Item I02 1.2
Coty f � ,�� ,' BOARD OF COUNTY COMMISSIONERS
�� Mayor David Rice,District 4
The Florida Keys � Mayor Pro Tem Craig Cates,District 1
y Michelle Coldiron,District 2
James K.Scholl,District 3
Ij Holly Merrill Raschein,District 5
County Commission Meeting
August 17, 2022
Agenda Item Number: I.2
Agenda Item Summary #10883
BULK ITEM: No DEPARTMENT: Airports
TIME APPROXIMATE: STAFF CONTACT: Richard Strickland(305) 809-5200
N/A
AGENDA ITEM WORDING: Ratification and approval of Amendment No. 2 to State of Florida
Department of Transportation Public Transportation (PTGA) Grant Agreement Number G2090, as
executed by the Director of Airports, providing $6,157,371.00 in funding for the Concourse A
Terminal Expansion Program at the Key West International Airport; requires a 50% match from the
anticipated 2022 Airport Bond Funds.
ITEM BACKGROUND: This grant is for programming, design,permitting and construction.
Amendment 2 provides additional funding the Terminal Concourse A project.
PREVIOUS RELEVANT BOCC ACTION: Approval of original grant contract G2090 on
October 20, 2021, and Amendment 41 on Mach 16, 2022. On September 15, 2021, the BOCC
adopted Resolution No. 288-2021 authorizing the Director of Airports to execute FAA and FDOT
Airport grants as received to meet deadlines for returning grants to the granting agency and expedite
use of grant funds, with grants to be ratified by the BOCC at the next available regularly scheduled
commission meeting.
CONTRACT/AGREEMENT CHANGES:
Adds an additional $6,157,371 in funding
STAFF RECOMMENDATION: Approval
DOCUMENTATION:
447911-1-94-01 - G2090 - APTGA 42
FINANCIAL IMPACT:
Effective Date: October 20, 2021
Expiration Date: December 31, 2026
Packet Pg. 1915
1.2
Total Dollar Value of Contract: $6,157,371.00
Total Cost to County: 0
Current Year Portion:
Budgeted: Yes
Source of Funds: 50% FDOT/50% 2022 Airport Bond Funds
CPI:
Indirect Costs:
Estimated Ongoing Costs Not Included in above dollar amounts:
Revenue Producing: No If yes, amount:
Grant: $6,157,371.00 (50% Match)
County Match:
Insurance Required: No
Additional Details:
REVIEWED BY:
Beth Leto Completed 07/26/2022 5:22 PM
Richard Strickland Completed 07/27/2022 12:51 PM
Pedro Mercado Completed 07/27/2022 2:38 PM
Purchasing Completed 07/27/2022 2:52 PM
Budget and Finance Completed 07/28/2022 8:26 AM
Brian Bradley Completed 07/29/2022 3:57 PM
Lindsey Ballard Completed 08/01/2022 8:52 AM
Board of County Commissioners Pending 08/17/2022 9:00 AM
Packet Pg. 1916
1.2.a
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION Form 725-000-03
PUBLIC TRANSPORTATION STRATEGIC
DEVELOPMENT
AMENDMENT TO THE PUBLIC TRANSPORTATION OGC04/22
GRANT AGREEMENT
Financial Project Number(s): Fund(s): DDR,DPTO FLAIR Category: 088719
(item-segment-phase-sequence)
447911-1-94-01 Work Activity Code/Function: 215 Object Code: 751000
Federal Number/Federal Award Org. Code: 55062020629
Identification Number(FAIN)—Transit only: N/A Vendor Number: VF596000749053
Contract Number: G2090 Federal Award Date: N/A Amendment No.: 2
CFDA Number: N/A SAM/UEI Number:
CFDA Title: N/A
CSFA Number: 55.004 c�
CSFA Title: Aviation Grant Program
0
U
c14
THIS AMENDMENT TO THE PUBLIC TRANSPORTATION GRANT AGREEMENT("Amendment") is made and entered
into on by and between the State of Florida, Department of Transportation
("Department"), and Monroe County Airports, ("Agency"),collectively referred to as the "Parties."
RECITALSCN
WHEREAS, the Department and the Agency on 10/20/2021 (date original Agreement entered) entered into a Public
Transportation Grant Agreement ("Agreement"). i
cN
WHEREAS, the Parties have agreed to modify the Agreement on the terms and conditions set forth herein.
NOW THEREFORE, in consideration of the mutual covenants in this Amendment, the Agreement is amended as cN
follows:
1. Amendment Description. The project is amended to add FY23 funding.
2. Program Area. For identification purposes only, this Agreement is implemented as part of the Department
ro ram area selected below select all programs that apply):
p 9 ( p 9cN
X Aviation
T-
Seaports
Transit
Intermodal
T-
Rail Crossing Closure T,
Match to Direct Federal Funding (Aviation or Transit)
(Note: Section 15 and Exhibit G do not apply to federally matched funding)
Other
E
3. Exhibits. The following Exhibits are updated, attached, and incorporated into this Agreement:
X Exhibit A: Project Description and Responsibilities
X Exhibit B: Schedule of Financial Assistance
_ *Exhibit B1: Deferred Reimbursement Financial Provisions
*Exhibit B2: Advance Payment Financial Provisions
_ *Exhibit C: Terms and Conditions of Construction
X Exhibit D: Agency Resolution
— Exhibit E: Program Specific Terms and Conditions
— Exhibit F: Contract Payment Requirements
X *Exhibit G: Financial Assistance (Single Audit Act)
— *Exhibit H: Audit Requirements for Awards of Federal Financial Assistance
— *Additional Exhibit(s):
Packet Pg. 1917
1.2.a
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION Form 725-000-03
PUBLIC TRANSPORTATION STRATEGIC
DEVELOPMENT
AMENDMENT TO THE PUBLIC TRANSPORTATION OGC04/22
GRANT AGREEMENT
4. Project Cost.
The estimated total cost of the Project is X increased/_ decreased by$12,314,742 bringing the revised total
cost of the project to$19,788,742.
The Department's participation is X increased/ _ decreased by _$6,157,371. The Department agrees to
participate in the Project cost up to the maximum amount of $9,894,371, and, additionally the Department's
participation in the Project shall not exceed 50.00% of the total eligible cost of the Project. U
cN
Except as modified,amended,or changed by this Amendment, all of the terms and conditions of the Agreement and any E
amendments thereto shall remain in full force and effect.
cN
IN WITNESS WHEREOF, the Parties have executed this Amendment on the day and year written above. c�i
AGENCY Monroe County Airports STATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION
c14
00
110 CL
By: Sy: .
Name: Richard Strickland Name: Daniel Iglesias c,
Title: Director of Airports Title: Director of Trans ortation Development cN
RO CU, °
P D OTATE OF FLORIDA, DEPARTMENT OF TRANSPORTATION '
P AS813 Legal Review:Alicia Tru'illo
At�T ADO EDEiO J. ERC
mm
,
Date MT
c�
Packet Pg. 1918
1.2.a
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION Form 725-000-02
PUBLIC TRANSPORTATION STRATEGIC
DEVELOPMENT
GRANT AGREEMENT EXHIBITS OGC03/22
EXHIBIT A
Project Description and Responsibilities
A. Project Description (description of Agency's project to provide context, description of project components funded
via this Agreement (if not the entire project)): Key West Int'I Airport Terminal Concourse A
B. Project Location (limits, city, county, map): Key West International Airport/Key West, FL/Monroe
c�
C. Project Scope (allowable costs: describe project components, improvement type/service type, approximate
timeline, project schedule, project size): The terminal expansion program at Key West International Airport will include U
programming, design, permitting, financing, and construction. The expansion program is comprised of several cN
elements to improve the level of service to its' passengers and tenants. The program elements may include but not
limited to: a new second-level Concourse A of approximately 48,000 square feet, expansion program of additional E
baggage make up areas and devices, airline ramp/office spaces, ramp equipment storage areas and an additional bag
claim device; an expanded security checkpoint with area to support up to 4 lanes and added support spaces, a new
extended passenger bridge located post security will connect the existing terminal building with the new Concourse, a cN
new pedestrian bridge for public access to airport administration offices, passenger boarding jet bridges, airline
ticketing space, airline office space and baggage system space and systems; an expanded rent-a-car facility area and
baggage service offices.
I
D. Deliverable(s): The terminal expansion program at Key West International Airport will include cN
programming, design, permitting, financing, and construction. The expansion program is comprised of several
elements to improve the level of service to its' passengers and tenants. The program elements may include but not
limited to: a new second-level Concourse A of approximately 48,000 square feet, expansion program of additional cN
baggage make up areas and devices, airline ramp/office spaces, ramp equipment storage areas and an additional bag
claim device; an expanded security checkpoint with area to support up to 4 lanes and added support spaces, a new
extended passenger bridge located post security will connect the existing terminal building with the new Concourse, a
new pedestrian bridge for public access to airport administration offices, passenger boarding jet bridges, airline
ticketing space, airline office space and baggage system space and systems; an expanded rent-a-car facility area and
baggage service offices.
cN
The project scope identifies the ultimate project deliverables. Deliverables for requisition, payment and invoice
purposes will be the incremental progress made toward completion of project scope elements. Supporting
documentation will be quantifiable, measurable, and verifiable, to allow for a determination of the amount of
incremental progress that has been made, and provide evidence that the payment requested is commensurate with
the accomplished incremental progress and costs incurred by the Agency.
E. Unallowable Costs (including but not limited to):
F. Transit Operating Grant Requirements (Transit Only): E
c�
Transit Operating Grants billed as an operational subsidy will require an expenditure detail report from the Agency that
matches the invoice period. The expenditure detail, along with the progress report, will be the required deliverables for
Transit Operating Grants. Operating grants may be issued for a term not to exceed three years from execution. The
original grant agreement will include funding for year one. Funding for years two and three will be added by
amendment as long as the grantee has submitted all invoices on schedule and the project deliverables for the year
have been met.
Packet Pg. 1919
x N
� 00
d
Xr,L All,
�" r IRum�NUNtu � (d�
1
i 0 cm
J � JIB
r-
1
77
r
u
�F�,Y,
u
IG ��
�u
� r
00
op
1 1
PY wl
ryM�� l
ra lip
i
I I
1.2.a
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION Form 725-000-02
PUBLIC TRANSPORTATION STRATEGIC
DEVELOPMENT
GRANT AGREEMENT EXHIBITS OGC03/22
EXHIBIT B
Schedule of Financial Assistance
FUNDS AWARDED TO THE AGENCY AND REQUIRED MATCHING FUNDS PURSUANT TO THIS AGREEMENT
CONSIST OF THE FOLLOWING:
A. Fund Type and Fiscal Year:
Financial FLAIR State Object CSFA/ CSFA/CFDA Title or
Management Fund Category Fiscal Code CFDA Funding Source Funding
Number Type Year Number Description Amount U
447911-1-94-01 DDR 088719 2023 751000 55.004 Aviation Grant Program $1,232,695.0 c,4
447911-1-94-01 DPTO 088719 2023 751000 55.004 Aviation Grant Program $4,924,676.0
447911-1-94-01 DPTO 088719 2022 751000 55.004 Aviation Grant Program $2,737,000.0
447911-1-94-01 DPTO 088719 2022 751000 55.004 Aviation Grant Program $1,000,000.0 c14
447911-1-94-01 LF 088719 2023 751000 55.004 Aviation Grant Program $6,157,371.0
447911-1-94-01 LF 088719 2022 751000 55.004 Aviation Grant Program $2,737,000.0 1
c14
447911-1-94-01 LF 088719 2022 751000 55.004 Aviation Grant Program $1,000,000.0
Total Financial Assistance $19,788,742.0 >-
c14
B. Estimate of Project Costs by Grant Phase:
Phases* State Local Federal Totals State Local Feder;
Land Acquisition $0.00 $0.00 $0.00 $0.00 0.00 0.00 O.0
Planning $0.00 $0.00 $0.00 $0.00 0.00 0.00 O.0 64
Environmental/Design/Construction $9,894,371.00 $9,894,371.00 $0.00 $19,788,742.0 50.00 50.00 O.0
0
Capital Equipment/Preventative $0.00 $0.00 $0.00 $0.00 0.00 0.00 O.0
Maintenance
Match to Direct Federal Funding $0.00 $0.00 $0.00 $0.00 0.00 0.00 O.0
Mobility Management $0.00 $0.00 $0.00 $0.00 0.00 0.00 O.0
Transit Only)
Totals $9,894,371.00 $9,894,371.00 $0.00 $19,788,742.0 a
0)
0
*Shifting items between these grant phases requires execution of an Amendment to the Public Transportation Grant
Agreement.
