIC PLAZA • CCI..—La1PA-CE
i 3940 SYV. 136 Street, Miami, FL 331S6
Design: Suite '00 - CEL• Su;e 1 n?
Phone: (305) 235-5098-Fax: (30;) 251-5e941
r;cct. & Personnel Fax: (30 :) 235-52 1
wwvi.rnetriceng.con
ty '' METRIC
6;ENGINEERING
The roadway analysis will also include the analysis and design of any proposed signing and pavement marking
modifications, such as addition of crosswalks, relocation of signs, etc. In addition, this task includes the preparation
of two construction cost estimates during design as well as the field reviews needed by the technical staff.
Roadway Plans (Task 5.0):
This task includes the preparation of all the construction document plans for the proposed shared use path. This task
is based on three major submittals; one at approximately 60% , one at 90% and one final submittal. As part of this
task we will complete all the required plans including Key Sheet, summary of pay items, drainage maps, typical
section sheets, general notes sheet, summary of drainage structures, optional pipe sheet, plan sheets at scale 1:40,
profile sheets at scales 1:40, miscellaneous detail sheets, drainage structure sheets, storm water pollution prevention
plan, and the addition of the project network control information as provided by the surveyor.
Drainaze Analysis (Task 6.0):
This task will include all required analysis and documentation to ensure that the proposed drainage system satisfies
the requirements of the additional impervious area added by the shared use path. As part of this task, we will
determine base clearance water elevations based on geotechnical results and design a proposed drainage system
consisting of a combination of swales with ditch bottom inlets and French drains. We will also compile all the
design documentation and calculations into a drainage report to be submitted to Monroe County and FDOT for
review.
Utility Coordination (Task 7.0):
Scope includes requesting the existing information from all utilities within the project corridor to be included in the
proposed plans. These services also include coordinating with the utility companies if any relocations are required
to avoid utility conflicts.
Environmental Permits (Task 8.0):
As part of this project, we will review existing permits regarding easements, mitigation, conservation areas, related
commitments and other projects along proposed area of path to identify and minimize impacts. These services will
also include the required field investigations to confirm that there will not be any impacts to any existing wetlands.
The submittals to be included as part of these services include a letter report of findings, the completion of the
FDOT Permit Involvement Form, and the submittal of the request of exemption for the permit applications.
MF1-R;c PL.:i 7-n - Co r P1- H F--- A. D o L, F.a-r F.. RS
13940 I.W. 136 Stre c. !:Aialmi, F" 33186
Design: Suite 200 - CEI:'Suite 107
Phone: (30 ) 235-5098 - F.yx („'..>j . 1-- A9a
Acct. & Per_onne)
vd! ,ay. m. etri ce ncl.,. o n i-,
ire i
E N 5 1 N E E R I N a
Geotechnical Services:
Please refer to attached detailed scope of services and fee estimate from Tierra South Florida
Surveyinz Services:
Please refer to attached detailed scope of services and fee estimate from M.G. Vera & Asssociates.
IFTRt C PLA. 7. A - C' D R pol PATE t-, '. A. r-, 'nu Fz, Tcc PG
I q 9110 ISAV I 3C, hll;an I i, P- 1 9 6
Desion: ' ,., -) L I i t o 2 0 D - C E 1: S i r0 7'
Phone: i305) - Fax: `,305'1 1-5896,
Ar-,-T. K Personnel Fax (SOS)
I'll" "A"I'v. -M ell ice licl .Co M
ESTIMATE OF WORK EFFORT AND COST • PRIME CONSULTANT
Name of Project: US-1 Bayside Shared Use Path Consulant Name: Mobic Engineering, Inc.
County: Monroe County Consultant No.: r.-nte�'<onsultanis Vroj. �w�•cer
FPN: Data: Sit 5/2011
FAP No, E,bmator: FP
Houle From
Chief
Project
Senior
Prolecl
Secretary /
Staff Cl-'-
SUN Clacai-
Staff Claeai-
Staff CUaei-
Stiff Claesi-
Stall Cle„I-
SH
Salary
Average
9.
