HomeMy WebLinkAbout3rd Change Order 06/22/2022 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: Bimini Drive Bridge(#904603) Replacement Project CHANGE ORDER NO: 3
INITIATION DATE: 6/1/22
CONTRACT DATE: 12/09/20
REVISED SUBSTANTIAL COMPLETION DATE AS OF THIS CHANGE ORDER 3#: 9/28/22
TO CONTRACTOR:American Empire Builders,Inc.
The Contract is changed as follows:
The original Contract Sum .......................................... $3,190,000.00
Net change by previously authorized Change Orders $540,294.380
The Contract Sum prior to this Change order was.,-. .......... ..$3,730,294.38
The Contract Sum is(not changed)by this Change Order#3..... __ ..........$0
The Contract Sum including this Change Order ...... ........... ... $3,730,294.38
As a result of the contractor completing Change Order No for the temporary bridge strengthening at a cost of
$522,248.00, ninety additional days is added to the contracttime to perform this work.
This change order no. 3 revises the substantial completion date to September 28, 2022 at no additional cost.
Digitally signed by Antonio M
Antonio M Gonzalez cen=ale=
CONTRACTOR ANTONIO M.GONZALEZ Date:2022 06 01 15:44:41 04'DD'
Date
;2�
ENGINEERING SERVICES DIRECTOR' 44�
"
Kevin G.Wilson,P.E. Date
ASSISTANT COUNTY ADMINISTRATO 20 .22 "19-21.
-04'00' Date
MuiONAOE COUNTY AT70RNEYS C"F '
AF''P R0VIED AS TO FORM
TA IT CP UINTYATTORNEY
DATE: 6-16_2022
NN 1% )
June 1, 2022
Mr. Clark Briggs
Monroe County Engineering
1100 Simonton St.Rm 216
Key West, Fl. 33040
Bimini Bridge Project
Subject: Change Order#3 Addition of Contract Time for Bridge Strengthening
Dear Mr. Briggs:
American Empire Bridge has completed the Lump Sum Task to construct the Strengthening of Bimini Bridge. In
conjunction with CO 91 which provided payment to AEB in the amount of$522,248.00, AEB is requesting that 90
contract days is added for the additional work performed.
WSP concurs with this request and recommends that 90 contract days be added to the project schedule for this task.
Sincerely,
WSP
Keith Duke
Project Administrator
cc: PomsitChakkaphakP.E.
(Enclosure)