BUDGET/COST ANALYSIS CERTIFICATION AS REQUIRED BY SECTION 216.3475, FLORIDA STATUTES:
I certify that the cost for each line item budget category (grant phase) has been evaluated and determined to be
allowable, reasonable, and necessary as required by Section 216.3475, Florida Statutes. Documentation is on file
evidencing the methodology used and the conclusions reached.
Ingrid Munoz
Department Grant Manager Name
Signature Date
Packet Pg. 1921
1.2.a
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION Form 725-000-02
PUBLIC TRANSPORTATION STRATEGIC
DEVELOPMENT
GRANT AGREEMENT EXHIBITS OGC03/22
EXHIBIT D
AGENCY RESOLUTION
PLEASE SEE ATTACHED
c�
0
u
c14
c14
1
c14
c14
c14
E
u
Packet Pg. 1922
1.2.a
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION Form 725-000-02
PUBLIC TRANSPORTATION STRATEGIC
DEVELOPMENT
GRANT AGREEMENT EXHIBITS OGC03/22
EXHIBIT G
AUDIT REQUIREMENTS FOR AWARDS OF STATE FINANCIAL ASSISTANCE
THE STATE RESOURCES AWARDED PURSUANT TO THIS AGREEMENT CONSIST OF THE FOLLOWING:
SUBJECT TO SECTION 215.97, FLORIDA STATUTES:—
Awarding Agency: Florida Department of Transportation t0
State Project Title: Aviation Grant Program cN
CSFA Number: 55.004
*Award Amount: $9,894,371
*The award amount may change with amendments s
cN
Specific project information for CSFA Number 55.004 is provided at: Ih tp. „p,p ,;;f.r �,,,gp -, /�eardhcalalo asx
COMPLIANCE REQUIREMENTS APPLICABLE TO STATE RESOURCES AWARDED PURSUANT TO THIS
CN
AGREEMENT:
State Project Compliance Requirements for CSFA Number 55.004 are provided at:
CN
l.:k:t.p. ... ..p.lp.�.::.f:Ej.t�..::q i rm/f F /lea r lh_Cp i�:S.l�?.Il ii i ce..,. .�..p
The State Projects Compliance Supplement is provided at: I „ktp. „p,p ,flrj..,,gp ePi2l allii i ge, p
cN
c�
Packet Pg. 1923
To:Ingrid.Munoz@dot.state.fl.us
FLORIDA DEPARTMENT OF TRANSPORTATION
FUNDS APPROVAL
G2090
7/21/2022
CONTRACT INFORMATION
Contrast: G2090
Contrast Type: GD-GRANT DISBURSEMENT(GRANT)
Method of Procurement, G-GOVERMENTAL AGENCY(287.057,F.S.)
Vendor Name: MONROE COUNTY BOCC c�
Ve0dorlD: F596000749053 0
t)
cN
Beginning Date of This Agreement, 10/20/2021
Ending Dete ofThis Agreement, 12/31/2026
ContradtToW/Budgetary Ceding:, ct=$9,894,371.00
Description: Key West International Terminal Concourse A cN
FUNDS APPROVAL INFORMATION
FUNDS APPROVED/REVIEWED FOR ROBIN M. NAITOVE, CPA, COMPTROLLER ON 7/21/2022 l
cN
Action: Supplemental
Reviewed,or,Approved: APPROVED
cN
Organization Code: 55062020629
Expansion Option: A9
Object Code: 751000
Amount: $6,157,371.00
Financial Project: 44791119401 c14
Work Activlty(FCT): 215
e�
CFDA:
Fiscal Year: 2023
Budget Entity: 55100100
Category/Category Year: 088719/23
Amendment ID: S002
E
Sequence: 00
User Assigned ID A2
Eric Line(6s)/Status 0003/04
Total Amount: $6,157,371.00