ClaaeificatU
•SIn
Engineer
Manager
Engineer
Englnoe,
Designer
Cledcal
libation 7
fution 9
fixation 9
fication 1e
ficatlon 11
ficatbn /2
Su
By
Coal By
Rate Per
E71i CC
s13
, ii 01
f•15. Ci`
•
J'7 Jr
Firm'
Actives
ActivityTaak
3. Project General and Prolecl Common Teak,
132
3
13
30
66
132
$5.203
$3942
4. Roadway Adaty,i,
630
13
63
63
145
315
32
671
$24,896
$39.46
5. Roadway Plana
735
15
74
74
169
368
37
737
$29.093
$39.47
6. Drainage An.I m
am
8
41
at
93
203
20
406
E16,030
$39.48
7. Ulililies
52
1
5
5
12
26
3
52
E2,G37
E39.17
8. Environmenlal Permits. Compliance 6 Clearance,
43
1
4
4
10
22
2
43
E11658
$39.26
9. Structures - Misc. Task,, DWgs, N-Tech.
#DIVl01
10. Structures -Bridge Development Repon
#DIV/01
11. Structure, -Temporary Bridge
#DIV101
12. Structures -Shod Span Concrete Sn,ge
#DN/0!
13. Structures - Medium Span Conerele Bridge
0DIV/01
14. Slruclure,-Shucl-I Steel Bridge
pDIV/0!
15. Structures -Segmental Concrete Bridge
pDIV/01
16. Suuclurea - Movable Span
p'wQ
17. Structures - Relalning Walls
pDIV/o.
18. Structures - Miscellaneous
pDIV/0!
19. Sgning 8 pavement Marking Anaty,Ia
pDIVlOt
20. Signing 8 Pavement MaMir Plans
bG Vm
21. Sgnaf ation Analy,i,
p01V/OI
22. Slpnel¢alion Plans
zV/01
27. Lighting Anatyais
NDIV/01
24. Ugtding Plans
pDIV/01
25. Landscape Architecture Analysis
#01V/0!
26. landscape Architecture Plans
#D1VmI
21. Survey (Fwld 8 Olbce Suppod)
pDIV/01
26. Photo9rammetry
'DIV)0! .
29. Mapping
pDIV/01
W Gaolechnical
SOIV101
31. A'e belure Development
SDIV10!
32. Name Bali- Impact Design A,sessme.
pDIV/0!
33. Inlellgenl TUn,podalion Sy,tems Analy,is
#DIV/DI
34. Intelligent Tranepodalion Syetertn Plans
pDIV/01
T-I Staff Hour,
1.996
41
2W
2D0
459
1,OD0
101
2.001
Total Staff Coal
1
$2,870.00
E/3,000.W
E10,000.00
$W.655.W
E30,000.00
E2,424,W
E111149.00
$39.45
Survey Field Days by Subconaukanl
4 - Person Crew:
Note,:
1. This sheet to be used by Pnme Cons-rd to calculate the G,br Total he.
2. Manually enle, lee hom each subcomuitanl. Unused s,bc,naubnI row, may be Ndden.
Fee -.1 Flap.1-limationForm¢ Meak -Revised 9.1S11
ric Pega 5 of 15
SALARY RELATED COSTS:
OVERHEAD:
OPERATING MARGIN: +u
FCCM (F,614i s Capital Coat Money): -
EXPENSES:t
9-men crew
S=ey (FleM - if by Prime) days
SUBTOTAL ESTIMATED FEE:
Geolechnical: TUm South Florid,
Survey: MG Vera 8 Ae boo e,
SUBTOTAL ESTIMATED FEE:
OPTIONAL SERVICES ESTIMATED FEE;
LaMacapinp: SWC
Public InvoNament: To be done by Monroe County
GRAND TOTAL ESTIMATED FEE:
Check= $78,949.00
E78,949.D0
E134,B00.16
$20,526.74
$388.43
$6.976.50
/day
$243,740.83
$284,943.04
$284.943.04
oil 5/201I
First Amendment to the Contract with Metric Engineering, Inc. for
Engineering Design and Permitting Services for the U.S. 1 Bayside
Shared Use Path
This Contract Amendment is made and entered into this 201h day of June, 2012 by and between
Monroe County, whose address is 1100 Simonton Street, Room 2-216, Key West, Florida
33040 hereafter the "County", and Metric Engineering, Inc. a corporation of the State of Florida,
whose address is 13940 S.W. 136th Street, Suite 200, Miami, Florida 33186, its successors
and assigns, hereinafter referred to as "CONSULTANT",
Article 11 SCOPE OF BASIC SERVICES is amended to include:
Paragraph 2.1.2
The CONSULTANT will perform design for construction, completion and submission of all
required permit applications and support during the bid and construction phases of the
Pedestrian Bridge at Marvin Adams Waterway (MM 103) portion of the US 1 Bayside Shared
Use Path Project as described below and in Consultant's proposal included as Attachment A:
The scope of services for the US 1 Bayside Shared Use Path Pedestrian Bridge will include
development and completion of design for construction, permit applications and support during
the bid and construction phases of the project. All work will be conducted in accordance with
current FDOT, State and Federal requirements.
