04th Change Order 02/11/2022 MONROE COUNTY/DEPARTMENT OF AIRPORTS
CONTRACT CHANGE ORDER
PROJECT TITLE: Marathon International Airport
Terminal Reroof CHANGE ORDER NO: 4
INITIATION DATE:01/27/22
TO CONTRACTOR: CONTRACT DATE: 03.17.2021
The Contract is changed as follows:
The original(Contract Sum)(Guaranteed Maximum Price).......................................... $ 1,888,375.00
Net change by previously authorized Change Orders.................................................. $ 0.00
The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was.............$ 1,888,375.00
The (Contract Sum)(Guaranteed Maximum Price)will be(increased) (decreased)
(unchanged)by this Change Order.......$ 0.00
The new(Contract Sum)(Guaranteed Maximum Price)including this Change Order is....... $ 1,888,375.00
The Contract Time will be(increased) (decreased)(unchanged)by............................... 0 days
The date of Substantial Completion as of the date of this Change Order is.......................
Detailed description of change order and justification:
Bee removal from column-Includes five(5) hours of labor and materials.
Purchase and Install clearance signage/bars for airport terminal.
Pressure clean, prime and finish coated soffits.
This change Order is 0.01%of the original contract price.
Not valid until signed by Owner, Architect(if applicable),and Contractor
2i'8/ '.
ARCHITECT:
Date.._
r�s3
CONTRACTOR: n . ,..
Date
DIRECTOR OF AIRPORTS „+M ,_
Date
MONROE COUNTY: °' _
A/sst./County dmin rator Date 02.11.2022
A �E c uN Y A f�NEY
C
PEDt C
ASSIST LINTY ATTORNEY
Date 2/10/22
Change Order Attachment per Monroe County Code Section - ( )
• Change Order was not included in the original contract specifications. Yes ( x ) No
If Yes, explanation:
Bee removal from column-Includes five(5)hours of labor and materials.
Purchase and Install clearance signagelbars for airport terminal.
Pressure clean, prime and finish coated soffits.
This will be drawn against line item 70 of the budget.
• Change Order was included in the original specifications. Yes ( ) No ( x )
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes( ) No(x)
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes( x) No ( )
If no,explanation of why:
• Change Order is correcting an error or omission in design document. Yes( ) No ( x )
Should a claim under the applicable professional liability policy be made? Yes( ) No ( x )
Explain:
C O N S T R U C T I O N G R O U P
Gontin envy Use Directive jgUD _
OWNER: PROJECT: Date: 12t2r21
Monroe Board of County Comissioners Marathon International Airport
1100 Simonton Street Terminal Reroor CUD Number: 12
Key West,FL 33040 9400 Overseas Highway
Marathon,FL 33050
This Contingency Use Directive is for:
Bee removal from column-Includes five(5)hours of labor and materials.
Is additional time needed to perform scope changes? ®YES ®NO Time Extension 0 dav�s
_ _.... .. ...
Changes to Contract Sum:
Subtotal: $ 475.00
General Liability: $ 4.75
Subtotal: $ 479.75
GC Fee: $ 55.17
Subtotal: $ 534.92
Contractor's Bond $ 8.02
Total Proposed Amount: $ 542.94
Reason for Changes:
®Changes in scope given by architect or owner for aesthetic and/or design reasons
®Changes resulting from events or circumstances:defective design,o%kner caused delays,differing site conditions
Ej Approved by: Date: 1 / / 1
Declined by: Date:
Continents:
CGCO21647 I305-359-5269 1 PO Box 1706 Key West,FL 33041 i www.marino-construction.com
4
CTO
Ln
n
v
s
T
f i
C O N S T R U C T I O N G R O U P
Contingent Use;Directiv CU
OWNER: PROJECT: Date:1213/21
Monroe Board of County Comissioners Marathon International Airport
1100 Simonton Street Terminal Reroof CUD Number: 14
Key West,FL 33040 9400 Overseas Highway
Marathon,FL 33050
This Contingency Use Directive is for:
Purchase and Install clearance s gnage/bars for airport terminal.
