Notice to Proceed - Permits Sit
s
D UI �' Key West
International it
port
3491 South Roosevelt Boulevard Key West,Florida 33040
September 28, 2021
Douglas R. Masch II, President
DEC Contracting Group, Inc.
1560 Matthew Drive, Suite B
Fort Myers, Florida 33907
RE: Notice to Proceed - Permits:
Key West International Airport Noise Insulation Program
Construction of Key West by the Sea Building A— Phase 2
Project No. 630202 GAKA165
Dear Mr. Masch:
Pursuant to Special Provision No. 2, please consider this letter as Notice to Proceed — Permits,
which includes administrative procedures necessary to procure lead items, provide submittals for
review by the Program Manager, obtain necessary permits, and other pre-mobilization tasks for
the above contract dated September 15, 2021.
The Contractor shall commence the work to be performed under this agreement on Wednesday,
September 29, 2021. Pursuant to Special Provision No. 3, the Contract Time to Complete is set
forth as follows:
NOTICE TO PROCEED DESCRIPTION CONTRACT TIME TO
COMPLETE
This notice shall allow the Contractor to obtain
any necessary construction permits required to
NOTICE TO PROCEED- accomplish the work. Also, during this time, the
PERMITS Contractor shall order and deliver materials, 118 Calendar Days
equipment and supplies needed to complete the
work. No on-site construction activities shall be
accomplished.
NOTICE TO PROCEED - Noise Insulation Improvements at 28 KWBTS 140 Calendar Days
CONSTRUCTION Condominiums.
TOTAL CONTRACT TIME: 258 Calendar Days
I
�fli 4 4
Key West
International Airport
r
3491 South Roosevelt Boulevard Key West,Florida 33040
Please provide a fully developed overall Construction Schedule to the Program Manager for
review and approval within ten (10) days of this NTP (effective September 29, 2021) pursuant to
Section 01310 1.05.
The County will be issuing a Notice to Proceed - Construction, effective Tuesday, January 25,
2022, pursuant to Special Provision No. 2. A Pre-Construction Meeting will be held on Monday,
January 24, 2022; time and location to be determined.
If you have any questions, please contact me.
Sincerely,
Richard Strickland, CM
Senior Director of Airports
XC: Deborah Lagos, Airport Noise Program Coordinator
Steve Vecchi, NIP Project Manager
Dale Griffin, NIP Construction Manager