1st Change Order 02/07/2022 MONROE CouNTY/DEPARTmENT OF AiRpom CONTRACT CHANGE OMER PROJECT TITLE: CHANGE ORDER NO: I FBO ACCESS ROAD, KWIA INITIATION DATE: JANUARY 20, 2022 TO CONTRACTOR: CHARLEY TOPPINO &SONS, INC CONTRACT DATE: APRIL 21, 2021 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price).......................................... $3,163,649.67 Net change by previously authorized Change Orders.................................................. $ 0.00 The(Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$ 3,163,649.67 The(Contract Sum) (Guaranteed Maximum Price)will be(increased l(decreased) (unchanged) by this Change Order.......$ 49,986.60 The new(Contract Sum)_(Guaranteed Maximum Price) including this Change Order is....... $ 3,213,636.27 The Contract Time will be(increased) ................. 0 days J(decreased) (unchanged) by.............. The date of Substantial Completion as of the date of this Change Order is....................... July 15, 2022 Detailed description of change order and justification: This change order is to Increase size of watermain, change to HDPE from RCP, and line item quantity increases to match original bid schedule per attached quote. This change Order is 1.58%of the original contract price. Not valid until sl ned by Owner.Architect i if a licabiftli and Contractor ARCHITECT: 11260-022-.— Date CONTRACTOR: te - to DIRECTOR OF AIRPORTS ...... 2.1.22 Date 02.07.2022 MONROE COUNTY: A st./ o Administrator Date ACDVE NFIOE COUNW PED9C]0JERCA9G-----' ASSISTA T- UNTY ATTORNEY 2/3/22 Change Order Attachment per Monroe County Code Section • Change Order was not included in the original contract specifications. Yes No(X If Yes, explanation: • Change Order was included in the original specifications. Yes No (X If Yes, explanation of increase in price: • Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes No(X) If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes No If no,explanation of why: • Change Order is correcting an error or omission in design document. Yes No (X ) Should a claim under the applicable professional liability policy be made? Yes No (X) Explain: Admmllllbk. MW Attention: Rob Overby DATE 117/22 McFarland Johnson 2409 North Roosevelt Blvd Suite 4 Key West,Florida 33040 ITEMIZED QUANTITIES Location: 3491 S Roosevelt Blvd,Key West FL 33040 Scope: RFP-Change of Watermain Size(Sheet UT-05 to UT-07) hem Dosed bon Quantitv I Units Cost per Unit Line Item Cost Notes _j_C900 R22 Upsizing(6"to 8") 580.0 LF $ 9.47 -$--- 5�492.60 ADD 2 8"GV.Pipe Extension.&Ca o 1.0 EA _$ 2 918oD $ 2,918.00 ADD 3 Quantity increase'inlets,DT BOT,T 9D,c10 6.0 EA $ 9,920,00 $_ 59 520.00 ADD ..h $ 6_7 930.60 ADD Deductive CO for Materials 18-RCP 912.0 LF _I ......196.001 $ J178,752.00)DEDUCT 5 24'RCP 560 LF $ -224.0-01 $ 16484.00 DEDUCT _L_jjL5_216.00j DEDUCT 6 18'HDPE Storm Solid RDe 91Z0 LF $ 177.00 $_161424W ADD 7 24'HDPE Storm Solid ffpe 56.0 ............'7F ...... $ 283.00 $ 1584800 ADD $ 1177 272.00 ADD Subtotal $ 49.986.60 8 Performance/Pa ment Bonds $20 f)nfThnu-qnnrj1 1.0 LS 9 MobilizabonfDemobilizabon 1'0 LS 10 General Conditions 1.0 LS $ Total: $ 49,986.60 Notes: Net 30 Davment terms.DroDosal valid for 30 da Exclusions: soils removal.soddin Prepared by: Estimator Charley roppino&Sons,Inc. ................... �122 Sheet I of I Date: T