6th Change Order 06/28/2021 MONROE CCU I G/ PROJECT MANAGEMENT
CONTRACT CHANGE OMER
PROJECT TITLE:
Reduced Scope East Martello Phase II Drainage and Parking Improvements
CHANGE ORDER NO: 06
INITIATION DATE: 6/24/2021
CONTRACT DATE: 09/16t2020
TO CONTRACTOR:
Charley Toppino&Sons, Inc.
129 Toppino Industrial Drive
Key West, FL 33040
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price). ........ $530,029.50
Net change by previously authorized Change Orders.. ........ . . ... . .. .... . ...... . ...... $194,385.66
The (Contract Sum (Guaranteed Maximum Price) prior to this Change order was.... $724,415.16
The (Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased)
(unchanged) by this Change Order................... $&00
.... ._ __..._.. .._ _� ......_.—........—..—
The new(Contract Sum)_(Guaranteed Maximum Price) including this Change Order is. $724,415,16
The Contract Time will be (increased) (decreased) (unchanged) by......... . ..... ......... 60 days
The date of Substantial Completion as of the date of this Change Order is ....... ......... 08/17/2021
Detailed description of change order and justification:
This change order is requested by the contractor after receiving the estimated shipping date from the
manufacturer for additional lighting poles requested by the county. This is a time only change order with no
impact to the project budget. The Substantial Completion date will be moved from 611812021 to 811712021.
Change order is 0.00% of original contract price.
i
Not valid until signed by Owner Architect if applicable), and Contra ear., o.
ARCHITECT: qviq Salay �'sr. �.�``� /24/21
d ,t& loci e , ct D to y
CONTRACTOR: .�
v
Charley Toppin & Sons, Inc. Da
Car Kn i h t Digitally signed by Cry Knigh
DEPARTMENT DIRECTOR: y g Date:2021.06.2516:20:13-04.00'
Cary Knight date
Project Management
n=Kevin G.Wilson,P.E.,o=Monroe County,FL(the
COUNTY/ASSISTANT ADMINISTRATOR: - t <-_ Florid.,C us��emal who,ke�d@mo�roeCordt
Roman Gastesi Date
Kevin Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 024-2015
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: This change order for an extension in time only and is based on manufacturer's lead time
to produce and ship the product. The County requested additional lighting for this project via MC Change
Order#03, which was an addition to the original project scope of work.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
W
Charley Toppino&Sons
129 Toppino Industrial Dr
Key West, FL
305-296-5606
Tom Henry
Monroe County Project Manager
1100 Simonton St Ste 2-216
Key West, FL 33040
Subj : East Martello Phase II Drainage and Parking Improvements
Mr. Henry,
Charley Toppino &Sons, Inc hereby requests a time extension of 60 calendar days to achieve substantial
completion on this project due to significant delays in the production and procurement of the light poles
added to this project via change order. Construction materials of all types are currently backlogged due
to issues arising from Covid-19.
Sincerely,
Michael Labrada
Contract Administrator
Charley Toppino &Sons, Inc
An EQu al Oppor f-'unify Employer rr