1st Change Order 09/28/2021 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
West Martello Citadel— Hurricane Irma Repairs INITIATION DATE: September 08, 2021
CHANGE ORDER NO: 01
TO CONTRACTOR:
Innovative Masonry Restoration, LLC.
CONTRACT DATE: February 17, 2021
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)....................................... $247,000.00
Net change by previously authorized Change Orders..................................................... $ 0.00
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was........ $247,000.00
The (Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased) $ 0.00
(unchanged) by this Change Order...................
The new (Contract Sum)_(Guaranteed Maximum Price) including this Change Order is... $247,000.00
The Contract Time will be (increased) (decreased) (unchanged) by................... 60 days
The date of Substantial Completion as of the date of this Change Order is........ 11/08/2021
The following issues require this change order.
1) This Change Order provides for an extension of contract time to allow review and amendment of an
Agreement between the County and the State Division of Historical Resources (on behalf of the
National Park Service (the Grantees). The County has requested an addition to the scope of work
under this agreement to repair additional damage discovered at the West Martello, due to Hurricane
Irma. The County requested a proposal from the Contractor for this work. That proposal was
received and forwarded to the DHT/NPS in June 2021. DHR/NPS concurs with the request, but
additional time is needed to amend the agreement and get all signatures
This change order is 0.00% of the original contract price.
Not valid until signed by Owner Architect if applicable), and Contr tOrJPVI°J SACAy 9
ARCHITECT: David S i Arc/ 9/1 / 1
Bender Associate pR Date
CONTRACTOR: cl - '✓ 09/17/21
novative Masonry Renovation, LLC Date
Cary Knight Digitally signed by Cary Knight
DIRECTOR PROJECT MANAGEMENT Date:2021.09.28 15:34:53-04'00'
Cary Knight Date
n=Kevin G.Wilson,P.E.,o=Monroe County,FL
j i I• (the Flonda Keys ou ema I oh son-
COUNTY/ASSISTANT ADMINISTRATOR: �, ��� ;e;;°@q Q°;°„°un
,�na 9°"`-�s
Roman Gastesi Date
Kevin Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ❑ No
If Yes, explanation:
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
allMASONRY
RESTORATION ,
1001
16264 Lakeside Ave SE, Prior Lake, MN 55372
612-548-5589 (0) 888-751-5402 (F)
www.imrestoration.com
September 24, 2021
Cary Vick
Monroe County
1100 Simonton Street
Key West, Florida 33040
RE: West Martello Change Order #001
Regarding our contract for the West Martello Towers Citadel Hurricane Repairs
project, IMR requests a no-cost time extension for 60 calendar days to allow
additional time for agency review and approval of possible additional scope of repair
work.
If you have any questions please contact me at our office number listed above and/or
by email at j im@ im restoration.corn.
Best Regards,
Innovative Masonry Restoration
Jim Dolby, Principal