AGENDA ITEM WORDING: Receipt of monthly report on change orders reviewed by the County
Administrator's Office.
ITEM BACKGROUND: There were five change orders considered and approved by the Deputy
Administrator for the period beginning March 1, 2012, and ending March 31, 2012 totaling $19,043.49.
There were no change orders denied.
PREVIOUS RELEVANT BOCC ACTION: On September 9, 1998, Ordinance No. 026-1998 was
adopted in order to provide that the County Administrator may approve separate, non -cumulative
change orders for construction projects and professional service contracts in amounts not to exceed
$25,000.00 or 5% of the original contract price, whichever is greater. The BOCC requested a monthly
report of all change orders considered by the County Administrator.
CONTRACT/AGREEMENT CHANGES: N/A
STAFF RECOMMENDATIONS: NIA
TOTAL COST: N/A Indirect Costs BUDGETED: Yes N/A No —
DIFFERENTIAL OF LOCAL PREFERENCE: N/A
COST TO COUNTY: N/A SOURCE OF FUNDS: N/A
REVENUE PRODUCING: Yes _ No X AMOUNT PER MONTH Year
APPROVED BY: County Atty OMB/Purchasmg
DOCUMENTATION: Included X
DISPOSITION
Revised 7/09
Risk Management
Not Required
AGENDA ITEM #.
ce
LU
a
ce
O
LU
0
Z
«
�
u
w
U
LL.
LL.
O
�
ce
O
�
�
Z
�
�
Q
�
z
.3
O
U
w
�
�
�
�
uj
ce
w
0
�
Z
O
U
N
�
�
m
�
0
N
�
�
0
�
0
�
O
�
LU
IL
LU
�
�
ce
O
LL
c
2
E
_
\
\
2
-0
- GJ
§
cu00
-
\/
�7�;§g
§E
_
3�]s0E�
`
EE
fa
mm§-
=o;65
Qz
- a
�§
2\n=3
>z
e
}_
§§\�\0(\
$
/)
Q
mmtt`23c
=#oE3;oo
20
=Em2e2§g
°°°\//§§\2
�u
/mMEE
12/§12§
LU
O�
^
%
LU Lu
z
ƒ
\
\
\
\
S
.)
§
-
t
f
7
'
E
k
01
ru
E
/
&
ro
/
\
\§\
0
®
to
t
=
2
a
o
q
//
\
>
/
0
#
=
o
2
\}\
k
E
)
\
t)2
0
ky�
)
2
2wk
z
k
�
Iq
§
r,
@
S
$
/
/
k
k
«
�
+
�
#
o
U
@
§§m
+k/
cn
/
»23
U
tea@
/
��kk
a)
0)
/\k
�20a)Ep,
\\O
\0
aj
0OL
q§£
LUfu
.
\&£
z
0
;L
k
@
a
�
�
MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Renovation and Addition of Fire Station #17
In Conch Key
1
TO CONTRACTOR:
Pedro Falcon Electrical Contractors, Inc.
31160 Avenue C
Big Pine Key, FL 33043
The Contract is changed as follows:
CHANGE ORDER NO: 1
INITIATION DATE: March 1, 2012
CONTRACT DATE: September 21, 2011
The original (Contract Sum) (Guaranteed Maximum Price)............................................$1,695,000.00
Net change by previously authorized Change Orders ...................................................$ 0.00
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$1,695,000.00
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order ....... $ 826.88
The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ....... $1,695,826.88
The Contract Time will be (increased) (decreased) (unchanged) by .................................. N/A
The date of Substantial Completion as of the date of this Change Order is..................November 30, 2012
Detailed description of change order and justification:
Re i'acement of the Hot Water Heater
This change Order is 0488% % of the original contract price
ARCHITECT:
William P. Ho ect, P.A.
CONTRACTOR: 0310
Pedro Fa can I—Wrical Contractor's C
DIRECTOR PW/ENGINEERING:
e Wilson Date
DIRECTOR PROJECT MANAGEMENT: - P 2
J A. BA"% / Date
COUNTY/DEPUTY ADMI
Frederick
ti
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not Included in the original contract specifications. Yes ® No ❑
If Yes, explanation:
The Hot Water Heater was discovered leaking after construction began.
