12/15-E6 Tarpon Belly Keys, Geotechnical Services SERVICESMASTER AGREEMENT FOR PROFESSIONAL
TASK ORDER FORM
Effective Date Upon Execution Task Order No. 12/15-E6
Client Project o.404-630196-SC_00038 (G1007) Engineer Project No. E7
This Task Order is entered into on the effective date noted above pursuant to the "Master
Agreement for Professional Services" between Monroe County, Florida ("Client") and JACOBS
PROJECT MANAGEMENT CO. ("Consultant"), dated February 15, 2017 ("Agreement"). The
Agreement is incorporated herein and forms an integral part of this Task Order.
Services Authorized—Tarpon eKeys,Additional Geotechnical Services
Client authorizes Consultant to perform the Services described in Exhibit A attached hereto and
incorporated herein, which Exhibit A is marked with the above noted Task Order No. and
consists of_ 1 µ e(s).
Pricing
®,,/ Time and Expense per Agreement and Appendix B to the Agreement.
,- Firm Fixed Price of
_/_. - Other(Describe):
NRaE cauNrY ArTc�nNEv
A ROVE €OPM
Schedule
cV .tr�c
Services may commence on Execution PED a J. CA -
ASSI LINTY AMRNPY
Services will cease by w 35 days „ Dale 2/10/22
Recommended y: Approved by:
Director of Airports Date ® ®2022 00/unty AdministratorDate: 02.10.2022
JACOBS PROJECT MANAGEMENT CO
Jeffrey Digi-y signed by Jeffrey D.Acron
D. DN:cn-jefffey D.Acton,ooacobs
VPMCOLCM
t0nft- eoyA30 Jacohs. .c•uti
Jacqueline
y--- -- _ Date:202201.i3 1836:z4.OVW
£;Yd c¢x+axttauaa3Eerac c=Ja
e in�.Xa�np4Ts�
9tYd�4fa�dY°.:LtitP.B Xt98d e'A+,.8 CGC?
Witness Ross 09.2ev,01 14 06 2a n 006 W Title S. Region P Services Group Leader
File: MSTR APS Monroe County
Page 1 of 1
Exhibit A—(12/15-E6)
Scope of Services
Monroe County Airports
Key West International Airport
Tarpon Belly Keys -Additional Geotechnical Services
SCOPE OF WORK
Jacobs Project Management Company will provide the services as outlined in the Fee schedule
and in Tierra's Scope of Services and Fee Schedule.
Assumptions/Design Parameters
1. All work will be performed pursuant to the Master Agreement for Professional Services
between Project Management Co. and Monroe County, FL agreement signed between the
parties on February 15, 2017.
Page 1 of 1
JACOBS ENGINEERING GROUP JOB HOUR AND FEE ESTIMATE
Monroe County
Airport:
Key West International Airport
Project:
Tarpon Belly Keys-Additional Geotechnical Services-PSO#E6(12/16-E6)
FEE SUMMARY
BASIC SERVICES
Hours Fee DBE AMOUNT
Article A:Data Collection Services 18 $ 2,662
Total Basic Services Lump Sum Fee $ 2,662 $ -
SPECIAL SERVICES Hours Fee DBE AMOUNT
Article A:Data Collection
Tierra South Florida,Inc.-Geotech(Lump Sum) $ 42,680 $ 42,680
Total S octal Services Lump Sum Fee $ 42,680 $ 42,680
TOTAL LUMP SUM PROJECT FEE $ 46,232 $ 427580
DBE Percentage 94.14%
Page I of 2
December 29, 2021
Jacobs
200 West Forsyth Street, Suite 1520
Jacksonville, Florida 32202
Email: lasa.ennis@jacobs.com
Attention: Ms. Kaly Queiroz, P.E.
Airport Project Lead
Re: Proposal for Geotechnical Services
Key West International Airport(EYW)
Commercial Apron Mitigation—Tarpon Belly Key
Monroe County,Florida
TSF Proposal No.: 2112-924
Dear Kaly:
As requested, TSF is pleased to submit this proposal for the above-referenced project. Based on
information provided by Jacobs, the project will include I new mitigation area located at Tarpon
Belly Key and accessible by boat only.
PROPOSED SCOPE OF WORK
Based on information provided to this office, we propose to perform the study as follows:
Miti ation Areal 0.92 acres
6 SPT borings to a depth of 10 feet
The boring locations will be provided by Jacobs and located in the field by TSF. The locations are
accessible via boat. Due to the vegetation present on the islands, a tripod will be used to advance
a spoon manually and collect samples to 10 feet below grade or refusal, whichever comes first.
It is our understanding that this is undisturbed land, and therefore, we do not anticipate
underground utility lines to be present in the study area.
Upon completion of the field exploration,laboratory testing will be performed on selected samples.
A report will be issued that contains the field exploration results and laboratory data.
2765 Vista Parkway,Suite 10 o blest I'ahn Beach,Florida 33411
561 6II7 536® :ate' 1 :.GL=
State of Florida Professional Engineers License#28073
Jacobs
TSF Proposal:2112-924
Page 2
ESTIMATED FEES
It is proposed that the fee for the performance of the services outlined above is determined on a
lump sum basis and that the work be performed pursuant to TSF's General Conditions enclosed
herewith and incorporated into this proposal. On the basis of the proposed quantities, it is
estimated that the lump sum fee will be$42,580.00. Fee breakdown is being provided for general
reference only.
Our estimate covers the work needed to present the results.Not included are reviews of drawings,
preparation of construction specifications, special conferences and any other work requested after
submittal of our report.
SCHEDULE AND AUTHORIZATION
TSF will proceed with the work after receipt of a signed copy of this proposal. With our present
schedule, we can commence work within several days of project approval (weather permitting)
and fieldwork is expected take about 4 days to complete. The results can be submitted in about
three weeks after completion of the field work.
We at TSF appreciate the opportunity to submit this proposal and look forward to working with
you on this project. If you should have any questions concerning our proposal, please contact our
office.
Respectfully submitted,
TIERRA SOU FLORIDA, INC.
Raj Kr' nasamy, P.E. Ramer ar''Ve ul"a,P.E.
Presi nt Principal Engineer
Attachment: Fee Breakdown
Jacobs
TSF Proposal:2112-924
Page 3
TIERRA SOUTH FLORIDA,INC.
UNIT RATE FEE SCHEDULE
Unit #of Units Unit Pnce Total
L FIELD INVESTIGATION
Mobilization of Men and Equipment
Tripod+Equipment LS 1 $ 35000 $ 35000
Support Boat DAY 9 $ 50000 $ 450000
Standard Penetration Test Bonngs
(By Truck-Mounted Equipment)
Land:0-50 ft depth L F 0 $ 1800 $ 000
50-100 It depth L F 0 $ 2000 $ 000
Grout-Seal Boreholes
(By Truck-Mounted Equipment)
Land:0-50 ft depth L F 0 $ 675 $ 000
50-100 It depth L F 0 $ 800 $ 000
Casing
(By Truck-Moulted Equipment)
Land: 0-50 It depth L F 0 $ 9.00 $ 000
50-100 ft depth L F 0 $ 10.00 $ 000
Drill Crew-Helpers+Boat Operator(4 crew) Day 6 $ 3000.00 $ 18,00000
Field Permeability Tests Test 0 $ 85000 $ 000
Pavement Cores,Asphalt Each 0 $ 22500 $ 000
Pavement Core Equipment day 0 $ 400.00 $ 000
MOT LS 0 $ 120000 $ 0,00
8. LABORATORY TESTING
Visual ExaminationlStrably Per Hour 4 $ 100.00 $ 40000
Natural Moisture Content Tests Test 4 $ 10.00 $ 4000
Grain-Size Analysis-Full Gradation Test 4 $ 65.00 $ 26000
Grairv-Size Analysis-Single Sieve Test 4 $ 35.00 $ 14000
Organic Content Tests Test 4 $ 3500 $ 14000
Atterberg Limit Tests Test 0 $ 7500 $ 000
Liquid Limit Tests(Orgy) Test 0 $ 5200 $ 000
Plastic Limit Tests(Only) Test 0 $ 3350 $ 000
Laboratory C BR+Sampling Test 0 $ 70000 $ 000
Grain-Size with Hydrometer Test 0 $ 11500 $ 000
Proctor Test a)Modified Test 0 $ 10800 $ 000
b)Standard Test 0 $ 10200 $ 000
Bitumen Extraction Test 0 $ 15000 $ 000
Bitumen Gradation Test 0 $ 15000 $ 000
III ENGINEERING/COORDINATION/MANAGEMENT
Project Manager Hour 0 $ 16500 $ 000
Principal Engineer Hour 4 $ 150.00 $ 60000
Project Engineer Hour 6 $ 100.00 $ 60000
Senior Technician Hour 30 $ 85.00 $ 2,55000
CADD Hour 8 $ 75.00 $ 60000
Badging/training Her 0 $ 65.00 $ 000
IV. Travel,Hotel,per-diem LS 8 $ 1800.00 $ 14,40000
$ 42,580.00