The Design for Construction shall include, but shall not necessarily be limited to, plans and
specifications which describe all systems, elements, details, components, materials, equipment,
and other information necessary for construction. The Design for Construction shall be accurate,
coordinated and in all respects adequate for construction and shall be in conformity, and
comply, with all applicable law, codes, permits, and regulations. Products, equipment and
materials specified for use shall be readily available unless written authorization to the contrary
is given by the County.
2.1.2.1. DESIGN DEVELOPMENT (PRELIMINARY DESIGN AND PERMITTING)
The Consultant will develop the design of the Bayside Shared Use Path Pedestrian Bridge over
Marvin Adams Waterway. The design will conform to Florida Department of Transportation
(FDOT) standards, and all local, state and federal laws. Design will be sufficient to obtain all
required permits including FDOT right of way permit. This task includes completion of the
Bridge Development Report and environmental permits, compliance and clearances work.
Consultant will proceed with Optional Services (Bridge Hydraulic Report) only if determined
upon completion of preliminary design phase that the report is required.
2.1.2.2 CONSTRUCTION DOCUMENTS (FINAL DESIGN AND CONSTRCTION)
2.1.2.2.1 Based on the Design Development Documents and any further adjustments
authorized by the County in the scope or quality of the Project, the Engineer shall prepare, for
approval by the County, Construction Documents consisting of Drawings and Specifications
setting forth in detail the requirements for the construction of the project. Construction
Amend 1 to US 1 Bayside Trail
Metric Eng.
Page 1 of 6
documents shall conform to all local, state and federal laws and the standards contained in the
most current version of the following:
Florida Department of Transportation Roadway Plans Preparation Manuals
httn:. lwww.dot.state.fl.us/rddes4m/PPMManual/PPM.shtm
2. Florida Department of Transportation Design Standards
htt :,'.www.dot.state.fl.us/rddesi *n/Desi *nStandards/Standards.shtm
3. Florida Department of Transportation Surveying Procedure
http: 'www2.dot.state.tl.us/proceduraldocuments/t)rocedures/bin/550030101.pdf
4. Florida Department of Transportation Drainage Manual
ht :: www. dot. state.fl.us/rddesi gn/dr/files/2008Draina ReManual. pdf
5. Florida Department of Transportation Soils and Foundations Handbook
httn::"; www.dot.state.fl.us/structures/Manuals/SFH.pdf
6. Florida Department of Transportation Structures Manual (625-020-018) including
Temporary Design Bulletins
h. www.dot.statc.fl.us/structures/StructuresManual/CurrentRelease.'STRManual.hti-n
7. MUTCD
ht : /mutcd.ihwajot. govl
8. American Disabilities Act
htt ://www2. dot,state.tl.us/ roce(luraldocuments! rocedures/bin/625020015. )df
Florida Department of Transportation Pavement Coring and Evaluation Procedure
http://www.dot.state.fl. us/statematerialsoffice/administration/resources/library/pubIicatio
nshnaterialsmanuo I/documents/v 1-section32-clean, 0
to. Florida Department of Transportation Flexible Pavement Design Manual
ht ://www.dot.state.fl.us/ avementmana ,ctnent/PUBL.ICATI.ONS.slitm
1 1. Florida Department of Transportation Rigid Pavement Design Manual
12. Federal Highway Administration Checklist and Guidelines for Review of Geotechnical
Reports and Preliminary Plans and Specifications
http://www.fliwa.dot. og v/cn vze cering/geoteCll/pubs/rcviewguide/cliecklist.cfm
13. Florida Department of Transportation Manual of Uniform Minimum Standards for
Design, Construction and Maintenance for Streets and Highways
http://www.dot.state.fl.us/i•ddesign/FloridaGreenbook/2007/20071= loridaGreenbook.pdf
14. Florida Statutes
httD://www.leiz.state.fl.us/Statutes/index.cfm?Mode=View%20$tatutcs&Submcnu= I &Ta
Amend 1 to US 1 Bayside Trail
Metric Eng.
Page 2 of 6
b- statutcs&CFiD=14677574&CFTOKEN-80981948
15. Florida's Bicycle Facilities Planning and Design Handbook.
http* www.dot.state.fl.us/safetyped bike ped bike standards.hIm#Florida%20Bikc%20
Handbook
16. AASHTO Guide for the Development of Bicycle Facilities
ht :. 'www.sccitc.or T/bikes AASHTO 1999 BikeBook. df
17. Florida's Quality/Level of Service Handbook for Planning
htt : www.dot,state,fl.us/l)lanniniz/systeiiis/sm/los/los sw2.htm
18. A Policy on Geometric Design of Highways and Streets, American Association of State
Highway and Transportation Officials (AASHTO Green Book) (GDHS-5 AASHTO
Bookstore).
19. The Highway Capacity Manual (Transportation Research Board)
httn�' 'gulliver.trb.orkTJbookstore/
20. FDOT Standard Specifications for Road and Bridge Construction (with supplemental
specifications).
ht :i www.dot.state.fl.us/S ecifiicationsofficc/2007B.K/TOC.htm
21. Facilities Design Manual (Topic No. 625-020-016-a)
htt :;`fwww.dot.state.fl.us/structuredManuals/2002fdotfacilitiesmantial. df
22. AASHTO LRFD Bridge Design Specifications (Mandatory beginning 2007) (AASHTO
Bookstore `4-LRFDUS-4')
23. Right of Way Mapping Procedure (Topic No. 550-030-015-e)
ht!R:/,'www.dot.state.fl.us/surveyingaad mapping/RWMani)linaHandbook.pdf
24. Project Development and Environmental Manual Par 1 and 2 (Topic No. 650-000-001).
http:.`:'www,dot.state.fl.us, emo/pbs/pdeman.litm
Where FDOT design standards cannot be met the Consultant will request a design variance or
exception.
2.1.2.2.2 The Consultant shall provide Drawings and applicable Technical Special
Provisions to the County for the County's and FDOT's review at the 60%, 90% and 100%
stages of the project. The Consultant shall respond to questions resulting from County and
FDOT review and incorporate any required revisions to the construction drawings and
specifications. Design calculations package will be submitted with the 100% phase construction
drawings.
2.1.2.2.3 The Consultant will provide a construction cost estimate and a project schedule
at each phase submittal.
2.1.2.2.4 Upon completion of the Construction Documents Phase, the Consultant shall
provide Construction Documents for the County's approval. Upon approval by the County the
Consultant shall provide the County up to 5 sets of Construction Documents that have been
signed and sealed by the Engineer. The Consultant shall also provide an electronic version of
the construction documents.
2.1.2.2.5 The Consultant shall assist the County in the preparation of the necessary
bidding information for the production of bidding forms, the Conditions of the Contracts, and the
Amend 1 to US 1 Bayside Trail
Metric Eng.
Page 3 of 6
forms of Agreements between the County and the Contractors by providing supporting
information as to the projects scope, bid items, estimated quantities and construction duration.
The County shall prepare all Bidding Forms, Conditions of the Contract, and Forms of
Agreement.
2.1.2.2.6 The Consultant's construction documents (plans, specifications, etc.) will conform
to FDOT's requirements, to all codes and regulations of the federal government, county, state,
municipalities, agencies and state departments, in effect at the date of this Agreement, and shall
be of such completion as to be acceptable for review and ruling by said agencies when permits
are applied for. The Consultant shall use due care in determining permit requirements and shall
meet with regulatory agencies as necessary to coordinate specific permit requirements. The
Consultant shall document all meetings and conversations with said regulatory agencies. If
permits are denied for incompleteness or for lack of following said codes or regulations, or
permit requirements, then the Consultant will conform the construction documents in such
manner to receive permits upon such plans. Work required by the Consultant to conform
documents to federal, state, city, county, agency or FDOT specifications to allow them to be
approved shall be completed at no charge or cost to the County, unless said requirements are
changed during the course of the project.
2.1.2.2.7 The Consultant shall file (through the County) all documents required for the
approval of governmental authorities having jurisdiction over the project. The Engineer shall file
(through the County) the necessary documents to obtain Environmental Resource Permits,
Florida Department of Transportation right of way permit and all other permits required for
construction. The County shall be responsible for the timely submittal of all permit application
fees.
2.1.2.2.8 As needed by the County, the Consultant will provide clarification and answers to
questions from prospective bidders during the construction bid process. Answers will be
provided in a timely manner in order to facilitate bidding.
2.1.2.3. CONSTRUCTION PHASE
2.1.2.3.1 The Consultant will respond to Contractor's requests for information (RFI's). The
Consultant shall review and approve or take other appropriate action upon Contractor's Shop
Drawings submittals for prefabricated elements to be placed permanently in the structure but
only for the limited purpose of checking for conformance with information given and the design
concept expressed in the Contract Documents. The Consultant's action shall be taken with such
reasonable promptness as to cause no delay in the Contractor's Work or in construction by the
County's own forces, while allowing sufficient time in the Consultant's professional judgment to
permit adequate review. In general, said review and action shall be completed in 10 working
days from receipt of a shop drawing submittal, excluding resubmittals. Review of such
submittals is not conducted for the purpose of determining the accuracy and completeness of
other details such as dimensions and quantities or for substantiating instructions for installation
or performance of equipment or systems designed by the Contractors, all of which remain the
responsibility of the Contractors to the extent required by the Contract Documents. The
Consultant's review shall not constitute approval of safety precautions or, unless otherwise
specifically stated by the Consultant, of construction means, methods, techniques, sequences,
or procedures.
Amend 1 to US 1 Bayside Trail
Metric Eng.
Page 4 of 6
2.1.2.3.2 The Consultant shall, without additional compensation, promptly correct any
errors, omissions, deficiencies, or conflicts in the work product of the Consultant or its
consultants or both.
2.1.2.3.3 The Consultant must reimburse the County for any added costs paid by the
County during construction that were incurred as the result of any error, omission, deficiency, or
conflict in the work product of the Consultant, its consultants, or both. This added expense is
defined as the difference in cost from that which the County would have paid if the work was
included in the bid, and the actual cost presented by the Contractor.
2.1.2.3.4 Upon completion of construction the Consultant will submit 2 sets of signed and
sealed record drawings and one set in CADD format on CD based on the Contractors red -line
as built drawings. Updated design calculations will be submitted if different from 100% phase
submittal.
2.1.2.4. CONSTRUCTION COST
Contemporaneously with the submission of the Design, the Engineer shall submit to the County
in writing its final estimate of the contractor's anticipated bid price for constructing the Project.
Once submitted, the final anticipated price estimate shall be adjusted by the Engineer to reflect
any increase or decrease in anticipated price resulting from a change in Design.
2.1.2.4.1 The Construction Cost shall be the total estimated bid cost to the County of all
elements of the Project designed or specified by the Engineer.
2.1.2.4.2 The Construction Cost shall include the cost at current market rates of labor and
materials and Equipment designed, specified, selected or specially provided for by the
Engineer, plus a reasonable allowance for Contractor's overhead and profit.
2.1.2.4.3 Construction cost does not include the compensation of the Engineer and the
Engineer's consultants, the costs of land, rights -of -way, financing or other costs which are the
responsibility of the County.
2.1.2.4.4 The Consultant agrees that, should the bid for construction of the project exceed its
estimate by ten percent (10%) or more, it will redesign, redraw or rebid, at no additional cost or
expense to the County, until the bids are within the stated limits unless such variations result
from reasons outside of the Consultant's reasonable control.
Article VIII Payments is amended to include:
Paragraph 7.1.2
The Consultant shall be paid monthly for the Pedestrian Bridge design and permitting; the
following not to exceed amounts will apply for each phase of the project:
Design Development (Preliminary Design) $37,923.01
Construction Documents/Construction Phase $54,492.36
Bridge Hydraulic Report (if required) $30,484.74
Total Lump Sum Fee
$122,900.11
Amend 1 to US 1 Bayside Trail
Metric Eng.
Page 5 of 6
All requirements shall be completed no later than March 15, 2013 for total not to exceed fee of
One Hundred twenty-two thousand nine hundred dollars and eleven cents ($122,900.11).
IN WITNESS WHEREOF each party hereto has caused this Contract to be executed by its duly
authorized representative on the day and year first written above.