Is additional time needed to perform scope changes? ❑YES ®NO Time Fxtension 0 days
Changes to Contract Sum:
Subtotal: $ 3,415.00
General Liability: $ 34.15
Subtotal: $ 3,449.15
GC Fee: S 396.65
Subtotal: S 3,845.80
Contractor's Bond S 57.69
Total Proposed Amount: $ 3,903.49
Reason for Changes:
ElChanges in scope given by architect or owner for aesthetic andror design reasons
Changes resulting from events or circumstances:defective design,owner caused delays,differing site conditions
® Approved by: Date:
Declined by: _ Date:
Comments:
CGCO21647 !305-359-5269 1 PO Box 1706 Key West,FL 33041 1 www.marino-construction.com
C O N S T R U C T I O N G R O U P
Yd December 2021
Monroe Board of County Commissioners
1100 Simonton Street
Key West, FL 33040
Project: Marathon International Airport Terminal Reroof
Mr. Forney,
We are pleased to offer our proposal for the installation of the Clearance Signs at the Marathon
International Airport as per the discussed scope of work. Upon acceptance of this proposal,
Marino Construction will verify product specifications and place orders for materials to begin the
scope of work as soon as possible.
Scope of work to include:
• Order and install three (3) Clearance Signs (as per specs provided by Jacobs) for Airport
Terminal
• Includes materials: chains and bolts (Grade 316 Stainless Steel Aluminum as per specs
provided by Jacobs)
• Labor
• Supervision
• Clean-Up/Debris Removal
Exclusions:
• Permit Fees
Survey, Layout or elevation certificates
• Painting
Sitework or Landscaping
• Mechanical, Plumbing or Electrical
CGCO21647 1 305-359-5269 PO Box 1706 Key West, FL 33041 www.marino-construction.com
u
C O N S T R U C T I O N G R O U P
Proposal Amount: $ 3,415.00
In the event you have any questions regarding the content of this Proposal, please contact me at
352-585-7517. We appreciate your consideration and look forward to hearing from you.
Kind Regards,
Jenny Socha
Director of Operations
Marino Construction Group, Inc.
PO Box 1706
Key West, FL 33041
C: 352-585-7517 E:jsocha@marno-construction.com
CGCO21647 1 305-359-5269 1 PO Box 1706 Key West, FL 33041 www.marino-construction.com
C O N 5 T R U C T 1 O N G R O U P
ContinDn Use Direcfive'CUD
OWNER: PROJECT: Date:12/10/21
Monroe Board of County Comissioners Marathon International Airport
1100 Simonton Street Tcn-ninal Reroof CUD Number: 13-REV
Key West,FL 33040 9400 Overseas Highway
Marathon,FL 33050
This Contingency Use Directive is for:
Pressure clean,prime and finish coated soffits
Is additional time needed to perform scope changes? ®YES X]NO Time Fxtension 0 da s
Changes to Contract Sum:
Subtotal: $ 3,500.00
General Liability: $ 35.00
Subtotal: $ 3,535.00
GC Fee: $ 406.53
Subtotal: $ 3,941.53
Contractor's Bond $ 59.12
Total Proposed Amount: $ 4,000.65
Reason for Changes:
Changes in scope given by architect or owner for aesthetic and/or design reasons
Changes resulting from events:ar circumstances:defective design,owner caused delays,differing site conditions
Approved by: Date: 1 11 Y21
Declined by: Date:
Comments:
CGCO21647 {305-359-5269 1 PO Box 1706 Key West,FL 33041 ` www.marino-construction.com
essery Painting, Inc.
q. 15850 P,ne Ridge Road,Sulte 5
Fort Myers,FL 33908 US
(239)481-9632
Messaryptg@msn.com
INVOICE
13181
Marino Construction Group,Inc. 12/08/2021
7005 Shrimp Road Net 30
Key West,FL 33040 01/07/2022
FI.Keys Marathon airpor
DESCRIPTION ACTIVITY QTY RAT P i t
Pressure cleaned,Primed and Finish Painting 1 3,500.00 3,500.00
coated Soffits per Rob
r