Loading...
12/15-C7 Security Lighting Rehabilitation MASTER AGREEMENT FOR PROFESSIONAL SERVICES TASK ORDER FORM Effective Date . Jon execution_ Task Order No. 12/15-C7 Client Project No. ,W 5111 Engineer Project No, E9Y37989 4 . . . ............eeeeeee This Task Order is entered into on the effective date noted above pursuant to the "Master Agreement for Professional Services" between Monroe County, Florida("Client") and JACOBS PROJECT MANAGEMENT CO. ("Consultant"), dated February 15, 2017 ("Agreement"). The Agreement is incorporated herein and forms an integral part of this Task Order. Services Authorized—Security Site Lighting Rehabilitation—Construction Support Services Supplemental 1 Client authorizes Consultant to perform the Services described in Exhibit A attached hereto and incorporated herein,which Exhibit A is marked with the above noted Task Order No. and consists of 3 page(s). Pricing N/A Time and Expense per Agreement and Firm Fixed Price of$ 6 101.00 N/A Other(Describe): Schedule Services may commence on Execution Services will cease by 210 days ASS Date 9/28/21 Recommended by Approved by irector of Airports Date County Administrator Date 09/29/2021 CONSULTANT: JAC BS PROJECT MANAGEMENT CO Digitally signed by Jeffrey D.Acton JeffreyDN:cn-Jeffrey D.Acton,o-Jacobs }} VI'Mcol,ou, C l emalWetfrey.ActoneJecobs.com,c-U5 Jacqueline k � u s y Date:2021M.2>1222:23-oa�� � *MW tft*, 6Q0W a r aw Witness Ross t�.r.zoa1a�2aa2$0se.c4 Title % a„ t n ➢➢ t, I File: MSTR APS Monroe County Page 1 of 1 Exhibit A—Scope of Work(12/16—C7) Monroe County The Florida Keys Marathon International Airport(MTH) Security Site Lighting Rehabilitation—Construction Support Services Supplemental 1 SCOPE OF WORK This task is a supplemental to existing PSO 12/15—89. Jacobs will provide structural and electrical engineering documents for the replacement of five(5)concrete light poles for the GA apron. The scope also includes construction support services. These improvements will be located at the Florida Keys Marathon International Airport in Marathon,Florida.All design work shall be designed in accordance with the Florida Building Code 2020. EXISTING CONDITIONS The five(5)existing concrete lighting poles have deterioration and spalling requiring their replacement. The existing light fixtures,antenna,camera,pull box are to be removed and reinstalled on new poles. DESCRIPTION OF WORK The data collection and design,will provide the following: Article A—Data Collection Field Verification: Visit and inspect the site (1 visit) to determine the existing conditions. Take photographs and make written documentation, sketches, notes or reports to confirm and record the general conditions of the existing light poles. Within this initial phase we will also review the Master Utility Plan dated March 16, 2010. Services for Article A will be provided under a lump sum basis. Article B—100%Design The specific tasks Jacobs will perform are as follows: Jacobs shall prepare the Construction Documents sheet setting forth the requirements for the construction of this scope of work. During this work phase, we will prepare the required construction documents for permit and construction. This work effort will include structural notes and electrical plan. Services for Article B will be provided under a lump sum basis. Article D—Construction Support Services The specific tasks Jacobs will perform are as follows: Page 1 of 3 Jacobs will review shop drawings submitted by the contractors and all materials used in the construction of the project. Assume one (1) shop drawing throughout the course of the scope of work. Jacobs will coordinate with the owner and the contractor during construction. Services for Article B will be provided under a lump sum basis. QUALIFICATIONS AND ASSUMPTIONS For the purpose of providing a stipulated fee amount, this proposal has been based on the following qualifications and assumptions: • Permit issuance related work such as processing plans through City, County, and/or State agencies, other than plan revisions requested by such agencies, are not included. • Government Agency cost for all building and engineering permit fees are not included in this proposal. • Structural engineering is limited to design criteria and requirements for the pole manufacturers specialty engineering. • Construction administration services required by lending institutions and/or prospective tenants in this project are not a part of our services in this phase. • Preparation of close-out/warranty documents coordination is not included. • Life Cycle Cost Analysis is not included. • The testing scope of services along with the construction testing is by others. • Lightning protection will not be provided. • Architect/Engineer construction inspections are not included. Inspection services for building/permitting inspections is not in our scope(no inspectors on staff), none are anticipated by the architect/engineer. • Proposal is based on the existing electrical systems having adequate capacity to properly serve the renovation.No major modifications to the existing electrical systems are included in this proposal. • Attendance and/or presentation to public hearings and/or other meetings with municipal agencies are not included. • Municipal Agency and all associated permit fees are to be paid by the client. Jacobs is not responsible for obtaining any permits. Permits are to be obtained by the contractor. Jacobs will monitor the contractor's progress through the permit process for the client and provide follow up periodically with the permitting agency to verify the status,but it is ultimately the responsibility of the contractor to obtain all permits. • Services do not include"design to cost". Jacobs will assist the owner in evaluating and offering cost reduction strategies as requested by client. The "design to cost"is basically noting that if Jacobs receives direction from the client or one of its sub-consultants on how to design the project and if any changes are required due to the project being over budget,then the re-design required to bring the project back within budget is not a part of the lump sum fee and shall be treated as additional services. • Other services not described in the scope of work. Items identified as not included or limited in the scope of services can be provided or expanded upon as additional services under a separate agreement or supplemental to this agreement. Page 2 of 3 REFERENCES The client will need to provide the following documentation to Jacobs before commencing with our scope of work. • Master Utility Plan dated March 16, 2010. COMPENSATION See attached spreadsheet. SCHEDULE We anticipate completion of the deliverables in accordance with the following schedule: The overall duration of this effort will be as noted below: Item Duration Business Days) A. Data Collection 5 business days from agreement authorization B. 100%Design 10 business days D. Construction Support Services per contractor schedule Page 3 of 3 JACOBS ENGINEERING GROUP 09.14.21 Monroe County Airport: The Florida Keys Marathon International Airport Project: Security Site Lighting Rehabilitation -Construction Support Services Supplemental 1 FEE SUMMARY BASIC SERVICES Hours Fee PHASE 1 Article A: Data Collection 6 $ 960 Article B: 100% Design 33 $ 3,994 Article D: Construction Support Services 8 $ 1,147 TOTAL SERVICES LUMP SUM PROJECT FEE 47 $ 6,101