2nd Change Order 01/04/2022 CONTRACTMONROE CouNTY/DEPARTMENT OF AIRPORTS
E
PROJECT TITLE: Marathon International Airport CHANGE ORDER NO: 2
Hangar Rehabilitation
INITIATION DATE: 1218121
TO CONTRACTOR: Marino Construction Group, Inc CONTRACT DATE: 02/17/2021
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price).......................................... $499,950.00
Net change by previously authorized Change Orders.................................................. $ 0.00
The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was............$499,950.00
The(Contract Sum) (Guaranteed Maximum Price)will be Increased (decreased)
(unchanged)by this Change Order.......$ 0.00
The new(Contract Sum)_(Guaranteed Maximum Price)including this Change Order is.......$499,950.00
The Contract Time will be increased (decreased)(unchanged) by............................... 0 days
The date of Substantial Completion as of the date of this Change Order is.......................
Detailed description of change order and justification:
Installation of additional wall panels beyond the original bid
amount. Includes removal of damaged panels and installation of
new panels for Building 1 , 2 &3 . Costs are covered under
contingency allowances under CUD #2
This change Order is 0.00°0 of the original contract price.
of v lid 11 i n d b Ownor Architect(if a lica I-1 and Contra
..&'.,,'d'' .2.
ARCHITECT: Date
CONTRACTOR:
4Dat
DIRECTOR OF AIRPORTS
µ. Date
01.04 2022
MONROE COUNTY:
Asst./County Administrator Date
NROE
OVCOUNTY E PO#�3'UEY
RM
PED t],#. .a CA
ASSISTA U ATTORNEY
Date 12/23/21
Change Order Attachment per Monroe County Code Section 2-58(b)
• Change Order was not included in the original contract specifications. Yes(X) No( )
If Yes, explanation : Installation of additional wall panels beyond the
original bid amount. Includes removal of damaged panels and
installation of new panels for Building 1 , 2&3 . Costs are covered
under contingency allowances under CUD #2
• Change Order was included in the original specifications. Yes ( ) No (X )
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes() No(X)
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes(X) No ( )
If no,explanation of why:
• Change Order is correcting an error or omission in design document. Yes ( ) No (X)
Should a claim under the applicable professional liability policy be made? Yes( ) No ( )
Explain:
__....__................. ..
C O N S T R U C T 1 O N G R O U P
Contin enc Use Directive CUD
OWNER: PROJECT: Date 1218/21
Monroe Board of County Comissioners Marathon International Airport
1 100 Simonton Street Hangar Rehabilitation CUD Number 2-REV
Key West,FL 33040 9400 Overseas Highway
Marathon,FL 33050
This Contingency Use Directive is for:
Install additional wall panels beyond the original bid amount.Process to include removal of damaged panel and installation of new panel with new
fasteners for Buildings 1,2,&3.There is a total of 21 panels needing to be replaced.
Is additional time needed to perform scope changes? YES X�NO Time Extension 0 days
Changes to Contract Sum:
General Conditions: $ 1,09090
Subtotal: $ 6,279.00
General Liability: $ 62.79
Subtotal: $ 7,43269
GC Fee: $ 1,114,90
Subtotal: $ 8,547,59
Contractor's Bond $ 128,21
Total Proposed Amount: $ 8,67580
Reason for Changes:
®Changes in scope given by architect or owner for aesthetic and/or design reasons
Changes resulting from events or circumstances:defective design,owner caused delays,:differing site conditions
pP Y — Date: 1 i 13
s/
Approved b
Declined by: Date:
Comments:
CGCO21647 1305-359-5269 1 PO Box 1706 Key West,FL 33041 I www.marino-construction.com
S �
1,Off?
f
t
12/7/21
Invoice
SUBMITTED TO; Marino Construction Group
PROJECT; Marathon Airport - T Hanger Buildings
Change order # 2
Installation of additional wall panels.
Install additional wall panels beyond the original amount bid.
This process will include removal of damaged panel and installation
a new panel with new fasteners.
The total amount is for each additional panel required.
Bldgs. 1, 2 & 3
panels21 $ , 7
TARPON BA Y CONSTRUCTION
1220 SE 131h Ave Cape Coral, Fl. 33990
239/573-4733 FAX 239/573-8141
WEB SITE: tarponbayconstruction.com