01st Change Order 02/07/2022 CoNTRAcr CHANGE ORDER PROJECT TITLE:Marathon International Airport Terminal Reroof CHANGE ORDER NO: 1 INITIATION DATE: 01/27/22 TO CONTRACTOR: CONTRACT DATE: 3.17.2021 The Contract is changed as follows: The original (Contract Sum)(Guaranteed Maximum Price).......................................... $1,888,375.00 Net change by previously authorized Change Orders.................................................. $ 0.00 The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was.............$1,888,375.00 The(Contract Sum)(Guaranteed Maximum Price)will be(increased)(decreased) (unchanged)by this Change Order.......$ 0.00 The new(Contract Sum)_(Guaranteed Maximum Price)including this Change Order is....... $ 1,888,375.00 The Contract Time will be(Increased)(decreased)(unchanged)by............................... 0 days The date of Substantial Completion as of the date of this Change Order is....................... Detailed description of change order and Justification: Provide an inspection report by using camera to inspect 27 downspouts to check for drainage Issues. Provide video and report for underground sections of rain downspout discharge termination.Will provide as builts on provided plans if lines and discharge locations are not accurately indicated on original plans.This Is Phase 2 of the Gutter Drainage Inspections. This change Order is 0.01°/a of the original contract price. Not valid until signed by Owner.Architect(if applicable).and Contractor 2 1 12 2 ARCHITECT: Date CONTRACTOR: , y DIRECTOR OF AIRPORTS 3.2022 w._ Date .® MONROE COUNTY: y 02.07.2022 r _...� Asst./County Administrator Date In NROE COUNTY ATTOnNEY A iOY'E FORM PED 01 4EC ASSIS UNTY ATTORNEY Date 2/3/22 Change Order Attachment per Monroe County Code Section - ) • Change Order was not included in the original contract specifications. Yes( x ) No( ) If Yes, explanation: Provide an inspection report by using camera to inspect 27 downspouts to check for drainage Issues. Provide video and report for underground sections of rain downspout discharge termination.Will provide as builts on provided plans If lines and discharge locations are not accurately indicated on original plans.This is Phase 2 of the Gutter Drainage Inspections. This will be drawn against line item 80 of the budget. • Change Order was included in the original specifications. Yes ( ) No ( x ) If Yes, explanation of increase in price: • Change Order exceeds$50,000 or5%of contract price(whichever isgreater).Yes()No(x) If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes( x) No ( ) If no,explanation of why: • Change Order is correcting an error or omission in design document. Yes ( ) No( x ) Should a claim under the applicable professional liability policy be made? Yes ( )No( x ) Explain: C O N S T R U C T I O N G R O U P ® Contingengy Use Directive OWNER: PROJECT: Date: 10/12/21 Monroe County Board of Commissioners Marathon International Airport 1 100 Simonton Street Terminal Reroof PCO Number:2 REV Key West,FL 33040 9400 Overseas Highway Marathon,FL 33050 This proposed change order is for: Provide an inspection report by using camera to inspect 27 downspouts to check for drainage issues. Is additional time needed to perform scope changes? ®YES XNO Time Extension Changes to Contract Sum: Subtotak S 6,400,00 General Conditions: S 400.00 General Liability: $ 64.00� Subtotal-. $ 6,864.00 GC Fee: S 755.04 Subtotal: $ 7,619.04 Contractor's Bond $ 95.24 Total Proposed Amount: $ 7,714.28 Reason for Changes: ®Changes in scope given by architect or owner for aesthetic andor design reasons ®Changes resulting from events or circumstances:detective design,owner caused delays,differing site conditions Approved bmr Date: 5/ 21 El Declined by: Date: Comments: CGCO21647 1305-359-5269 1 PO Box 1706 Key West,FL 33041 1 www.morino-construction.com Gary's Plumbing and Fire,Inc. Proposal Ph. (305)296-6013 6409 2nd Terrace Suite i Key West,FL 33040 Date Ph.(30S)296-6oi3 garysplumbingi@aol.com 10/9/2021 Name/Address Marino Construction P.O.Box 17o6 Key West,FL 33041 Project Qty Total Ref:Marathon Airport Provide all labor,equipment,and material necessary to camera 27 down spouts and any connecting storm system within io'of the building and provide an inspection report. Labor 6,400.00 6,400.00 "Three of the down spouts on the second floor may require opening the walls to gain access.Wall opening and repair to be done by others." Subtotal $6,400.00 Signature/Title Sales Tax ( %) $0.00 Total $6,400.00 0,- M, , ,=--r- R,' C 0 N S T R U C T I 0 N G R 0 U P Confineny Use Directive(CUDp __ OWNER: PROJECT: Date: ll/2/21 Monroe Board of County Comissioners Marathon International Airport 1100 Simonton Street Terminal Reroof CUD Number:7 Key West,FL 33040 9400 Overseas Highway Marathon,FL 33050 This Contingency Use Directive is for: Provide video and report for underground sections of rain downspout discharge termination.Will provide as builts on provided plans if lines and discharge locations are not accurately indicated on original plans.This is Phase 2 of the Gutter Drainage Inspections. Is additional time needed to perform scope changes? YES XAINO Time Extension 0 Aa s Changes to Contract Sum: Cubtotal: 5 3,800.00 General Liability: $ 39.00 Subtotal: $ 3,838.00 GC Fee: S 441.37 Subtotal: S 4,279.37 Contractor's Bond S 64.19 Total Proposed Amount: S 4,343.56 Reason for Changes: Changes in scope given by architect or owner for aesthetic and/or design reasons ®Changes resulting from events or circumstances:defective design,owner caused delays,differing site conditions L_jApproved by: Date: " 1/ '� Declined by: Date: Comments: CGCO21647 1305-359-5269 1 PO Box 1706 Key West,FL 33041 I www.marino-construction.com Gary's Plumbing and Fire,Inc. Proposal Ph. (305)296-6013 6409 end Terrace Suite i Key West,FL 33040 Date Ph.(305)296-6oi3 11/2/2021 garysplumbingl @aol.com Name/Address Marino Construction P.O.Box 1706 Key West,FL 33041 Project Marathon Airport Total Qty Ref: Marathon Airport Provide video and report for underground sections of rain downspout discharge termination. Will provide as builts on provided plans if lines and discharge locations are not accurately indicated on original plans. Contract Labor 3,800.00 3,800.00 Exclusions: Removal of and possibly collapsing sections of discharge piping. Subtotal $3,800.00 Sales %) $0.00 Signature/Title Total $3,800.00