Loading...
Item F5 BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY Meeting Date: October 16. 2002 Division: Public Works Bulk Item: Yes No -X- Department: Engineering/Construction Management AGENDA ITEM WORDING: Approval to reject all bids for Old Mariner's Hospital Renovation and authorization to re-bid. ITEM BACKGROUND: On September 12th, 2002,the bids were received for the Old Mariner's Hospital Renovation project. McTeague Construction Co. Inc., the apparent low bidder and D. L. Porter Construction, Inc., the high bidder, did not submit unit prices for concrete repairs, and therefore they were considered to be non-responsive by our architect. F & L Construction, Inc., the apparent second low bidder requested and received their bid security back after learning that they were not the low bidder and therefore, in essense, withdrew their bid. The remaining bid was received from Hewett-Kier Construction, Inc. Recommendation was given by the project's architect, Bender & Associates to award to the F & L Construction, Inc. prior to knowledge of their bid withdraw!. Recommendation was given by County Attorney's office to reject all bids and re-bid the project. Bids were as follows: McTeague Construction Co. Inc. $2,313,396.00; F & L Construction Inc., $2,480,000.00; Hewett-Kier Construction, Inc. $2,862,000.00; D.L. Porter Constructors, Inc., $2,898,439.00. PREVIOUS REVELANT BOCC ACTION: This project is included in the Capital Improvements Plan. On February 21, 2001, BOCC approved a contract with Bender & Associates Architects for design services. CONTRACT I AGREEMENT CHANGES: NI A STAFF RECOMMENDATIONS: Approval as stated above. TOTAL COST N/A BUDGETED: Yes 1L- No COST TO COUNTY: REVENUE PRODUCING: d by: Stephanie L. C ffer, Construction Manager -X AMOUNT PER MONTH_ Year APPROVED BY: DIVISION DIRECTOR APPROVAL: Dent Pierce, Division Director DOCUMENTATION: Included --A- DISPOSmON: To Follow_ Not Required - AGENDA ITEM # ~ Revised 2/27/01 y f5 II " ...J ~ ~ Ii! ~ I.L NV) 0....00 ~w2::r: 2w 'v) .... ::r: N - U)V)~fD ~z....z %00...... UHW~ ~I-V)< ::><:E:E CL...J< ~ I:::>Og Ua)OOD U<~ H 0"""'" V) a) m~....Z Z<O ~~..~ 2w~< ::>0..<> OODO UDZZ W""WW OCOo..~ ~ Ow ~ ~ ~ ~ !i II 8 8 8 8 g 0\ ~, ~ (\') 0 ~, 0\ 6 co N ~ co 0\ ..0 (Y) ~, co, co, .... (\'), N N N N -4A- -4A- -4A- -4A- D Z D D D 0 m Z Z Z 8 0 0 0 m m m ~, D D D H H H " m m m 0 ~ ~ ~ co It) It) It) .... -4A- .' '-> '-> ti Z Z H H Z Z 0 ~ H, W U) 0 '-> 0 CL. 1= z 0 '-> ~ '-> 0 H ::::> 1= a) z '-> ~ H ::::> '-> Z ~ U) ::::> 0 Z ~ 1= U) 0 z U) '-> 0 '-> Z ::::> '-> CL. 0 ~ w '-> CL. ~ ~ w U) ~ ::::> Z CL. (.!) 0 0 w < '-> 0.. ~ ~ -1 -.J ~ w u u.. d I :E Q) u 'i: ~ o 2' 'Vi o ..c u L. :::I 0.. I ~ o c o Z I (a) .:.:. o -1 C o L. o ..c U) " c o VI (a) L. o + u s: VI o ~ ~ + C (a) VI (a) L. 0.. (a) (a) + :t: E E o '-> " m .... c: ~ (a) L. 0.. u ..0 :::I 0.. (a) ..c .... ~ o VI L. (a) ..0 E (a) :E .... VI C '0 . en" o (a) ~~ .:.:. (a) ~ ~ ..c (a) U E c: ._ (a) .... (a)" .0 C (a) 0 > (a) o .... ..c 0 (a)" > (a) O..c -g.... " ~ (a).o 1;;" = ~ VI 'ij L. U (a) (a) " L. :E (a) .0 L. (a) c; ;: .... ~ ,.g 0 +.0 " 0 c" o ~ 2' .!!! 'c VI 8..:E 0.0 " = \ .:0 < " . ._ VI ~ 2' ~+: o .~ ~- Q.,L. o 0 U" + c ~~ L." L. (a) 0" U C " (a) c c.. o VI (a) :::I :::I U) ~ ~. 0" VI ~ .- U VI 'S; ..c c .... 0 +'-> ,.g..g + .- ~S +:u.. L.~ (a) 0 U (a) ~+ .0 0 (a) .... L. U) (a) (a) ..c..c H.... CL. W >- ::::> .m u)' w CL. ~ '-> ~ U) o -1 CL. < '-> >.. m " (a) c (a) c.. o " Q5 __I"~;:'i: From: Hutton-Suzanne Sent: Wednesday, September 25,20028:38 AM To: Coffer-Stephanie Subject: Mariner's Bid Subsequent to my last e-mail on this subject, there were a number of conversations, with you, with dave Koppel, with Rob Wolfe, and even with Sheriff Roth, that I have concluded, as I told the sheriff, that if we have these many differences of opinion at this stage of the bidding, the project, or challenges to the bid process, or both, would be fraught with problems if we go forward by recommending an award of the bid to anyone, Therefore, it is now my opinion that the wisest course of action would be to go out for bid all over again, and to revise the sections and language in the RFB which gave rise to the problems this time, September 24, 2002 Bender & Associates REVISED SEPTEMBER 27, 2002 ARC H ~ TEe T S p,a. ~ ec.. l' ~ -z. '1 , a '"l;. ~ Ms. Stephanie Coffer, Dir. of Planning & Constr. Monroe County Construction Management The Historic Gato Cigar Factory 1100 Simonton Street Key West, FL 33040 . ~~; ~~ /t1A. ~ --- &^- - Re: Mariners Bid Recommendation Dear Stephanie: My September 16,2002, letter advised you that I considered two of the bidders, McTeague and D. L. Porter, to be non-responsive due to their failure to include Section 00310, the "Supplementary Bid Form for Unit Prices". My September 16th letter with its backup is attached for reference. Following distribution of that letter, Mike McTeague protested my recommendation for disqualification. I advised him and D. L. Porter to submit the documents I requested of the responsive bidders. I met with Suzanne Hutton, Assistant County Attorney to review the specifications and specifically how they relate to my September 16 determination. Suzanne advised me at that meeting that she had determined that F&L Construction, one of the bidders I considered responsive, had requested the return of their bid bond immediately following the bid opening, and the purchasing office complied. Therefore F & L had withdrawn their bid. The specification sections that apply to my determination of non-responsive bids from McTeague and D. L. Porter are: ARTICLE 5 BIDDING PROCEDURE 5.1 FORM AND STYLE OF BIDS 5.1.1 The Bid Proposal shall be submitted on the forms included in Section - 00110 of these Bidding Documents with the exception of the Bid Bond, which may be submitted in alternate forms as described in Section 5.3.1 of these Instructions to Bidders. Each of the forms in Section 00110 must be properly filled out, executed, and submitted as the Bid Proposal. 410 Angela S treel KeyWest,Florida33040 Telephone(305) 296-1347 Facsimile(305) 296-2727 FloridalicenseAAC002022 Ms. Stephanie Coffer Page 2 September 24, 2002 Revised 9/27/02 5.1.2 All blanks on the Bid Form shall be filled in with ink or by typewriter. 5.1.3 Where so indicated on the Bid Form, sums shall be expressed in both words and figures, and in a case of discrepancy between the two, the amount written in words shall govern. 5.1.4 Any interlineation, alteration, or erasure must be initialed by the signer of the Bid. 5.1.5 All requested Alternates shall be bid. Ifno change in the Base Bid is required, enter "No Change". Failure to comply shall constitute a non-responsive bid. 5.1.6 All requested Allowances shall be bid. Failure to comply shall constitute a non- responsive bid. 5.1.7 All requested Owner Options shall be bid. Failure to comply shall constitute a non-responsive bid. Section 00310, "Supplementary Bid Form for Unit Prices", is an integral part of the bid with required pricing that is significant to the scope of work and is useful in evaluating the bids. However, Mike McTeague has argued that Section 5.1.1 above does not require submission of the Supplementary Bid Form, nor is it listed in the "checklist" that is part of the Bid Form, which states: I have included pages 2 through 6 of the Bid Proposal which entails the Proposal Form _, the required Bid Security _, the Non-Collusion Affidavit ----.-:> and the Lobbying and Conflict of Interest Clause_. In addition, I have included a certified copy of Contractor's License, City of Key West Occupational License, Insurance Checklist and an Insurance Agent's Statement. (Check mark items above. as a reminder that they are included). The Check List is included as a courtesy to bidders, clearly stating; "as a reminder that they are included". Section 5.1.1. states that the bid proposal shall be submitted on the forms in Section 00110, but it does not state that those are the ~ forms to be submitted. Both 5.1.6 and 5.1.7 apply to the Supplementary Bid Form: Ms. Stephanie Coffer Page 3 September 24, 2002 Revised 9/27/02 5.1.6 All requested Allowances shall be bid. Failure to comply shall constitute a non- responsive bid. 5.1.7 All requested Owner Option shall be bid. Failure to comply shall constitute a non- re~onsive bid. The verbiage in 5.1.6 and 5.1.7 is clear and binding. The verbiage does not allow the option of compliance, it does not say may constitute..., it says" ....shall constitute a non-responsive bid." The specifications also provide for additional criteria in evaluating bids. 6.3 A WARD OF CONTRACT 6.3.1 The Owner reserves the right to reject any and all Bids or any part of a bid, to waive the right to disregard all non-conforming, non-responsive or conditional bids. 6.3.2 In evaluating Bids, the Owner may consider the qualifications of the Bidders and whether or not the Bids comply with the prescribed requirements in the Bid Instruction. If requested by the Construction Manager, Bidders shall submit a properly filled out and executed Contractor's Qualification Statement after submission of bid, and prior to the Bid Clarification Meeting. An AlA Document A305-1986 is to be completed for this purpose. 6.3.3 The Owner shall have the right to accept alternates. The alternates will be accepted only in the order they are listed; alternate number one will be accepted first, alternate number two, second, and. so on. 6.3.4 The Owner may consider the qualifications and experience of subcontractors and/or other entities (including those who are to furnish materials, or equipment fabricated to a special design) proposed for each of the principal portions of the Work. Ifrequested by the Construction Manager, Bidders shall submit their listing of subcontractors after submission of bids, and prior to the Bid . Clarification Meeting. A Proposed Subcontractor Listing Form supplied by the Owner is to be completed for this purpose. Ms. Stephanie Coffer Page 4 September 24,2002 Revised 9/27/02 6.3.5 The Owner may conduct such investigations as he deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications, and financial ability of the Bidders, proposed subcontractors, and other persons or organizations to do the Work in accordance with the Contract Documents to the Owner's satisfaction within the prescribed time. The Owner has the right to conduct Bid Clarification Meetings with any Bidder to determine if Bidder has bid the scope of work in its entirety. Bidder shall be required to attend Bid Clarification Meetings, as necessary. 6.3.6 The Owner reserves the right to reject the Bid of any Bidder who does not pass any such evaluation to their satisfaction. 6.3.7 If the Contract is awarded, it will be awarded to the Bidder whose evaluation by the Owner shows him to be responsible and has indicated to the Owner that the award will be in the best interest of the Project. Additional documents were obtained from three bidders. F & L did not provide additional documents based on the County Attorney's preliminary opinion that their bid had officially been withdrawn. I have worked previously with both Hewett-Kier and D. L. Porter and consider both of them to be reputable firms who will provide a good project. Although I have not previously worked with McTeague Construction, their references are good and I believe they are a reputable firm that will also produce a good project. They have never failed to complete a project. Hewett-Kier was the Contractor of Record for the Harvey Government Center at the Historic Truman School. I noted in their Contractor's Qualification Statement that they had filed suit against Monroe County for non-payment on that project, and requested additional information. Those documents indicate that the case was settled for $10,535, which was the amount of court ordered restitution received by Monroe County from Bill Bibo. The Architects estimate of construction cost was $3,410,000. Bids were originally scheduled to be received on June 4, and postponed by Addendum several times until September 12,2002. During this nearly five month bidding period, we witnessed a downturn in the economy and anticipated a favorable bidding climate, but not to the extent experienced with the low end of the bids received. The two high bids at $2,898,439 and $2,862,000 are approximately 15% below our estimate. The low bid at $2,313,396 is approximately 32 % below our estimate, and the spread from low to high is about 25%. Because of this discrepancy, I compared the bidders spread sheets and noted the following: ' Ms. Stephanie Coffer Page 5 September 24, 2002 Revised 9/27/02 McTeague Hewett-Kier D. L. Porter General Conditions (w/out insurance) 155,380 314,022 278,189 Builders Risk:/Ins.Upgrades 34,892 39,405 85,000 Concrete Repairs/Reinforce Walls 171,174 *** 210,693 301,866 (234,396) Insulating Concrete 62,800 43,488 88,000 Roofing (included Demo) 155,000 159,540 155,000 Cabinets 118,448 123,515 118,447 French Drains/Injection well 25,500 79,667 * . Site work Total 150,268 200,346 193,935 Mechanical 119,000 158,305 136,923 Plumbing 119,400 ** 83,360 119,400 ** Electrical 314,800 421,522 375,000 * Not broken out separately, but included in site work total. Includes underground outside building envelope. McTeague's Summary shows $234,390 which includes 8.2% profit and overhead, but the line item total is only $171,174. ** *** In reviewing the line item breakdowns, McTeague's bid total shows a deduction of $36,860 for equipment. I would expect this to be an addition. Mike McTeague has stated that this represents equipment in subcontract bids also estimated by McTeague. In comparing the above line items, the biggest discrepancies between McTeague's bid and the average of the other two bidders are: General Conditions Electrical Site work Subtotal 8.2% P&O Total $141,000 85,000 47.000 $273,000 22.000 $295,000 Ms. Stephanie Coffer Page 6 September 24,2002 Revised 9/27/02 These three items account for almost $300,000. I have advised Mike McTeague of the above and he has verified his bid and will stand by it as submitted. I have not included the differences in concrete repairs because different methods and means could account for price differences and without the unit prices requested in the Supplementary Bid Form, a reasonable comparison is not possible. Specifically, we have gathered data from previous projects and use those unit prices as a benchmark to evaluate the reasonableness of those prices. As a side note, the specifications require builders risk for "the value of the completed project." I suspect that both Hewett-Kier and McTeague priced builders risk for the value of their construction contract and not the "value of the completed project". You should clarify the intent with Risk Management. Summary My recommendation is made with consideration given to all of the above, my September 16, 2002 correspondence, and is summarized as follows: 1. The specifications require me to deem the bids from McTeague and D. L. Porter as non- responsive. My interpretation of the specifications is that only the B.O.C.C. can waive this item. 2. My determination that these two bids are non-responsive is consistent with my previous actions on several past projects, most notable, the Gato Building. 3. F & L Construction has withdrawn their bid, and although they claim this was not their intent, the Assistant County Attorney has advised me that their bid is invalid. 4. The project is substantially under the Architect's estimate and within budget. 5. All of the bids are public record and rebidding the project with no changes will result in an unfair bidding climate, and the potential of having sub-contractors pressured to cut prices leading to possible construction problems. 6. This current bidding phase has taken six months, from mid-April to mid-October. Rebidding the project will require re-advertising and must include a pre-bid conference for new bidders to have an equal playing field. Assuming that we advertise the first weekend of November, and allowing for the Thanksgiving/Christmas holiday season, bids can be received in early to mid-January and a recommendation brought to the B.O.C.C. in mid-February, an additional four month delay with a total bidding period of ten months. Ms. Stephanie Coffer Page 7 September 24,2002 Revised 9/27/02 7. Although Mike McTeague has confIrmed his bid and I believe he is an honorable man who will endeavor to fulfIll his obligations, I have some concerns that areas of his bid are insufficiently funded, especially for subcontracts where he will have less control over performance than he has when utilizing his own forces. 8. (9/27/02) All of the above has been discussed with the County Attorney, who has reviewed the issue with various County employees. Given the lack of consensus, Suzanne Hutton recommends rebidding. (9/27/02) Recommendation: Based on and with consideration to all of the above, I concur with the County Attorney's opinion and recommend rebidding. Alternatives: The Board of County Commissioners has several options: 1. Throw out all bids and re-advertise the project. 2. Waive the requirement for the Supplementary Bid Form, make a determination that McTeague is the qualifIed responsive low bidder, and award to McTeague. 3 . Award the Contract to Hewett Kier as the only responsive bidder for the base bid amount of $2,862,000. 4. Take any other action they deem appropriate, based on public input at the October 16, 2002 public hearing, including awarding to D. L. Porter, who was the third bidder, should they deem it to be in the best interest of Monroe County. Please call if you have any questions. I have forwarded this recommendation to the four bidders to allow them the opportunity to respond or challenge this recommendation, and to allow them time to prepare for the B.O.C.C. meeting if they so choose. Sincerely, ~ - ~er, Architect ------.