(SEAL)
Attest: DANNY L. KOLHAGE, CLERK
Deputy Clerk
(SEAL)
A.itestZlv/
:
1'=
Title *ly
BOARD OF COUNTY COMMISSIONERS
OF MONROE COUNTY, FLORIDA
By
- /Ox
Mayor/Chair n
METRIC ENGINEERING, INC..
By
Title _ 1 ,. tiJ l t - rl t 1:> �
MONROE COUNTY ATTORNEY
APPRPVED AS TO FORM:
CKRISTINE M. LIMBERT•BARROWS
ASSISTANT COUNTY ATTORNEY
Date (o ! ►11
Amend 1 to US 1 Bayside Trail
Metric Eng.
Page 6 of 6
ATTACHMENT A
CONSULTANT'S PROPOSAL
METRIC
ENGINEERING
Proposed Scope of Services for
Engineering Design and Permitting Services for the Pedestrian Bridge along
US-1 Bayside Shared Use Path over Marvin D. Adams waterway
Monroe County
The project "Engineering Design and Permitting Services for the US-] Bayside Shared Use Path" consists of
developing design and construction documents for the addition of a shared use path adjacent to the north side of US-
1 from approximately mile markers 106 to approximately mile marker 99.5. The proposed supplemental scope
includes the design of a new pedestrian bridge crossing the Marvin D. Adams waterway. The sections below
describe in further details the scope of services to be accomplished as part of this project. The effort and fee
estimate associated with the landscape architecture services has been included in this scope of services for review.
The attached fee estimate following the scope of services includes the associated effort for Tasks 5, 6, 8 to 10 and
Tasks 13. Similarly, there are detailed fee estimates attached for the geotechnical work to be perfor=4 by Tierra
South Florida as well as the surveying services to be performed by MG Vera & Associates.
Project General Tasks (Task 3.0Z:
Included under the general scope for the Shared Used Path.
Roadway Plans (Task 5.0):
Scope includes the preparation of the Bridge Hydraulic Recommendation Sheet for the proposed structure. This
particular task can be considered optional services, if coordination with FDOT during the execution of Task 10
warrants the sheet is not required by minimizing impacts to the waterway.
Drainaee Analysis (Task &01:
Scope includes the preparation of the Bridge Hydraulic Report for the proposed structure. This particular task can be
considered optional services, if coordination with FDOT during the execution of Task 10 warrants the sheet is not
required by minimizing impacts to the waterway.
METR[r ALA24. - CORRORATe HCAOglr.a RTEr7
I39-Vi SIN 136 $1reet. Miami. F1, 331665
Or-, ran: Suite 2C0. CEI: Suite 107
Ph,)ne' (305) 235.5098 • Fah: (305) 2S, 56N
Acct. & pr-rsnnnel fax: 605; 23-.5271
v>:Ltin^;.rnEt rj�ZntJ.Gtl m
METRIC
ENGINEERING
Environmental Permits (Task 8.0):
As part of this project, we will review existing permits regarding easements, mitigation, conservation areas, related
commitments and other projects along proposed area of path to identify and minimize impacts. These services will
also include the required field investigations to confirm that there will not be any impacts to any existing wetlands.
The submittals to be included as part of these services include a letter report of findings, the completion of the
FDOT Permit Involvement Form, and the submittal of the request of exemption for the permit applications. This
task also includes the preparation of permit application as per attached fee estimate Task 8 form -
Structures — Summary and Miscellaneous Tasks and Drawin s ask 9 0 :
As part of this project, we will prepare general drawings, construction cost estimates and specifications, conduct
field reviews and attend technical coordination meetings as listed in the summary form attached.
Structures —Bridge Development Report (Task 10.):
As part of this project, we will prepare a detailed report outlining the possible types of structures feasible for the
intended used and location of this pedestrian bridge. A maximum of three alternatives are anticipated and include:
Prestrassed Beam Structure, Steel Girder Structure and utilization of a prefabricated bridge. The report will also
evaluated the most feasible foundation system for all superstructure alternatives.
Structure — Medium San Concrete Bride Task 13.0 :
As part of this project, we will prepare detailed construction plans and structural calculations for the selected bridge
alternative. All calculations and drawings will follow the current edition of the FDOT Structures Design Guidelines
and the AASHTO LRFD Guide Specifications for the Design of Pedestrian Bridges.
