03rd Change Order 02/07/2022 CONMCT CHANGE ORDER
PROJECT TITLE: Marathon International Airport
Terminal Reroof CHANGE ORDER NO: 3
INITIATION DATE: 01/27/22
TO CONTRACTOR: CONTRACT DATE:1 3.17.2021
The Contract is changed as follows:
The original (Contract Sum)(Guaranteed Maximum Price).......................................... $1,888,375.00
Net change by previously authorized Change Orders.................................................. $ 0.00
The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was.............$1,888,375.00
The(Contract Sum)(Guaranteed Maximum Price)will be(increased)(decreased)
(unchanged)by this Change Order.......$ 0.00
The new(Contract Sum)_(Guaranteed Maximum Price)including this Change Order is....... $ 1,888,375.00
The Contract Time will be(increased) (decreased)(unchanged)by............................... 0 days
The date of Substantial Completion as of the date of this Change Order is.......................
Detailed description of change order and justification:
Provide and weld in 2 locations 3"by at least 15'tall, capped on top pipes provided and welded by
Key West Awnings.Will be welded following the
plans provided by the architect.
This change Order is 0.01%of the original contract price.
Not valid until signed by Owner,Architect(If apj2llcablel,and Contractor
ARCHITECT: r M
..
Date
CONTRACTOR: _. r
D
DIRECTOR OF AIRPORTS
' 2.3.2022
Date
02.07.2022
MONROE COUNTY:
A st./County Administ or Date
11 A OVE U A FO NEY
t
RNM
PED O J. .aR
ASSISTA U ATTORNEY
Date 2/3/22
SectionChange Order Attachment per Monroe County Code -
• Change Order was not included in the original contract specifications. Yes( x ) No ( )
If Yes, explanation:
Provide and weld in 2 locations 3"by at least 15'tall,capped on top pipes provided and welded by
Key West Awnings.Will be welded following the
plans provided by the architect.
This will be drawn against line item 70 of the budget.
• Change Order was included in the original specifications. Yes ( ) No ( x )
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes( ) No(x)
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes(x) No ( )
If no,explanation of why:
• Change Order is correcting an error or omission in design document. Yes ( ) No ( x )
Should a claim under the applicable professional liability policy be made? Yes( ) No( x )
Explain:
C O N S T R U C T I O N G R O U P
ConfingeIll. Use Directive CUD
OWNER: PROJECT: Date:10/21/2 t
Monroe Board of County Comissioners Marathon International Airport
1100 Simonton Street Terminal Reroof CUD Number:5
Key West,FL 33040 9400 Overseas Highway
Marathon,FL 33050
This proposed change order is for:
Provide and weld in 2 locations 3"by at least 15'tall,capped on top pipes provided and welded by Key West Awnings.Will be welded following the
plans provided by the architect.
Is additional time needed to perform scope changes? ❑YES ❑X NO Time Extension 0 days
Changes to Contract Sum:
Subtotal: S 6,342.50
General Liability: $ 63.43
Subtotal: $ 6,405.93
GC Fee: S _736.68
Subtotal: $ _—u____- TMxx7,142.61_
Contractor's Bond S 107.14
Total Proposed Amount: $ 7,249.75
Reason for Changes:
®Changes in scope given by architect or owner for aesthetic and/or design reasons
❑Changes resulting from events or circumstances:defective design,owner caused delays,differing site conditions
❑ Approved_bx._.._ - .__._m _ ___ ...._. Date: 1 /28/21
❑ Declined by: Date:
Comments:
CGCO21647 1305-359-5269 1 PO Box 1706 Key West,FL 33041 1 www.marino-construction.com
KEY WEST AWNINGS •
1075 Duval St, C-21 #222
Key West,FL 33040 Date Estimate
10/1 T2021 1367
Name/Address
Marino Construction
Harold Schreckengost
7025 Shrimp Rd,Suite 2E
Key West,FL 33040
Project
Description Qty Cost Total
The 3"by 3" edge angle can be replaced in the limited length where 3 1,100.00 3.300.00T
severe corrosion has occurred approximately 5'to 8'in each
location.At these locations,cut the vertical leg of the angle flush
with the bottom leg and weld a new plate matching the leg length
and thickness of the removed angle.Stitched weld the new plate to
the bottom leg of the angle with a 2-6 1/4"fillet weld along the
entire length of the
repaired area.Weld the interface between the existing vertical leg
and the new repair length at the ends of the repair to allow
for load transfer across the vertical elements.
Provide and weld in 2 locations 3"by at least 15'tall,capped on top 2 1,300.00 2,600.00T
pipes provided and welded by Key West awnings will be welded
following the plans provided by the architect.Taking all the
necessary safety measures by providing welding blankets this can be
done as quickly as this coming week or weekend so roofers can be
doing their job without any interruptions.
7.50% 442.50
Total $6,342.50
Customer Signature