4th Change Order 09/17/2021 Q S
El r A rn j, F f o f
Phone 305,441,186a
.Jacobs F a x,, I�3 8"')7
REVIEW — Change Order
Attention: Christian Brisson Date Returned: 09/13/2021
To: Pedro Falcon Contractors, Inc. Pr2ject No: E9Y37989
31160 Ave C Project Name: IVITH Security Site Lighting
Rehabilitation
Big Pine Key, Fl. 33043
We are sending you these items via: Email
FURNISH AS
REVISE SPECIFIED
N
COPIES TYPE OF SUBMITTAL ...... An =epn
SUBMITTED CORRECTED RESUBMIT ITEM
1 Change Order#4 x
Remarks:
REVIEWED AND ACCEPTED.
Reviewed By: Ryan Forney Date: 09/1312021
Corrections and Comments made on the shop drawings during this review do not relieve contractor from compliance
with requirements of the drawings and specifications. This check is only for review of general conformance with the
design concept of the project and general compliance with the information given in the contract documents. The
contractor is responsible for: confirming and correlating all quantities and dimensions; selecting fabrication
processes and techniques of construction; coordinating his work with that of all other trades; and performing his work
in a safe and satisfactory manner.
Recommended by Approved by
A#NROE COUNTY ATTOFINEY
e'l HOVE FOPAA 0:
P 00 JD U E
ASSISTWNTY ATTORNEY
Date 9/15/21
rector of Airports Asst./County Administrator
Date: 9.14.21 - Date: 09/17/2021
1's
PEDRO FALCON
CONTRACTORS, INC.
31160 Avenue C,Big Pine Key,FL 33 .4 16
sR ( 0 )872-2 00-Fax(3 3)872-2210
EC 13003416/CGC 1607617
t
� ., wwwpedrofalcon,com
Request for Time Extension
Date Submitted: 09/13/2021
Jacobs
3150 SW 38"Ave, Suite 700
Miami,FL 33145
Phone: 305-441-1864
Attn: Mr. Ryan Forney,AIA,NCARB, CGC
Senior Project Manager
Project: MTH Security Site Lighting Rehabilitation
Project#: E9Y37989
Change Order Request No: Four
Re_quest for Time Extension
Mr. Forney,
The purpose of this letter is to request a 45 day time extension from 05 September 2021
for the following additional work demolition of 3 concrete bases, add 2 new bases and
remove lighting pole with fixtures.
Please let me know if you need any additional information.
Respectfully Submitted,
Christian Brisson
Project Manager
Change Order Attachment per Monroe County Code Section 2-58(b)
- Change Order was not included in the original contract specifications. Yes ( ) No ( x)
If Yes, explanation:
- Change Order was included in the original specifications. Yes ( ) No ( x )
If Yes, explanation of increase in price:
- Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes( ) No(x)
If Yes, explanation as to why it is not subject for a calling for bids:
- Project architect approves the change order.Yes(x ) No ( )
If no,explanation of why:
- Change Order is correcting an error or omission in design document. Yes ( ) No ( x )
Should a claim under the applicable professional liability policy be made? Yes ( ) No (x)
Explain: This Change Order is not changing the original intent and scope of work for the
Marathon International Airport Security Site Lighting Rehabilitation project.