06th Change Order 02/28/2022 PROJECT TITLE: Marathon International Airport Terminal Re-Roof Project CHANGE ORDER NO: 6 INITIATION DATE: February 8,2022 TO CONTRACTOR: CONTRACT DATE: 03.17.2021 The Contract Is changed as follows: The original (Contract Sum)(Guaranteed Maximum Price).......................................... $1,888,375.00 Net change by previously authorized Change Orders.................................................. $ 0.00 The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was.............$1,888,375.00 The(Contract Sum)(Guaranteed Maximum Price)will be increased (decreased) (unchanged)by this Change Order.......$ 0.00 The new(Contract Sum)_(Guaranteed Maximum Price)including this Change Order is....... $ 1,888,375.00 The Contract Time will be(increased) (decreased)(unchanged)by............................... F6_0__1 days The date of Substantial Completion as of the date of this Change Order is....................... Detailed description of change order and justification: Final Completion time extension requested due to roofing subcontractor being understaffed caused by COVID outbreaks within the company multiple times. Time extension to start February 8,2022. This change Order is g.QJ0&of the original contract price. Not valid until signed by Owner, Architect(if aaQlicablel,and Contractor ARCHITECT: Date CONTRACTOR: ` µ Die DIRECTOR OF AIRPORTS 4 A04 I Date MONROE COUNTY: _ ,..., 02.28.2022 sst./County Administrator Date � 4 N OE RN PRO ORM ADO ASSISTANT COUNTY ATrORNEY, Date -- �. SectionChange Order Attachment per Monroe County Code - • Change Order was not included in the original contract specifications. Yes (x ) No( ) If Yes, explanation: Final Completion time extension requested due to roofing subcontractor being understaffed Caused by COVID outbreaks within the company multiple times.Time extension to start February 8,2022. • Change Order was included in the original specifications. Yes ( ) No ( x ) If Yes, explanation of increase in price: • Change Orderexceeds$50,000 or5%of contract price(whichever isgreater).Yes()No(x) If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes(x ) No ( ) If no,explanation of why: Change Order is correcting an error or omission in design document. Yes ( ) No( x ) Should a claim under the applicable professional liability policy be made? Yes ( ) No ( x) Explain: C O N S T R U C T I O N G R O U P aspi'".a$.'-,R��S.4lFw. ^� ft�'t.,4*�° '.. r OWNER: Monroe Board of County Comissioners PROJECT: Marathon International Airport Date: 2l7/2022 1100 Simonton Street Terminal Reroof Contract Date: 2/27/2021 Key West,FL 33040 9400 Overseas Highway Change Order No: 6 Marathon,FL 33050 The Contract Is changed as follows: Final Completion time extension requested due to roofing subcontractor being understaffed caused by COVID outbreaks within the company mutliple times.Time extension to start February 8,2022. The Original Contract Sum was $ 1,888,375.00 The net change by previously authorized Change Orders $ The Contract Sum prior to this Change order was $ 1,888,375.00 The Contract Sum will be by this Change Order in the amount of The new Contract Sum including this Change Order will be $ 1,889,375.00 The Contract Time will be Increased by (60)days The date of Substantial Completion as of the date of this Change Order,therefore is 8-Apr-22 NOT VALID UNTIL SIGNED BY TILE OWNER,CONTRACTOR AND ARCHITECT: Marino Construction Group,Inc. OANI ER(Finn Name) CONTRACTOR(Finn Vame) ARCHITECT(Finn Naine) P.O.Box 1706 Key West,FL 33041 ADDRESS - ADDRESS ADDRESS BY(Signature) BY(Signature) BY(Signature) (Printed Name) (Printed Name) (Printed aVame) DATE DATE DATE C CO21647 ( 305- 59-5269 ( PO Box 1706 Key West,FL 33041 I www.marino-construction.com