2nd Change Order 05/10/2022
M ONROE C OUNTY/E NGINEERING/ P ROJECT M ANAGEMENT
C ONTRACT C HANGE O RDER
This change order is a time extension only request by the contractor to add 90 days to the construction
schedule due to engineering plan delays and to resolve concrete discrepancies. The new substantial
completion date will be changed to July 13, 2022.
Change order is 0% of original contract price.
5/3/2022
Ejhjubmmz!tjhofe!cz!Dbsz!Lojhiu!
Dbsz!Lojhiu
Ebuf;!3133/16/21!1:;65;68!.15(11(
Lfwjo!H/!Xjmtpo-!Q/F/!
3133/16/21!23;65;18!.15(11(
Delays in plan review and concrete issues necessitated a contract extension.
No architect on project.
April 14, 2022
Attn:Tom Henry
Monroe County PWD
1100 Simonton St
Key West, FL 33040
Re: Big Pine Sheriff House Replacement
Subject: Time Extension
Dear Mr. Henry,
Sea Tech is requesting a ninety (90) day no cost time extension to our contract. We have
had delays due toengineering changes for the building permit approval and delays with the
resolving the concrete discrepancies. This will result in a July 13, 2022 substantial completion
date.
Sea Tech has every intention of accelerating the work progress to reduce the time
indicated on the project schedule. Please advise if you need additional information. I may be
reached at (305) 872-0888.
Sincerely,
Ryon LaChapelle
Project Manager