3. 2nd Change Order 11/12/2021 ONROE COUNTYANGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: Harbour Drive Bridge (#904604) and Seaview Drive Bridge (#904606)
Strengthening Project
CHANGE ORDER NO: 2
INITIATION DATE: 11/8/21
SUBSTANTIAL COMPLETION DATE: 10/17/21
TO CONTRACTOR: American Empire Builders, Inc. CONTRACT DATE: 3/10/21
The Contract is changed as follows:
The original Contract Sum ...................................................................................................$1,663,376.00.
Net change by previously authorized Change Order.....................................................................$80,014.00.
The Contract Sum prior to this Change Order..........................................................................$1,743,390.00.
The Contract Sum is(increased) by this Change Order..............................................................................$0.
The Contract Sum including this Change Order....................................................................... $1,743,390.00.
As a result of construction material acquisition delays (at no fault of the contractor), delays for temporary
utility relocations by the FKAA and no work being performed during the Thanksgiving and Christmas
holidays, 90 additional days are required to obtain substantial completion for the Seaview Drive bridge and
30 more additional days are required to obtain substantial completion for the Harbour Drive bridge.
Total amount of additional time added to this contract is 120 days at no additional cost.
The new substantial completion date for the Harbour Drive and Seaview Drive bridge strengthening project
is 2/14/22.
Antonio M Digitally signed by Antonio M
Gonzalez
CONTRACTOR Gonzalez Date:2021.11.10 10:38:07-05'00'
Date
ENGINEERING SERVICES DIRECTOR Judith Clarke, P.E. Digitally
ea20 .11 signed104412 C0500'PE
Kevin G.Wilson,P.E. Date
ASSISTANT COUNTY ADMINISTRATOR " 2021.11.12 11:01:50-05'00'
Date
MONROE COUNCTTY,�,ATTORNEY
VVD AS TO FOW:PR
Chi RJS11N8 LIMBF:RT•BARROWS
ASSISTANT COUNTY ATTORNEY
DATE... 11/12/21
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation:
Additional bridge strengthening was added to this contract.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project engineer/architect approves the change order. Yes ® No ❑
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain: