Loading...
1st Change Order 05/13/2021 ONROE CouNTY/ENGINES G/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Hurricane Irma Roadway Repairs I Upper Keys Project CHANGE ORDER NO: 1 CONTRACT DATE: 09/16/20 FIRST CONTRACT DAY: 11/04/20 CONTRACT COMPLETION DATE: 02/02/21 CONTRACT COMPLETION DATE (as of this change order): 07/12/21 TO CONTRACTOR:Claar4ey-T "649eft&;Iee. Affordable Asphalt OW The Contract is changed as follows: The original Contract Sum .......................................................-.—.........................—$149,295.50 Net change by previously authorized Change Order.................................................. ...................$0 The Contract Sum prior to this Change order was..-................................ ........... ........$149,295.50 The Contract Sum is(increased)by this Change Order.............................................................-..$0 The Revised Contract Sum including this Change Order............................................... ..$149,295.50 The contract time was increased 160 days due to weight limit restrictions on the Bimini Drive bridge on Duck Key. The restrictions prevented the contractor from accessing the work location with materials and equipment. The Contract Sum is unchanged as a result of this change order. CONTRACTOR a 4 j Date ENGINEERING SERVICES DIRECTOR Judith Clarke, P.E. cu o =KuNn G„Wilon,PE,=?I ,,oe County,FL(the Date cn FlOAda Keyz,ou.em0—lwn ASSISTANT COUNTY ADMINISTRATOR ` `'�'< 221,0mnnt�tt47-0 5027.95.1316:57:4]-64'W' Date MAYOR N/A Date MONROE COUNTY ATTORNEY / ! k1PPR CH RISTINE LIMBERT-BARROWS ASSISTANT COUNTY ATTORNEY DATE.. 5/26/.21— Affordable Asphalt CO No. 1 Change Order Attachment per Ordinance No. 999 • Change Order was not included inthe originalcontrac specifications, Yes El NoFl If Yes, explanation: Additional contract time was added ho this contract. • Change Order was included |n the original specifications. Yes [] NoZ If Yes, explanation of increase inprice: • Change Order exceeds$25,000 or 5%of contract price (whichever is greater). Yes 7NoED |f Yes, explanation oato why itie not subject for e calling for bids: • Project engineer/architect approves the change order. Yes [] No �� |f no, explanation of why: Approved by Monroe County staff. • Change Order ia correcting an error or omission in design document. Yes F]NoE Should a claim under the applicable professional liability policy be made? Yes MNoZ Explain: