09th Change Order 07/26/2022 MONROE CouNTY/DEPARTwNT OF AIRPORTS CONTRACT CHANGE ORDER PROJECT TITLE: Marathon International Airport CHANGE ORDER NO:9 Terminal Re-Roof Project INITIATION DATE. April 20,2022 TO CONTRACTOR. CONTRACT DATE- March 17, 2021 The Contract is changed as follows: The original (Qgn1[jgJ§=)(Guaranteed Maximum Price)...... $1,888,375.00 Net change by previously authorized Change Orders... 0.00 The(Contract unm`i(Guaranteed Maximu rn Price) prior to this Change order was. $1,8 88,37&00 The(Contract Sum)(Guaranteed Maximum Price)will be QagMgj2M(decreased) (unchanged)by this Change Order....._$ The new(Contract Su M)_(Guaranteed Maximum Price) including this Change Order is....... $ 1,888,375.00 The Contract Time will be flng[RilpAl(decreased) (unchanged) by. 40 days The date of Substantial Completion as of the date of this Change Order is..... Detailed description of change order and justification: This change order Is for Final Completion Time Extension#3 requested In order to compile final closeout documents and attain all final Inspections. This change Order is 2.01L06 of the original contract price. Not valid until 211-n:;i '1 11,or rOwnerArc 'if a IlcabIts and Contractor ARCHITECT: %O-AA Foev� E/ 2l Date Jlil ?CONTRACTOR: Marino Construction Group, Inc. ' yDate -1 DIRECTOR OF AIRPORTS 7.20.2022 Date M ONRO COCA 0712612022 L E TY: —Z4'A st lCou n�ty'��d�rrmi n istrato r Date M�NROE COUNTY ATTOtnNEY2 ArkOVE FO 9D&0J._MERCA9G---- � ASSP T 'UNTY ATMRNEY Date— 7/21/22 Change Order Attachment per Monroe County Code Section 2-58(b) • Change Order was not included in the original contract specifications. Yes( X) No( ) If Yes, explanation: This change order is for Final Completion Time Extension#3 requested in order to compile final closeout documents and attain all final inspections. • Change Order was included in the original specifications. Yes ( ) No ( X ) If Yes, explanation of increase in price: • Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes() No(X) If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes(X ) No ( ) If no,explanation of why: • Change Order is correcting an error or omission in design document. Yes ( ) No ( X ) Should a claim under the applicable professional liability policy be made? Yes( ) No ( X ) Explain: