02nd Change Order 02/07/2022 MoNRoF, COUNTY/DEPARTMMT oF Ampom PROJECT TITLE: Marathon International Airport Terminal Reroof CHANGE ORDER NO: 2 INITIATION DATE: 01/27/22 TO CONTRACTOR: CONTRACT DATE: 3.17.2021 The Contract is changed as follows: The original (Contract Sum)(Guaranteed Maximum Price).......................................... $1,888,375.00 Net change by previously authorized Change Orders.................................................. $ 0.00 The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was.............$1,888,375.00 The(Contract Sum)(Guaranteed Maximum Price)will be(increased)(decreased) (unchanged) by this Change Order.......$ 0.00 The new(Contract Sum)_(Guaranteed Maximum Price)including this Change Order is....... $ 1,888,375.00 The Contract Time will be(increased) (decreased)(unchanged)by............................... 0 days The date of Substantial Completion as of the date of this Change Order is....................... Detailed description of change order and justification: Demo 2 existing antenna sites on roof top;Install new flex and conduit from existing location to antenna with weather head and J box at both antenna locations. Demo and remove existing 4 ft light.Install new 4 ft LED light in same location. Light is to be fed with existing wiring and switching. Remedy the non-existing box grounding at the ceiling mounted light fixtures as required by the local inspector. Demo existing puck light housing; Install new puck light housing. This change Order is 0.01%of the original contract price. Not valid until signed by Owner,Architect(if ap ).and Contractor a 22 ARCHITECT: _ -.- -Date CONTRACTOR: 1,14� - w .Date Y2.3.2022 DIRECTOR OF AIRPORTS s Date MONROE COUNTY: w 02.07.2022 sst./County Administrator Date NROE CO nNEY A , HOVE FORM y � PED O J. c hSSISTA U ATTORNEY Date 2/3/22 Change Order Attachment per Monroe County Code Section 2-58(b) • Change Order was not included in the original contract specifications. Yes ( x ) No( ) If Yes, explanation: Demo 2 existing antenna sites on roof top; Install new flex and conduit from existing location to antenna with weather head and j box at both antenna locations. Demo and remove existing 4 ft light.Install new 4 ft LED light in same location. Light Is to be fed with existing wiring and switching. Remedy the non-existing box grounding at the ceiling mounted light fixtures as required by the local inspector. Demo existing puck light housing; Install new puck light housing. This will be drawn against line item 70 of the budget. • Change Order was included in the original specifications. Yes ( ) No ( x ) If Yes, explanation of increase in price: • Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes( ) No(x) If Yes, explanation as to why it is not subject for a calling for bids: Project architect approves the change order. Yes(x) No ( ) If no,explanation of why: • Change Order is correcting an error or omission in design document. Yes ( ) No ( x ) Should a claim under the applicable professional liability policy be made? Yes( ) No( x ) Explain: C O N S T R U C T I O N G R O U P Contingency,Use Directive(CUD) OWNER: PROJECT: Date: 10/21/21 Monroe Board of County Comissioners Marathon International Airport 1100 Simonton Street Terminal Reroof CUD Number:3 Key West,FL 33040 9400 Overseas Highway Marathon,FL 33050 This proposed change order is for: Demo 2 existing antenna sites on roof top;Install new flex and conduit from existing location to antenna with weather head and j box at both antenna locations. Is additional time needed to perform scope changes? ®YES ®NO Time Extension 0 days Changes to Contract Sum: Subtotal: $ 4,127.19 General Liability: $ 41.25 Subtotal: $ 4,169.07 OC Fee: S 479.44 Subtotal: S 4,648.51 Contractor's Bond $ 69.73 Total Proposed Amount: $ 4,718.24 Reason for Changes: Changes in scope given by architect or owner for aesthetic and/or design reasons x❑Changes resulting from events or circumstances:defective design,owner caused delays,differing site conditions Approved by: Date: 11 J / 1 Declined by: Date: Comments: CGCO21647 {305-359-5269 1 PO Box 1706 Key West,FL 33041 1 www.madno-construction.com To-mWm Electric LLC Eartmate 1665 NARCISSUS AVE VTOMKIMS ELECTRIC BIG PINE KEY, FL33043 US +1 3053008451 1'1-'- C C7MC.'., (30S) goo -84SI info@tomkinselectric.com RGSMENrIAL COMMERCIAL MAMNE www.tomkinselectric.com ADDREM John Foundas Marino E-STMAH. DAM 1191 10/18/2021 P.ROJEGTNAME RFI #3 DATE DESCRIPTION QTY WE AMOUNT Matefial Wire way; 1 1,487.79 1,487.79 Conduit; Fittings; J-Box; Weatherhead-goose neck; Straps; Hardware; Labor Demo 2 existing antenna sites 16 165.00 2,640.00 on roof top; Install new flex and conduit from existing location to antenna with weather head and j box at both antenna locations; If accepted please sign below TOTAL $4,127-79 Accepted By Accepted Date Im R -1- N-0 C O N S T R U C T I O N G R O U P CtanfinencyUse"Directive CUD OWNER: PROJECT: Date: 10/21/21 Monroe Board of County Comissioners Marathon International Airport 1100 Simonton Street Terminal Rcroof CUD Numbcn 4 Key West,FL 33040 9400 Overseas Highway Marathon,FL 33050 This proposed change order is for: Demo and remove existing 4 It light.Install new 4 ft LED light in same location.Light is to be fed with exisiting wiring and switching. Is additional time needed to perform scope changes'? YF.S X NO Time Extension 0 days_ Changes to Contract Sum: Subtotal: S 757.93 General Liability: $ 7.55 Subtotal: $ 765.51 GC Fee: $ 88.03 Subtotal: $ 853.54 Contractor's Bond S 12.50 Total Proposed Amount: $ 866.34 Reason for Changes: Changes in scope given by architect or owner for aesthetic and/or design reasons X❑Changes resulting from events or circumstances:defective design,owner caused delays,differing site conditions Approved by: �, Date:® 11 1 Declined by: Date: Comments: CGCO21647 1305-359-5269 1 PO Box 1706 Key West,FL 33041 I .madno-construction.com TornUm Electric LLC -Eadmate 1665 NARCISSUS AVE )TOMMNS ELECTPIC I LC BIG PINE KEY, FL 33043 US +1 3053008451 (30S)300 -e4SI info@tomkinselectric.com R45SIOLMNTIAL COMMERMAL MARINE www.tomkinselectric.com ADDRESS John Foundas Marino # DKEE 1192 10/16/2021 PROJEGT NAK41E RF146 DATE DESCRIPTION QTY RATE AMOUNT Mateidal 4-ft LED Commercial Vaportite 1 132.93 132.93 Light; Labor Demo and remove existing 4 ft 5 125.00 625.00 light; Install New 4 ft LED light in same location; (Light is to be fed with existing wiring and switching); If accepted please sign below TOTAL $7-57M Accepted By Accepted Date ­0 C O N S T R U C T 1 O N G R O U P Contin enc Use D(rective CUD OWNER: PROJECT: Date: 12/8/21 Monroe Board of County Comissioners Marathon International Airport 1100 Simonton Street Terminal Reroof CUD Number:15 Key West,FL 33040 9400 Overseas Highway Marathon,FL 33050 This Contingency Use Directive is for: Remedy the non-existing box grounding at the ceiling mounted light fixtures as required by the local inspector. Is additional time needed to perform scope changes? YES X NO Time Extension 0 days Changes to Contract Sum: Subtotal: S 3,587.00 General Liability: $ 35.87 Subtotal: $ 3,622.87 GC Fee: $ 416.63 Subtotal: $ 4,039.50 Contractor's Bond S 60.59 Total Proposed Amount: S 4,100.09 Reason for Changes: Changes in scope given by architect or owner for aesthetic and/or design reasons ®Changes resulting from events or circumstances:defective design,owner caused delays,differing site conditions w Approved by: -'`� Date: 1 / / 1 Declined by: Date: Comments: CGCO21647 !305-359-5269 1 PO Box 1706 Key West,FL 33041 i .madno-construction.com WWW.TOMKINSC-LECTRICCOM (305) 300-8451 December 3, 2021 To: Ms. Katie Beardsley Marino Construction Group, Inc. 7025 Shrimp Road, Suite 2E Key West, FL 33040 Re: Florida Keys Marathon International Airport Terminal Re-Roof Rehabilitation Dear Ms. Beardsley: Tomkins Electric LLC is pleased to offer this proposal for the electrical work on the above referenced project for the change order to remedy the non-existing box grounding at the ceiling mounted light fixtures as required by the local inspector. Proposal pricing includes only electrical work as described below. The total cost for electrical work is THREE THOUSAND,FIVE HUNDRED AND EIGHTY-SEVEN DOLLARS($3,587.00). WORK INCLUDED: Drill and tap holes in each of forty-four(44)ceiling mounted light fixtures; Furnish and install a#10 AWG grounding lug with hardware at the tapped holes in each of the forty- four(44)ceiling mounted light fixtures; Connect the ground lug to the circuit ground wire with a#10 AWG conductor at each of the forty-four (44)ceiling mounted light fixtures; STIPULATIONS: WORK WL1., BE COMPLETED VI TOM KI S ELECTRIC LLC STANI)ARD .G RATES; ESCORTS, WHERE REQUIRED,TO BE FURNISHED BY MARINO CONSTRUCTION GROUP, INC.; Sales tax on materials is included; Cost for bond is not included; Encountering or handling hazardous materials is not included; No dumpster or disposal is included; Any work beyond this scope is not included; All work to be completed in a competent manner according to standard practices and the local authority having jurisdiction; Tomkins Electric LLC would like to thank you for the opportunity to provide this proposal.Should there be any questions or if additional information is needed, please feel free to contact me at any time, Sincerely, James Tomkins Tomkins Electric LLC (305)300-8451 C O N S T R U C T I O N G R O U P Contingency Use Directive (CUD OWNER: PROJECT: Date: 12/10/21 Monroe Board of County Comissioners Marathon International Airport 1100 Simonton Street Terminal Reroof CUD Number: 17 Key West,FL 33040 9400 Overseas Highway Marathon,FL 33050 This Contingency Use Directive is for: Demo existing puck light housing;Install new pack light housing. Is additional time needed to perform scope changes'? rjYES ®NO Time Extension 0 days _ Changes to Contract Sum: Subtotal: $ 3,550.00 General Liability: S 35.50 Subtotal: S 3,585.50 GC Fee: S 412.33 Subtotal: S 3,997.83 Contractor's Bond S 59.97 Total Proposed Amount: $ 4,057.80 Reason for Changes: ®Changes in scope given by architect or owner for aesthetic and/or design reasons ®Changes resulting from events or circumstances:defective design,owner caused delays,differing site conditions 1113/22 Approved by: Date: El Declined by: Date: Comments: CGCO21647 1305-359-5269 1 PO Box 1706 Key West,FL 33041 1 www.morino-construction.com Tornldns Electdc LLC EsIdmate 1665 NARCISSUS AVE VTOMKINS ELECTRIC BIG PINE KEY, FL 33043 US +1 3053008451 (90s) 300 -8451 info@tomkinselectric-com ReSfDENTAL COMMERCIAL MARWE www.tomkinselectric.com ADDRESS John Foundas Marino Construction Group F-IM"MAI"E# DA',rF- 1215 12/09/2021 PROJECT NAME Knee Wall Puck Style Light Fixt DATE DESCRIPTION CITY RATE AMOUNT Labor Demo existing puck light 1 3,500-00 3,500-00 housing; Install new 14 puck light housing for new lights according to drawing E-1 01; ***Demo of existing lights will be provided by Tomkins Electric***; 'Repair of knee wall concrete and support to mount light can will be done by Narino Construction Group*** Material Hardware; 1 50-00 50-00 If accepted please sign below TOTAL $3A%U0 Accepted By Accepted Date