-1 cc: Dent Pierce Suzanne Hutton, Assistant County Attorney Mike McTeague Jim Hewett Gary Loer Julio Batista September 16, 2002 "Bender 6' Associates Ms. Stephanie Coffer, Dir. of Planning & Constr. Monroe County Construction Management The Historic Gato Cigar Factory 1100 Simonton Street Key West, FL 33040 ARC H II TEe T S p.a. RE: Mariner's Bid Review Dear Stephanie, I have reviewed the bids for Mariner's and have determined that the bids submitted by McTeague Construction and D.L. Porter are non-responsive in that they did not include the required "Supplementary Bid Form For Unit Prices" Specification Section 00310. This is a substantial error in that the project includes a $25,000 allowance for "unforseen concrete repairs" and these unit prices are to be used to determine a potential credit or additional charge to the Owner for concrete repairs less than or beyond those identified as "Base Bid". This is a similar situation to the bidding for the Gato Building and I have attached a copy of that bid recommendation for your use. The Gato Building was awarded to Lodge Construction, who eventually walked off the job. Because of those events, the B.O.C.C. directed, in a public meeting, that future bid awards consider bidders' financial solvency, ability to perform, thoroughness of their bids, and evidence that bidders have allowed sufficient funding to complete the project. In keeping with the B.O.C.C. directive and by copy of this letter, I am requesting the two responsive bidders, F&L construction and Hewett-Kier construction to provide the following documents: 1. Contractor's Qualification Statement, AlA Document A305, along with the required financial statements and other supporting documents. 2. A line item bid breakdown. The Specifications contain unique insurance requirements. The bid breakdown should include those costs and the following as a minimum. General Conditions: (Insurance costs for Builder's Risk broken out separately) Site Work Selective Demolition Asphalt Paving and Grading Storm Drainage System Landscape Work Concrete Repairs Lightweight Insulating Concrete Unit Masonry Metals Carpentry Roofing (Broken down for roof demolition, roofing materials and labor. Six 410 Ao&ela Street KeyWest, Florida 3 3040 Telepbooe(305) 296-1347 Facsimile (05) 296-2727 Plo, Idll L Ie In 1I.1i1 COO:J O:J:J systems were speCltled and no requested substitutions during bidding received prior approval. The roofing materials price should also state which of the six specified systems will be used) Doors and Frames Windows and Glazing Storm Shutters Finishes Specialties Mechanical Plumbing ElectricaI 3. A complete subcontractor listing with the following trades listed as a minimum. Site Work and Grading Paving Concrete and Concrete Repairs Masonry Roofing Carpentry Metal Studs and Drywall Mechanical Plumbing Electrical The deadline for the October 16,2002 B.O.C.C. agenda is October 2,2002. Therefore, I am requesting that F&L and Hewett-Kier have the above documents in my office not later than Tuesday, September 24, 2002. I will have my recommendation to you by 3 :00 PM on Monday, September 30,2002, allowing you two full days to prepare the agenda item. Please adVise me if you need more time. I recognize that your recommendation mayor may not coincide with mine and that the B.O.C.C. may take action that differs from either of our recommendations. Therefore, I have blocked out October 16, 2002 to attend the B.O.C.C. meeting at the Harvey Government Center in Key West. Please call if you have any questions or comments. I have copied all four bidders for their information. Sincecely, _ ~ ~~ ~ Bert L. Bender, Architect BLB/ddk Enclosure cc: Dave Koppel Mike McTeague F&L Construction Jim Hewett, Hewett-Kier Gary Loer, D.L. Porter July 17, 1999 Mr. Steve Piazza Construction Management 51 O~ College Road Key West, FL 33040 RE: Gato Building Bids Dear Steve, copy I have reviewed the bids for the Gato Building and have determined that the bid submitted by Pedro Falcon is non-responsive in that he did not include the required "Supplementary Bid Fonn For Unit Prices" Specification Section 00310. This is a substantial error in that the project includes a $20,000 allowance for "unforseen concrete repairs" and these unit prices are to be used to determine a potential credit 'or additional charge to the Owner for concrete repairs less than or beyond those identified as "Base Bid". Therefore, it is my determination that Lodge Construction is the lowest responsive bidder. I recommend accepting the base bid and deductive alternate numbers 1, 2, 4, and 7, for a combined bid price of$4,350,000. This bid price is detennined as follows: Base Bid Alternate # 1 (Deduct wood flooring @ first floor and substitute quarry tile) Alternate #2 (Substitute wire glass for "Firelite") Alternate #4 (Delete aluminum fencing @ south & east) Alternate #7 ((Deduct permit fees) Alternate #8 (Substitute carpet for wood @ 2nd floor) TOTAL BID PRICE Please call if you have any questions. Sincerely, COPY Bert L. Bender, Architect BLB/ddk $4,553,000 (7,000) (78,000) (12,000) (106,000) (16,000) $4,334,000