Geotechnical Services:
Please refer to attached detailed scope of services and fee estimate from Tierra South Florida
SurVerft Services:
Please refer to attached detailed scope of services and fee estimate from M.G. Vera & Associates.
Mr-rRIG PLAZA •' �',ORrORAYE: H1:'ADWUA1R*rF-fi3
1394) S W 135 Street. (amt Ft 33185
Design, Suits 200 - CEO: Suite 10?
Phone: 1345) 235-5098 - Fax {305) 351-5S9 }
Acct. & Personneel Fax: (305) 235-52 71
Y.•V 1-'uVletrlrenq.CDrn
tierra
SOUTH FLORIDA
November 18, 2011
Mr. Oscar Cruz
Metric Engineering, Inc.
13940 SW 136 Street, Suite 200
Miami, Florida 33186
Re: Proposal for Geotechnical Services
Proposed Pedestrian Bridge
Key Largo, Florida
TSF Proposal No.: 1111-386
Dear Oscar:
As requested, TIERRA SOUTH FLORIDA, INC. (TSF) is pleased to submit this proposal for the
above -referenced project. This proposal includes an outline of our proposed scope of work, an
estimate of the total fees, and our anticipated schedule for completion of the work.
PROPOSED SCOPE OF WORK
We understand that geotechnical investigation is required to explore the subsurface conditions at the
proposed pedestrian bridge. We understand that the proposed pedestrian bridge will be 120' long
and 14' wide simple span bridge.
To explore the subsurface conditions, we proposed to drill two (2) SPT borings to a depth of 60 feet
below existing grade.
Boring locations will be approximately located and noted in the held byour personnel by measuring
distances with a tape from known reference points. Elevations at boring locations can be interpreted
from topographic plans if furnished by others. Prior to drilling at the project site, TSF will notify the
local utility companies and request that underground utilities be marked. Our experience, however,
is that the utility companies will not mark privately owned utilities. Private owned utility need to be
identified by others. The study will be summarized in accordance with the FDOT's Soil and
Foundation Manual.
270S VISTA PARKWAY. SVITF 10 • wFsr PAI" RFACH, fTORIT)A 33411
(5011687 8537 • FAX 4361.) 687 8570
Rate of Florida Professional Engi+xers 'xeme #28073
Metric Engineering, Inc.
TSB' Proposal No. 1111-386
A geotechnicai engineer will evaluate the results of all drilling and laboratory testing. A report will
be issued that contains the exploration data, a discussion of the site and subsurface conditions, and
recommendation for foundation design and some construction consideration.
ESTIMATED FEES
It is proposed that the fee for the performance of the services outlined above be determined on a unit
price basis in accordance with the attached Fee Schedule and that the work be performed pursuant to
TSF's General Conditions enclosed herewith and incorporated into this proposal. The estimated fees
for the project are attached.
Our estimate covers the work needed to present our findings and recommendations in a formal
report. Not included are reviews of drawings, preparation of construction specifications, special
conferences and any other work requested after submittal of our report.
SCHEDULE AND AUTHORIZATION
TSF will proceed with the work after receipt of a signed copy of this proposal. With our present
schedule, we can commence work within several days of project approval (weather permitting). The
fieldwork will take about two days to complete_ The written report can be submitted about two
weeks after completion of the field exploration, depending on the extent of the laboratory -testing
program. Verbal preliminary recommendations can be made to appropriate parties prior to submittal
of the written report.
Metric Engineering, Inc.
TSF Proposal No. 1111-386
We at TSF appreciate the opportunity to submit this proposal and look forward to working with you
on this project. If you should have any questions concerning our proposal, please contact our office.
Respectfully submitted,
TIERRA SOUTH FLORIDA, INC.
Raj Kris samy, RE.
Principal ' eotechnical Engineer/ President
Attachments: 1. Fee Estimate
AUTHORIZED BY:
INVOICE TO:
Name:
Firm:
Title:
Name:
Date:
Address:
E IVI. G. Vera & Assoc., Inc. ENGINEERS•SURVEYORS•PLANNERS
Revised April 26, 2012
Metric Engineering, Inc.
13940 SW 136" Street
Suite 200
Miami, FI 33186
Project: Pedestrian Bridge over Adams Cut, Key Largo FI.
