Loading...
08th Change Order 06/15/2022 MONROE COUNTY/DEPARTMENT OF AIRPORTS CoNTRAcr CHANGE ORDER PROJECT TITLE: Marathon International Airport CHANGE ORDER : 8 Terminal Re-Roof Project INITIATION :April 6,202 TO CONTRACTOR: Marino Construction Group,Inc CONTRACT : March 17,2021 The Contract is changed as follows: The original(Contract Sum)(Guarant d Maximum Price).......................................... $1,888,375.00 Net change by previously authorized Change Orders..................................................$ 0.00 The(Contract Sum) (Guaranteed Maximum Price)prior to this Change order was.............$ 1,888,375.00 The(Contract Sum)(Guaranteed Maximum Price)will be ceadl(decreased) (unchanged)by this Change Order.......$ 0.00 Then (Contract&qumljGuaranteed Maximum Price)including this Change Order is.......$ 1,888,375.00 The Contract Time will be flagpitgt90(decreased)(unchanged)by............................... 0 days The date of Substantial Completion as of the date of this Change Order is....................... July 7,2022 Detailed description of change order and justification: Fabrication 6 mast support steel posts with eye and cable; specs In received plans, welding on location and Installation Included. This change Order is 2.1% of the original contract price. N' � u tl er h to t a �cle a Contr c or Forney, N—�a[4,sgned by Forney Ryan rid'A m-=Forney.Ryan w=Users, r..ARp email=RVan FomeyaAcobs.com 6/10/22 VHIT T: Y n Z 20'n 06101121.04-0400 Date CC Lc CONTRACTOR: �I Date DIRECTOR OF AIRPORTS ��C���'r 6.132022 MONROE COUNTY: n mmi Wµ �06.15.2022 ►sst.ICou�ry � � A� �trator Date NROE COUf'dTy'"ATT0N7 ,°a AOVEC FORM PED, O J CA ASSIST COUNTY ATTORNEY C Date 6/13/22 Change Order Attachment per Monroe County Code Section 2-58(b) a Change Order was not included in the original contract specifications. Yes(X ) No If Yes, explanation: Fabrication of 6 mast support steel posts with eye and cable. Welding on location and installation Included. 0 Change Order was included In the original specifications. Yes No (X) If Yes, explanation of increase in price: 0 Change Order exceeds$50,000 or 5%of contract price(whichever Is greater).Yes No(X) If Yes, explanation as to why it is not subject for a calling for bids: 0 Project architect approves the change order. Yes(X) No If no,explanation of why: 0 Change Order is correcting an error or omission in design document. Yes No (X) Should a claim under the applicable professional liability policy be made? Yes No(X) Explain: xdr%/ ;. WI in,..✓ ..,,,,:.G.l .... i,.w:,,rid II, "PI S.„ i, e i/ ✓e C O N S T R U C T I O N C R 0 U P OWNER: PROJECT: Date:416/22 Monroe Board of County Corrussioners Marathon International Airport t 100 Simonton Street Terminal Rcroof CUD Number:26 Key West,FL 33040 9400 Overseas Highway Marathon,FL 33050 This Contingency Use Directive is for: Fabrication of 6 mast support steel posts with eye and cable.Welding on location and installation included. 1s additional time needed to perform scope changes? S ND Time"Extension 02s s Changes to Contract 699nt General Conditions: S 745.00 Subtotal: S 5,200.00 General Liability- $ 52.00 SubtotaL b 5,997.00 CC Fee: 5 689.66 Subtotal: S 6,696.66 Contractor's Bond S 100.30 Total Proposed Amount: S 6,786,96 Reason forChanges; Changes in scope given by architect or owner for aesthetic and/or design reasons ElChanges resulting from events or circumstances:defective design,owner caused delays,differing site conditions Approved Date: Declined bye Date: Comments: CGCO21 7 1 05-359-5269 1 PO Box 1706 Key West,FL 33041 1 www.morino-constfuction.com ESTI MATE ESTIMATE#040422.2 DATE:APRIL 4,2022 r I 'rr1" M110r1if Jakub Blazek,Owner 5642 3,d Avenue Key West Florida 33040 Phone:305-842-1820 Email:KubiCustom@gmail.com BILL TO: SHIP TO: Marino Construction MARINO CONSTRUCTION Florid Keys Marathon Intematlonal Airport FLORIDA KEYS MARATHON INTERNATIONAL AIRPORT QUANTITY DESCRIPTION UNIT PRICE TOTAL Fabrication 6 mast support steel posts with eye and cable;specs 5,200.00 in received plans,welding on location and installation Included SUBTOTAL ,2 .00 SALES TAX 0.00 SHIPPING&HANDLING 0.00 TOTAL DUE 5,200.00 Estimate Is valid for 15 days.This estimate Is not a contract or a bill,It is our best guess at the total price to complete the work stated above, based upon our Initial Inspection.If prices change or addAlonal parts and labor are required,we will Inform you prior to proceeding with the work Make all checks payable to Jakub Slazek.If you have any questions,contact Jakub Blazek THANK YOU FOR YOUR AUSINESSI