1st Change Order 06/23/2021 .Jacobs
CHANGE ORDER
REVIEW TRANSMITTAL
Attention: Roman Svirldenko Date Returned: 6/17/21
To: Pedro Falcon Contractors, Inc. Project No: E9Y37989
31160 Ave C Project Name: MTH Security Site Lighting
Rehabilitation
Big Pine Key, Fl. 33043
We are sending you these items via: Email
COPIES E OF SUBMITTAL
1 Change Order#1 - Credit APPROVED
Provide galvanized pole with
enhanced corrosion protection VS
black powder coated
Remarks: This is a deductive change order to provide hot-dipped galvanized steel poles with
enhanced corrosion protection in lieu of black powder coat for the eight(8) Musco lighting poles for
the terminal apron area.
Reviewed By: Ryan Forney Date: 06/17/2021
06.23.2021
21/21
.,
t I ,.Y...4...
lV
�:.
t.. c,.
�r-.-a r,,,_
Y..
,
Project: Marathon International Airport
Change Order/Credit M 1
Description of Change: Provide galvanized pole with enhanced corrosion protection VS Black Powder coated.
Date: 06.17.2021
LABOR
uanti Units Hours /unit Cost of labor
Providing black powder coated poles will add significant cost wihci has been accounted for in our bid. If the
Owner chooses to provide and install normal hot-dip galvanized steel poles with enhanced corrosion protection
(they will be gray and will fit aesthetically into the skyline). We will provide a credit of$1 S,000.00
PM Time for review,comment,pricing&coordinating
Office $ 105.00 $ -
Labor Subtotal $ -
Labor Burden Percentage 38°o $ -
Labor Total $MATERIAL SUPPLIER BACK-UP REQUIRED
QuanIL Units Descri lion /unit . Cost of Material
Material subtotal Material Sales Tax 7.50% $Freight $ -
Material Total -
EQUT ENT}1 SUBCUNT CTO '`/,UPIiT,C.QSI YS.,
uanti Units Descri tion !unit Cost of E/S/U
1 L.E. Powder coat credit $ 13,018.00 $ 13,018.00
Total: $ 13,018.00
Material Sales Tax 0.00% $ -
E ui ent&Sub Total 13,018.00
Labor Total $ -
aterial total $Equip./Sub/Unit Total $ 13,018.00
Subtotal $ 13,018.00
Allowable OH&P 15% $ 1,952.70
Bond&Insurance 1. % $ 29.29
GRAND TOTAL no ennies 15,000
Additional Da s Requested 0 Days
Change Order Attachment per Monroe County Code Section - ( )
• Change Order was not included in the original contract specifications. Yes ( ) No(x)
If Yes, explanation:
• Change Order was included in the original specifications. Yes ( ) No ( x )
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes() No(x)
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order.Yes(x ) No ( )
If no,explanation of why:
• Change Order is correcting an error or omission in design document. Yes ( ) No ( x )
Should a claim under the applicable professional liability policy be made? Yes( ) No (x)
Explain: This Change Order is changing the original intent and scope of work for the
Marathon International Airport Security Site Lighting Rehabilitation project.