• Change Order was included in the original specifications. Yes rl No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes []No
Should a claim under the applicable professional liability policy be made? Yes ❑ No M.
Explain:
Pedro Falcon
Electrical Contractors, Inc.
31160 Avenue C, Big Pine Key, FL 330434516
(305) 872-2200 • Fax (305) 872-2219 • falconelCa'bellsouth.net
CGC1507617 / EC0001491 / EC13003416
Monroe County
Fadllitles Developrnent
MAR 012012
Ttnne:
REC 1 0 BY•
Request for Change Order
01 March 2012
Project: Conch Key Fire Station No. 17
Change Order Request No: One
Description: Replace Existing Water Heater
Pedro Falcon
Field Coordination (2 Hours at
$100.00).......................................................................................$200.00
Atlantic Plumbing of the Keys, Inc.
Proposal Invoice 3288.......................................................................$550.00
Subtotal........................................................................................$750.00
OH&P
Overheadat 5%..........................................................................................................$37.50
Industrial • Commercial • Institutional - Utility
Established 1985
Subtotal........................................................................................$787.50
Profitat 5%.................................................................................................................$39.38
NetAmount of Request for Change Order: ........................................................ $826.88
Additional Time Requested for Change: ................................................ 0 Days
Respectfully Submitted,
Ken Bygler
Project Manager
Atlantic Plumbing of the Keys, Inc.
5585 Second Avenue #1
Key West, FL 33040
305-294-4042 / 305-2944047 fax
atlanticolumbinala)bellsouth.net
Phone # 305-294-4042
Fax # 305-294-4047
Bill To
Pedro Falcon Electrical Contractors, Inc
31160 Avenue C
Big Pine Key, FL 33043
r- Date
Invoice #
12/23/2011
3288
f P.O. No. 1 Due upon receipt I Project
Quantity Description Rate Amount
Labor and material to replace leaky water heater at Conch Key 550.00 550.00
Fire Station.
TOTAL $550.00
All invoices are due upon completion. Any invoice remaining unpaid after 30 days is
subject to 1.5% late charge per month. Customer is responsible for all attorney fees Sales Tax (7.5%) $0.00
and other collection costs.
Total $550.00
Payments/Credits $0.00
Balance Due $550.00
Campo-Abra
From: Campo-Abra
Sent: Friday, March 09, 2012 8:50 AM
To: County Commissioners and Aides
Subject: Change Orders
Attachments: FS #17.pdf; MK Courthouse.pdf
Please review the attached Change Orders submitted by Pedro Falcon Electrical Contractors:
o Change Order #1 for the Renovation and Addition of Fire Station #17
o Change Order #2 for the Marathon Courthouse
Abra Campo
Sr. Administrative Assistant
Office of County Administrator
The Historic Gato Cigar Factory
1100 Simonton Street, Suite 2-205
Key West, FL 33040
Office: 305.292.4441
Fax: 305.292.4544
camoo-abra@monroecounty-fl.ciov
Please consider the environment before printing this email.
PLEASE NOTE: Florida has a very broad public records law. Most written communications to or from the County regarding County
business are public record, available to the public and media upon request. Your e-mail communication may be subject to public
disclosure.
MEMORANDUM
TO: Board of County Commissioners
From: Debbie Frederick
Deputy County Administrator
Date: March 8, 2012
RE: Change Orders
Attached is a proposed change order for Pedro Falcon Electrical Contractors, Inc. for the
Renovation and Addition of Fire Station #17. Change Order #1 is for $826.88 for the
replacement of a hot water heater.
According to Ordinance 026-1998 adopted by the Board of County Commissioners,
proposed change orders are to be presented to members of the Board of County
Commissioners prior to approval, assuming they are within the Administrator's
prescribed limits. Change orders not within the Administrator's authority are placed on
the BOCC agenda.
The Administrator/Deputy Administrator i
March@, 2012.
