4th Change Order 07/25/2022 NROE COUNTY/ENGINEERING/ PROJECT A4ANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Long Key Transfer Station Building Repairs CHANGE ORDER NO: 04
INITIATION DATE: 07/20/2022
CONTRACT DATE: 04/21/2021
TO CONTRACTOR:
Pedro Falcon Contractors,Inc.
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)......... ......... ......... ......,,, $394,186.00
Net change by previously authorized Change Orders...... ......... —...--. .................. .. $153,475.70
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was....... $547,661.70
The(Contract Sum)(Guaranteed Maximum Price)will be(increased)(decreased)
(unchanged)by this Change Order................... $0.00
The new(Contract Sum)(Guaranteed Maximum Price)including this Change Order is. $547,661.70
The Contract Time will be(increased)(decreased)(unchanged) by.................. 90 days
The date of Substantial Completion as of the date of this Change Order is 8/24/2022
Detailed description of change order and justification:
The Substantial Cora letion shall be extended by 00 calendar days from May 26 2022 to August 24 2022 to
account for material suoplv chain Belays the Contractor is pAperien in .
Chen e Order is 0 of the oftnal contract 12fice.
Not valid until signed by Owner Architect if a licab.121,and Contractor
ARCHITECT: : � .r � ..
F�4 rchite s Inc.In Date
w ,
"Al
CONTRACTOR: � :
"ro Falcon Contractors Date
Digitally signed by Cary Knight
Cary Knight Date:2022.07.25 14:19:54
DEPARTMENT DIRECTOR: -04'00'
Cary Knight Date
Kevin G.Wilson,P.E.
2022.07.25 14:31:52
COUNTY/ASSISTANT ADMINISTRATOR: -04'00'
Roman Gastesi Date
Kevin Wilson
Change Order Attachment per Ordinance No. 024-2015
• Change Order was not included in the original contract specifications. Yes® No❑
If Yes, explanation: Changes in the scope of work already approved on prior change orders have required the
procurement of additional materials for the project Supply chain delays necessitate adding time to the contract.
• Change Order was included in the original specifications. Yes❑ No
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5%of contract price(whichever is greater). Yes❑ No
• Project architect approves the change order. Yes® No❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
From: ke
Sent:VVednexday,July 2O 20228»45AM
Tm: sandero-stexen
Subject: Long Key Building Repairs-Contract Time Extension
~^
CAUTION:This email originated from outside of the County.Whether you know the sender or not,do
not click links or open attachments you were not expecting.
Steve,
Pedro Falcon Contractors, Inc. requests 90-doycontrac1 extension for Long Key Building Repairs as we
try to finalize material procurement and labor scheduling to address the changes 1othe project.
Thanks,
Ken8yg|er
Project Manager
Pedro Falcon Contractors, Inc.
3116O Ave C
Big Pine Key, Florida 33O43
Tel:3OS'872-22OO Ext. 2Q
Ce||:3DS-731-GS7O