Dear Mr. Oscar Cruz,
Below is our scope of services for the Design Survey of the above referenced project. This scope
Items are based on Design Survey criteria and are derived from the FDOT Project Activity 27; Survey
Marl -Hour spread sheet, attached hereto. In addition to the specific scope items, all work shall be
accomplished In accordance with the criteria established by the Departments Highway Field
Specifications, Survey Handbook (Survey Procedure Topic No. 550-030-101a) (Chapter 20, sec 23
(3)(a), F.S.),CADD Production Criteria Handbook and must comply with the Minimum Technical
Standards for Land Surveyors Rule 5J-17 F.A.G., Florida Statue 472.027, the latest's addition of the
District VI Survey Standards and Guidelines and any special instructions. The proposed Design Survey
Scope of work includes the following Design Survey Services:
Design Survey Services:
27.01 Horizontal Primary Network Control (HPNC)
27.02 Vertical Primary Network Control (VPNC)
27,03 Alignment (Project Survey Baseline)
27,06 Topographic Survey
27.07 Digital Terrain Model (DTM)
27.09 Canal Soundings
27.27 Work Zone Safety
27.01 Horizontal Control
A Horizontal and Vertical Project Network Control (HPNC & VPNC) has been established as part of a
previous project. However one additional control point must be set within the project area. Secondary
control points will have to be established in order to complete the Canal Soundings. A new PNC sheet
will be created for this project. Horizontal control will be established on the Florida State Plane
Coordinate System, East Zone, and North American Datum (NAD) of 1983 / 1990 Adjustment. Vertical
control will be on NAVD 88 vertical datum. PNC sheets will depict all set control points with their
horizontal and vertical values (X, Y & Z), as well as station and off -set.
27.03 Survey Baseline
The Historic survey baseline and along US-1 has been previously established. Survey baselines will be
placed in Topo file, PNC sheet and the survey database. A Geopack .GPK file will be submitted as part
of the survey data -base.
MANUEL G. VERA & ASSOCIATES, INC. . 13900 SOUTHWEST 47rH STREET • MIAMI, FL 33176
PHONE (305) 221-6210 • FAX (305) 221-1295.ON THE WEB @ WWW.MGVERA.COM
"M. G. Hera & Assoc., Inc. ENGINEERS.SURVEYORS*PLANNERS
27.06 Topographic Survey] DM
Topographic and DTM Survey has been completed under a previous project.
Note:
,27.09 Canal Sounding
Canal soundings will be performed along the proposed pedestrian bridge.
27.27 Work Zone Safety
Provide work zone as required by F.D.O.T. standards
Notes:
FDOT does not have any current survey information for this project.
A surveyors report will be prepared; signed and sealed copies will be provided for all design survey
tasks.
If additional tasks are required beyond the aforementioned items, MGV will provide an additional fee
estimate
Cost and Man-hour breakdown
Please refer to FDOT Project Activity 27: Survey Man -Hour spreadsheet for our man-hour breakdown
and to the Fee sheet attached Here -to.
We look forward to providing our services and please contact me if you have any questions or require
additional information.
Sincerely,
Manuel G. Vera & Associates, Inc.
Manuel G. Vera Jr. PSM
MANUEL G. VERA & ASSOCIATES, INC.. 13960 SOUTHWEST 47r" STREET . MIAMI, FL 33175
PHONE (305) 221-6210 • FAX (305) 221-1295. ON THE WEB @ WWW.MGVERA.COM
Key Largo Pedestrian Badge Date: 4/26/7.012
Summary of Design Fees per Task
MEI Project No. 01.2073 U51 Bayside Shared Used Path
Proposed Pedestrian Bridge
Task No.
Task
Hours
Fee
Comments
8
Environmental Permits, Compliance & Clearances
157
$ 19,144.41
9
Structures - Misc. Tasks Dw s, Non Tech.
111
$ 13,535.22
10
Structures - Bride Development Report
154
$ 18,778.60
13
Structures - Medium Span Concrete Bride
235
$ 28,777.59
Total
658
$ $0,235.82
optional Services (Bridge Hydraulic Report)
5
Roadway Plans
40
$ 4,877.56
6
Draina a Analysis
210
$ 25,607.28
Subtatall
1S 30,484.74
Totall 908 1 $ 110,720.56
Average Loaded Hourly Rate $ 121.94
Subconsu Ita nts
Geotechnical
IS 7,205.00
Survey
1 1 $ 4,974.55
TOTAL $ 122,90D.11