DLF: adc
M6n d O q
to approve this change order on -Friday;
clC
-Debbie Frederick
Deputy County Administrator
MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Renovation of the Monroe County
Courthouse (Marathon)
TO CONTRACTOR:
The Contract is changed as follows:
CHANGE ORDER NO: 2
INITIATION DATE: February28, 2012
CONTRACT DATE: November 17, 2010
The original (Contract Sum) (Guaranteed Maximum Price)............................................$835,776.00
Net change by previously authorized Change Orders...................................................$165,176.55
The (,.C,ontract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$1,000,951.56
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order ....... $ 11,074.61
The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ....... $1,012,026.16
The Contract Time will be (increased) (decreased) (unchanged) by .................................. N/A
The date of Substantial Completion as of the date of this Change Order is ......................... July 26, 2012
Detailed description of change order and justification:
This change Order is 1 325% of the original contract once
ARCHITECT:
CONTRACTOR:
DIRECTOR PROJECT MANAGEMENT.
DIRECTOR PUBLIC WORKS/E
I
COUNTY/DEPUTY ADMINIS TOR:
Electrical
Gastese/Debbie Frederick
ate
0,J0
Date
'S T-I2
Date
Date
Change Order Attachment per Ordinance No. 004-1999
• Change order was not included in the original contract specifications. Yes ® No ❑
if Yes, explanation: Because of the asbestos remedledon, the Sheriff's magnetometer must be
moved from its current location.
• Change Order was included in the original specifications. Yes [] No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes O No
if Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
if no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ONO
Should a claim under the applicable professional liability policy be made?- Yes O No
Explain:
Pedro Falcon
Electrical Contractors, Inc.
31160 Avenue C, Big Pine Key, FL 330434516
(305)872-2200 -Fax (305)872-2219 -falconel@bellsouth.net
CGC 1507617 / EC 0001491 / EC 13003416
Request for Change Order
28 February 2012
Project: Renovation of the Monroe County Courthouse (Marathon),
Change Order Request No: ??????
Description: Provide Temporary Building for Sherriff's Equipment
Pedro Falcon
Provide 10' W x 16'L x 8'H (Building Size Determined by Size of .Mauow&w, clearances
required for Occupants) Temporary Building for Duration of Project to House Sherriff's
Equipment for the life of the project: Building to have electrical hook-up from existing
building, electrical outlets, plywood interior walls, lights, (2) doors, insulated, A/C Unit
8,000 btu, handicap accessible
BuildingCost................................................................................$8,720.00
Building Set-up & Removal...............................................................$800.00
Electrical Set-up & Removal..............................................................$525.00
Subtotal.................................................................................... $10,045.00
Industrial - Commercial -Institutional - Utility
Established 1985
OH&P
Overheadat 5%................................................................................................$502.25
Subtotal ............................................................................... $10,547.25
Profitat 5%.......................................................................................................$527.36
Exclusions: Permit Fees of any sort
Net Amount of Request for Change Order: ................................................. $11,074.61
Additional Time Requested for Change: To Be Determined Based upon Processing
of this Modification. PFEC currently demobilized and off site per Monroe County
direction.
Respectfully Submitted,
Ken Bygler
Project Manager
Campo-Abra
From: Campo-Abra
Sent: Friday, March 09, 2012 8:50 AM
To: County Commissioners and Aides
Subject: Change Orders
Attachments: FS #17.pdf; MK Courthouse.pdf
Please review the attached Change Orders submitted by Pedro Falcon Electrical Contractors:
o Change Order #1 for the Renovation and Addition of Fire Station #17
o Change Order #2 for the Marathon Courthouse
Abra Campo
Sr. Administrative Assistant
Office of County Administrator
The Historic Gato Cigar Factory
1100 Simonton Street, Suite 2-205
Key West, FL 33040
Office: 305.292.4441
Fax: 305.292.4544
cameo-abra@monroecounty-fl.gov
`A Please consider the environment before printing this email.
PLEASE NOTE: Florida has a very broad public records law. Most written communications to or from the County regarding County
business are public record, available to the public and media upon request. Your e-mail communication may be subject to public
disclosure.
MEMORANDUM
TO:
Board of County Commissioners
From:
Debbie Frederick
Deputy County Administrator
Date:
March 8, 2012
RE:
Change Orders
Attached is a proposed change order for Pedro Falcon Electrical Contractors, Inc. for the
renovation of the Monroe County Courthouse in Marathon. Change Order #2 is for an
increase of $11,074.61 to provide a building for the Sheriff's magnetometer for the life of
the project. The building is to have electrical hook-up, electrical outlets, plywood interior
walls, lights and doors, insulation and an 8,000btu air conditioning unit. The building will
be handicap accessible.
According to Ordinance 026-1998 adopted by the Board of County Commissioners,
proposed change orders are to be presented to members of the Board of County
Commissioners prior to approval, assuming they are within the Administrator's
prescribed limits. Change orders not within the Administrator's authority are placed on
the BOCC agenda. j
(l
The Administrator/Deputy Administrator intends to approve this change order on Fray;
March IS2012.
�"C/c
bie Frederick
Deputy County Administrator
DLF: adc
4,
MONROE COUNTY ENGINEERING
CONTRACT CHANGE ORDER
PROJECT TITLE: No Name Key Bridge Emergency Repairs
CHANGE ORDER NO: 1
INITIATION DATE: 3/9/12
TO CONTRACTOR: CONTRACT DATE: 2/3/12
The Contract is changed as follows:
The original Contract Sum........................................................................$143,000.00
Net change by previously authorized Change Orders ............................................$
0.00
The Contract Sum prior to this Change Order was ........................... ..............$143,000.00
The Contract Sum will be changed by this Change Order....................................$7,142.00
The new Contract Sum including this Change Order is...................................$150,142.00
The Contract Time will be increased by............................................................44
Days
The date of Substantial Completion as of the date of this Change Order is
.............. 4/30/12
Detailed description of Change Order and justification:
As a result of a designed 3 ton weight limit restriction during bridge repairs, life safety and livelihood
concerns were raised by the residents of No Name Key. Additional bridge deck support was required to
eliminate the weight restriction. Time, materials and equipment were increased from the original bid
amount. The following items are included in this Change Order:
Dockage, maintenance of barges and equipment = $ 2,800.00
Additional jacks = $ 644.00
30 days rental on additional jacks = $ 2,340.00
14 days rental on existing jacks = $1,078.00
Shims = $ 280.00
Net Amount of this Change Order = $ 7,142.00
This Change Order is less than 5% of the original contract price.
CONTRACTOR:
oral arine Constru ion Date
D RECTOR: �\ � /��%� Yhlc l
ENGINEERING SERVICES I
Ju th S. Clarke, P.E. Date
PUBLIC WORKS & ENGINEERING DIVISION DI
COUNTY/DEPUTY ADM
19
Date
CORAL MARINE CONS RUCTkON
10610 7TH AVE GULF, MARATHON, FL 33050
Ph: 305-743-0907 Fax: 305-743-0900
March 8, 2012
CHANGE ORDER REQUEST #1
Project: No Name Key Bridge Repair
Monroe County Engineering Department
1100 Simonton Street
Key West, FL 33040
1. Request for time extension on above mentioned project due to delay time as
a result of weight restriction problems on the bridge. We request original
contract be amended to a completion date of April 30, 2012.
2. Due to additional weight restriction compliance as well as a delay in start
time we request additional funds to be added to original contract as follows:
Dockage, Maintenance of Barges and Equipment
14 Days @ $200.00
Additional Jacks
30 Days Rental on Additional Jacks
14 Days Rental on Existing Jacks
Shims
Total Additional Funds Requested
George Steinmetz
Coral Marine Construction, LLC
$ 2,800.00
$ 644.00
$ 2,340.00
$ 1,078.00
$ 280.00
$ 79142.00
MONROE COUNTY PUBLIC WORKS
PROJECT:
Energy Retrofit — Jackson Square
Monroe County
CONTRACTOR:
Electronic System Services, Inc
5840 Halifax Avenue
Fort Myers, Florida 33912
Change Order
CHANGE ORDER NUMBER: 003
DATE: March 8, 2012
PROJECT NUMBER: PWD-236-129-2011
CONTRACT DATE: September 21, 2011
NOTICE TO PROCEED: October 7, 2011
CONTRACT FOR: General Construction
THE CONTRACT IS CHANGED AS FOLLOWS:
Funding was identified by the County Grant Manager for Change Order No. 2 although have been advised
by the County Grant Manager to place Change Order No. 2 on hold until the funding is in place for Change
Order No. 2. In order to provide adequate time for the County Grant Manager to insure funding is in place
for Change Order No. 2 and for the Contractor to procure and install tasks identified in Change Order No.
2, the contract time is hereby extended by (60) sixty days. The contract amount remains the same.
The original Contract Sum was $599,000.00
The net change by previously authorized Change Orders $ 88,700.00
The Contract Sum prior to this Change Order was $599,000.00
The Contract Sum will be changed by this Change Order in the amount of $ 0----------
The new Contract Sum including this Change Order wilp, a $687,700.00
S.sx �� Z"
The Contract Time will be increased by (60) tly days.
The date of Final Completion as of the date of this Change Order therefore, is May 14, 2012.
NOT VALID UNTIL SIGNED BY THE CONTRACTOR AND THE OWNER
Robert A. Stone, MCPw
Owner's Representative
10600 Aviation Blvd.
Marathon. FL 33050
Address
BY (:Signature)
.�A
DAT
Electronic Systems Services. Inc Monroe Cog=. FL
Contractor Owner
5840 Halifax Avenue
Fort Meyers, FL 33912
Address /
dl
1100 Simonton Street
Key West FL 33040
Address ,
DAT
MEMORANDUM
DATE: MARCH 8, 2012
TO: DENT PIERCE, PUBLIC WORKS DIVISION DIRECTOR
FROM: BOB STONE, MIDDLE KEY OPERATIONS DIRECTOR
RE: ENERGY RETROFIT - JACKSON SQUARE
Attached for approval is Change Order No. 3, executed by the Contractor
and myself for the project referenced above. This is a no cost change
order and only extends the final -completion date by sixty days while
still fitting within the time frame established by the Monroe County
Grant Manager.
The change order is needed to provide additional time to insure
placement of State funding and installation of the activities identified
in Change Order No. 2. Funding was identified by the Monroe County
Grant Manager prior to the issuance of Change Order No. 2, although,
have been advised by the Monroe County Grant Manager to place
Change Order No. 2 on hold until the State funding is in place. A
notice to proceed with Change Order No. 2 has not been issued to the
Contractor. Only upon notice by the Monroe County Grant Manager
to proceed with Change Order No. 2 would the scope of work
identified within Change Order No. 2 commence.
Please let me know if there are any questions or more information is
desired.
Campo-Abra
From:
Campo-Abra
Sent:
Tuesday, March 13, 201210:26 AM
To:
County Commissioners and Aides
Subject:
Change Order - Electronic System Services
Attachments:
Electronic System Services.pdf
Please review the attached Change Order #3 submitted by Electronic System Services for the Energy Retrofit Jackson
Square Project.
Abra Campo
Sr. Administrative Assistant
Office of County Administrator
The Historic Gato Cigar Factory
1100 Simonton Street, Suite 2-205
Key West, FL 33040
Office: 305.292.4441
Fax: 305.292.4544
camoo-abra@monroecounty-fl.gov
Please consider the environment before printing this email.
PLEASE NOTE: Florida has a very broad public records law. Most written communications to or from the County regarding County
business are public record, available to the public and media upon request. Your e-mail communication may be subject to public
disclosure.
MEMORANDUM
TO:
Board of County Commissioners
From:
Debbie Frederick
Deputy County Administrator
Date:
March 12, 2012
RE:
Change Orders
Attached is a proposed change order for Electronic System Services, Inc. (Change
Order #3 for the Energy Retrofit Jackson Square project is for a no -cost time extension
of 60 days to insure placement of State funding and installation of the activities identified
in Change Order #2.)
According to Ordinance 026-1998 adopted by the Board of County Commissioners,
proposed change orders are to be presented to members of the Board of County
Commissioners prior to approval, assuming they are within the Administrator's
prescribed limits. Change orders not within the Administrator's authority are placed on
the BOCC agenda. 6�
The Deputy Administrator intends to approve is change order on TCueselay, March 1.3'
2012.
Y-C/C'
-�,.-Debbie Frederick
Deputy County Administrator
DF/ac
_t
MONROE COUNTY PUBLIC WORKS
Change Order
PROJECT: CHANGE ORDER NUMBER: 002
Monroe County, FL — MCSO
Roofing Improvements - DATE: March 15, 2012
Monroe County Detention Center
CONTRACTOR: PROJECT NUMBER: PWD-118-247-2011
Peach State Roofing, Inc. CONTRACT DATE: June 15, 2011
1401 SW 10t' Avenue NOTICE TO PROCEED: July 24, 2011
Pompano Beach, Florida 33069 CONTRACT FOR: General Construction
THE CONTRACT IS CHANGED AS FOLLOWS:
To provide time for obtaining warranty documentation, project closeout and final invoicing, the contract
time is hereby extended by (30) thirty days. Please note that the contract amount has not changed.
The original Contract Sum was $624,200.00
The net change by previously authorized Change Orders $ 0-----
The Contract Sum prior to this Change Order was $624200.00
The Contract Sum will be changed by this Change Order in the amount of so -------
The new Coltract Sum including this Change Order will be $624,200.00
The Contract Time will be increased by (30) thirty days.
The date of Substantial Completion as of the date of this Change Order therefore, is April 18, 2012.
1OI .VAL- 916N'E&9V;TI4E CON R K___C TOK AND tHt UWNVK
Robert A. Stone, MCPw Peach State Roofing.Inc. Monroe County, FL
Owner's Representative C ntr for Owner
10600 Aviation Blvd., Marathon, FL 14 W 1 ' venue 1100 Simonton Street
Marathon, FL 33050 o c FL_330 Key West FL 33040
Address d ress
BY (Signature) BY i a ure) igna ure)
DATE A E DATE
MEMORANDUM
DATE: MARCH 21, 2012
TO: DENT PIERCE, PUBLIC WORKS DIVISION DIRECTOR
FROM: BOB STONE, MIDDLE KEY OPERATIONS DIRECTOR
RE: ROOFING IMPROVEMENTS- MONO RE COUTNY DETENTION
CENTER - STOCK ISLAND
Attached for approval is Change Order No. 2, executed by the Contractor
and myself for the project referenced above. This is a no cost change
order and only extends the substantial completion date by thirty days.
The project is 99% complete and this time extension is requested to
provide for proper closeout and final payment.
Please let me know if there are any questions or more information is
desired.
Campo-Abra
From: Campo-Abra
Sent: Friday, March 23, 2012 11:14 AM
To: County Commissioners and Aides
Subject: Change Order
Attachments: Change Order.pdf
Please review the attached Change Order #2 submitted by Peach State Roofing, Inc. for roofing improvements at the
Monroe County Detention Center. This change order is for a no cost time extension of 30 days to obtain warranty
documentation, project closeout and final invoicing. Details are attached.
Abra Campo
Sr. Administrative Assistant
Office of County Admin'Irator
The Historic Gato Cigar Factory
1100 Simonton Street, Suite 2-205
Key West, FL 33040
Office: 305.292.4441
Fax: 305.292.4544
carnoo-abra@monroecounty-fl.Qov
WA Please consider the environment before printing this email.
PLEASE NOTE: Florida has a very broad public records s law. Most written communications to or from the County regarding County
business are public record, available to the public and media upon request. Your e-mail communication may be subject to public
disclosure.
MEMORANDUM
TO:
Board of County Commissioners
From:
Debbie Frederick
Deputy County Administrator
Date:
March 22, 2012
RE:
Change Orders
Attached is a proposed change order for Peach State Roofing, Inc. for roofing
improvements for the Monroe County Detention Center (Change Order #2 is for a no
cost time extension of 30 days to obtain warranty documentation, project closeout and
final invoicing. As of this change order the date of Substantial Completion will be April
18, 2012.)
According to Ordinance 026-1998 adopted by the Board of County Commissioners,
proposed change orders are to be presented to members of the Board of County
Commissioners prior to approval, assuming they are within the Administrator's
prescribed limits. Change orders not within the Administrator's authority are placed on
the BOCC agenda.
The Administrator/Deputy Administrator inte ds to approve this change order on €fey,
March 22l, 2012.
fh
r
ebbie Frederick
Deputy County Administrator
DLF: adc
M E M O R A N D U M
DATE: March 30, 2012
TO: Belle DeSantis, Deputy Clerk
FROM: Beth Leto, Public Works
RE: CO #2 w/Peach State Roofing, Inc.
Enclosed please find fully -executed original Change Order No. 002 extending contract
time/completion date by thirty (30) days to April 18, 2012, as executed by
Debbie Frederick, Deputy County Administrator, in accordance with Ordinance 026-1998.
Should you have any questions, please feel free to contact me at x4560 or Bob Stone at
x6077.
M.I
cc: Jackie Clynes
Ann Riger
Bob Stone