1st Change Order 01/04/2022 MONROE CouNTY/DEPARTMENT OF AiRpom
CONTRACT CHANGE ORDER
PROJECT TITLE: Marathon International Airport CHANGE ORDER NO: 1
Hangar Rehabilitation
INITIATION DATE: 12/8121
TO CONTRACTOR: Marino Construction Group, Inc CONTRACT DATE: 02/17/2021
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price).......................................... $499,950.00
Net change by previously authorized Change Orders.................................................. $ 0.00
The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was............$499,950.00
The(Contract Sum)(Guaranteed Maximum Price)will be(Increased)(decreased)
(unchanged) by this Change Order.......$ 0.00
The new(Contract Sum)_(Guaranteed Maximum Price) including this Change Order is.......$499,950.00
The Contract Time will be(increased)(decreased) (unchanged)by............................... 0 days
The date of Substantial Completion as of the date of this Change Order is.......................
Detailed description of change order and justification:
Installation of New Composite Deck Boards at Plane Entrance. Costs are covered under
contingency allowances under CUD# 1.
This change Order is 0 00°°of the original contract price.
Not valid until signed by Owner.Architect(If applicable),and Contractor
ARCHITECT: 2/22/2111
Date
CONTRACTOR:
Da e
DIRECTOR OF AIRPORTS
mm.uw Date
MONROE COUNTY: -- 01.04.2022
sst./county`Adm n strator Date
NROE COUNTY ATTOnNEY
A f iOE FORM
PED J. C
ASSIS 'UNTY ATTORNEY
Date 12/23/21
Change Order Attachment r Monroe County Code Section 2-58(b)
• Change Order was not included in the original contract specifications. Yes(X) No( )
If Yes, explanation : Installation of New Composite Deck Boards at Plane Entrance. Costs are
covered under contingency allowances under CUD#1.
• Change Order was included in the original specifications. Yes ( ) No (X )
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes()No())
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes(X) No ( )
If no,explanation of why:
• Change Order is correcting an error or omission in design document. Yes( ) No (X)
Should a claim under the applicable professional liability policy be made? Yes( ) No (X)
Explain:
--R, N'',-0-
C O N S T R U C T I O N G R O U P
Contin enc Use Directive ICUD
OWNER: PROJECT: Date: 11122/21
Monroe Board of County Comissioners Marathon International Airport
1100 Simonton Street Hangar Rehabilitation CUD Number: 1
Key West,FL 33040 9400 Overseas Highway
Marathon,FL 33050
This Contingency Use Directive is for:
Install new bevel cut boards with tapcons at each location.Install new composite deck boards
at plane entrance.
Is additional time needed to perform scope changes? ®YES XNO Time Extension 0 days
Changes to Contract Sum:
General Conditions: $ 1,000.00
Subcontractor Subtotal: $ 12,600.00
General Liability: $ 126.00
Subtotal: $ 13,726.00
GC Fee: $ 2,058.90
Subtotal: $ 15,784.90
Contractor's Bond $ 236.77
Total Proposed Amount: $ 16,021.67
Reason for Changes:
Xa Changes in scope given by architect or owner for aesthetic and/or design reasons
Changes resulting from events or circumstances:defective design,owner caused delays,differing site conditions
Approved by: Date: "�6 2
El Declined by: Date:
Comments:
CGCO21647 1305-359-5269 1 PO Box 1706 Key West,FL 33041 I .marino-construction.com
F
Agra 'r
11/19/21
Change Order
SUBMITTED TO, Marino Construction Group
PROJECT; Marathon Airport - T Hanger Buildings
Change order # 1
Install new composite deck boards at plane entrance.
Remove existing deck boards and install new bevel cut boards
with tap-cons at each location.
The total amount for this work is.
Total 1 ,
TARPON BAY CONSTRUCTION
1220 SE 131h Ave Cape Coral, F1. 33990
239/573-4733 FAX --239/573-8141
WEB SITE: tarponbayconstruction.com